CEO Report

Brian P. Kelly, CEOApril 11, 2024


Program Updates |Procurement Packaging Update | Networking Fair and Industry Update |Relevant Materials |


PROGRAM UPDATES

  • Arcadis Contract Extension
  • Justification:
    • Arcadis has the Project Construction Manager contract for CP 2-3, and the prior end-date for this contract was March 31, 2024. This contract amendment to increase the budget and extend the contract duration allows Arcadis to continue providing the critical expertise and resources needed by the Authority to continue advancing the completion of CP 2-3. Without the approval of this request, the Authority would not have the services in place beyond March 31, 2024.
  • Scope of Work:
    •  No change to the scope of work. Increase in budget and extends contract to September 30, 2025.
  • Cost:
    • $75,000,000

PROCUREMENT PACKAGING UPDATE

  • Anticipated Fall 2024:
    • Progressive Design-Build Traction Power System
    • Progressive Design-Build Rail Train Control and Communications System
    • Anticipated Winter 2024/2025:
      • CM/GC Construction of Track and OCS
    • Draft documents will be available for industry review prior to advertisement of these procurements
    • Additional contracts, including Independent Cost Estimator, Integration Support, Facilities Design, Construction Management for the track and systems contracts, construction of civil infrastructure for Merced and Bakersfield extension project sections, and Construction Management, will be issued as those services are needed
  • Additional information available at the May 7, 2024, HSR Small Business Fast-Track Networking Fair & Industry Update

Networking Fair and Industry Update

May 7, 2024

9:00 a.m. to 2:00 p.m.

DGS Ziggurat

707 3rd Street

West Sacramento, CA 95650

  • Event will provide small businesses an opportunity to connect with HSR prime contractors and consultants and learn about contracting and procurement opportunities in California
  • Contracting opportunities and procurement updates to be discussed include:
    • Upcoming RFP and RFQ schedule
    • Track and Systems
    • Merced and Bakersfield extensions
    • Station and facility design
    • Design and construction of traction power system, including solar and battery energy storage systems

RELATED MATERIALS

Board of directors

Board Resolutions

View the Board Resolutions

Contact

Board of Directors Secretary
(916) 324-1541
boardmembers@hsr.ca.gov

The California High-Speed Rail Authority makes every effort to ensure the website and its contents meet mandated ADA requirements as per the California State mandated Web Content Accessibility Guidelines 2.0 Level AA standard. If you are looking for a particular document not located on the California High-Speed Rail Authority website, you may make a request for the document under the Public Records Act through the Public Records Act page. If you have any questions about the website or its contents, please contact the Authority at info@hsr.ca.gov.