تقرير الرئيس التنفيذي

Brian P. Kelly, CEO11 أبريل 2024


تحديثات البرنامج |Procurement Packaging Update | Networking Fair and Industry Update |المواد ذات الصلة |


تحديثات البرنامج

  • Arcadis Contract Extension
  • التبرير:
    • Arcadis has the Project Construction Manager contract for CP 2-3, and the prior end-date for this contract was March 31, 2024. This contract amendment to increase the budget and extend the contract duration allows Arcadis to continue providing the critical expertise and resources needed by the Authority to continue advancing the completion of CP 2-3. Without the approval of this request, the Authority would not have the services in place beyond March 31, 2024.
  • مجال العمل:
    •  No change to the scope of work. Increase in budget and extends contract to September 30, 2025.
  • كلفة:
    • $75,000,000

PROCUREMENT PACKAGING UPDATE

  • Anticipated Fall 2024:
    • Progressive Design-Build Traction Power System
    • Progressive Design-Build Rail Train Control and Communications System
    • Anticipated Winter 2024/2025:
      • CM/GC Construction of Track and OCS
    • Draft documents will be available for industry review prior to advertisement of these procurements
    • Additional contracts, including Independent Cost Estimator, Integration Support, Facilities Design, Construction Management for the track and systems contracts, construction of civil infrastructure for Merced and Bakersfield extension project sections, and Construction Management, will be issued as those services are needed
  • Additional information available at the May 7, 2024, HSR Small Business Fast-Track Networking Fair & Industry Update

Networking Fair and Industry Update

7 مايو 2024

9:00 صباحًا إلى 2:00 ظهرًا

DGS زقورة

707 الشارع الثالث

West Sacramento, CA 95650

  • Event will provide small businesses an opportunity to connect with HSR prime contractors and consultants and learn about contracting and procurement opportunities in California
  • Contracting opportunities and procurement updates to be discussed include:
    • Upcoming RFP and RFQ schedule
    • المسار والأنظمة
    • Merced and Bakersfield extensions
    • Station and facility design
    • Design and construction of traction power system, including solar and battery energy storage systems

مواد ذات صلة

Board of directors

قرارات مجلس الإدارة

عرض قرارات مجلس الإدارة

اتصال

سكرتير مجلس الإدارة
(916) 324-1541
boardmembers@hsr.ca.gov

تبذل هيئة السكك الحديدية عالية السرعة في كاليفورنيا قصارى جهدها للتأكد من أن موقع الويب ومحتوياته تفي بمتطلبات ADA الإلزامية وفقًا لإرشادات الوصول إلى محتوى الويب 2.0 Level AA من ولاية كاليفورنيا. إذا كنت تبحث عن مستند معين غير موجود على موقع هيئة السكك الحديدية عالية السرعة في كاليفورنيا ، فيمكنك تقديم طلب للحصول على المستند بموجب قانون السجلات العامة من خلال صفحة قانون السجلات العامة. إذا كان لديك أي أسئلة حول الموقع أو محتوياته ، يرجى الاتصال بالهيئة على info@hsr.ca.gov.