NEWS RELEASE: High-Speed Rail Authority Issues Draft 2026 Business Plan for Public Review and Comment

Streamlining efforts cut Phase 1 costs by $1.7 billion, delivering high-speed rail faster and more efficiently

February 28, 2026

您需要了解什麼: The Authority’s Draft 2026 Business Plan lays out a clear plan to connect key regions of California by right-sizing the high-speed rail project to deliver service as quickly and economically as possible. Throughout construction, the California High-Speed Rail has created more than 16,400 good-paying construction jobs and generated nearly $25 billion in economic impact and growth across the state.

加利福尼亞州薩克拉門托—— The California High-Speed Rail Authority (Authority) today issued its Draft 2026 Business Plan for 60-day public review and comment. The overall projected cost for Phase 1 delivery, between San Francisco and Los Angeles/Anaheim, dropped by $1.7 billion due to streamlining efforts aimed at making high-speed trains a reality as quickly and economically as possible.

Through partnerships, proposed private financing, and legislative changes, the Authority has laid out a clear, cost-effective approach to taking travelers from San Francisco to Los Angeles. The Authority also envisions creating new revenue streams through real estate development, ancillary projects, and initial fare service that will help pay for the delivery of transformative transportation.

Tom Richards, Chair

“The Draft 2026 Business Plan sets out the path forward: completion of Merced to Bakersfield, expansion to major population centers for revenue positive service, and early asset commercialization to produce additional revenue to build out high-speed rail. It explains how we build from progress underway, prioritize investments that produce early and durable commercial benefits, and create the conditions for long-term financial strength and private-sector participation as the system expands.”

Authority Board Chair Tom Richards

Based on proven global best practices for development of high-speed rail, the Draft Business Plan includes policies and implementation tools that would help speed the delivery of high-speed rail.

The Authority is providing the following options for submitting comments on the draft Business Plan. The comment period is from February 28 through April 29. There are four ways to provide comment:

  • Online comment form at: 2026 Draft Business Plan Comment Form
  • 通過電子郵件: BusinessPlan2026@hsr.ca.gov
  • By U.S. mail to the Authority: California High-Speed Rail Authority Attn: Draft 2026 Business Plan 770 L Street, Suite 1180, Sacramento, CA 95814
  • At the March 4, 2026, Board of Directors meeting during the public comment section.

高鐵進展

Work continues daily on the high-speed rail project, with 171 miles currently under design and construction from Merced to Bakersfield. Nearly 80 miles of guideway are complete, along with nearly 60 fully completed major structures, and 29 more structures underway across Madera, Fresno, Kings and Tulare counties.

該項目繼續在全州範圍內推進,舊金山至洛杉磯/阿納海姆 494 英里長的系統中的 463 英里已完全完成環境清理並準備施工。

Since construction began, the project has created more than 16,400 good-paying jobs—most filled by Central Valley residents. Up to 1,700 workers report to high-speed rail construction sites each day.

buildhsr.com for more on construction updates and progress.

如有要求,可提供西班牙語採訪。欲了解更多信息,請聯繫管理局媒體關係辦公室: news@hsr.ca.gov.

Se ofrecen entrevistas en Español bajo solicitud。如需獲取更多信息,請聯繫電子通訊媒體關係辦公室: news@hsr.ca.gov.

以下鏈接包含最近的視頻、動畫、攝影、新聞中心資源和最新效果圖: https://hsra.box.com/v/ca-hsr-media-resources。所有文件均由加州高速鐵路管理局免費提供。

更快建立更多內容

高速鐵路是紐森州長任期內的一個重要組成部分 更快建立更多內容 議程,升級基礎設施並在全州範圍內創造就業機會。發現更多: 加州政府建網站

 

演說局

加州高速鐵路管理局發言人局由通訊辦公室管理,提供有關高速鐵路計劃的信息演示。

請求演講者

接觸

丹妮拉·孔特雷拉斯
916-719-4976 (c)
Daniela.Contreras@hsr.ca.gov

 

媒體查詢

各個領域都需要。

加利福尼亞州高鐵管理局盡一切努力確保網站及其內容符合加利福尼亞州規定的Web內容可訪問性指南2.0級AA標準所規定的ADA規定。如果您要查找不在加利福尼亞高速鐵路管理局網站上的特定文件,則可以通過“公共記錄法”頁面根據“公共記錄法”來請求該文件。如果您對網站或其內容有任何疑問,請通過以下方式與管理局聯繫: info@hsr.ca.gov.