The California High-Speed Rail Authority (Authority) anticipates issuing two Requests for Qualifications (RFQ) to procure two contracts for Right-of-Way Engineering and Survey Support Services (ROWE) (Merced to Bakersfield ROWE I and ROWE II)

範囲 – 期間 – 予算
The procurements will result in two contracts with scopes of work that provide personnel and expertise to prepare Right-of-Way (ROW) appraisal maps, legal descriptions, land surveying, staking, monumentation, record maps, exhibits to support ROW acquisition and/or RON packages, and other required services. The geographic scope for the services will be located in the 171-mile Merced to Bakersfield segment in the Central Valley.
The resulting contracts will both have durations up to 4 years and not-to-exceed amounts of $10 million.

スケジュール
The anticipated schedules for these procurements are as follows:

  • RFQ Release Dates: April 2025 (ROWE I) and May 2025 (ROWE II)
  • Virtual Pre-Bid Conference and Small Business Workshop: May 2025 (ROWE I) and (ROWE II)
    • To register for the pre-bid meeting go to the event website: Link to come.
  • Statements of Qualifications (SOQ) Due Dates: June 2025 (ROWE I) and July 2025 (ROWE II)
  • Notice of Proposed Award Dates: July 2025 (ROWE I) and August 2025 (ROWE II)
  • Contract Execution and Notice to Proceed Dates: August 2025 (ROWE I) and September 2025 (ROWE II)

アクセス
The RFQs will be available to download from the California State Contracts Register (CSCR). Updates, including responses to written questions and any RFQ addenda, will be provided on the CSCR.

当局にアクセスしてください 中小企業プログラムのウェブページ プログラムの概要、認定資格、認定資格の取得方法、ベンダーレジストリへのアクセスなどの情報。

利益相反
IMPORTANT NOTICE: Offerors with existing ROWE contracts and/or Offerors who intend to submit SOQs on both RFQs, are required to submit a request for an organizational conflict of interest (OCOI). Failure to submit an OCOI prior to submittal of an SOQ may delay the contract award.

If you have questions about a potential organizational conflict of interest, please submit questions and/or a request for an Organizational Conflict of Interest determination to the Authority’s Chief Counsel at 法律関連、そしてタウニャ・サザン、 メールアドレス referencing the applicable Right of Way Engineering and Survey Support Services (Merced to Bakersfield ROWE I and/or ROWE II) RFQs.

質問
Questions regarding this procurement should be submitted to Chris Rice(for ROWE I) and Gordon Miyauchi (for ROWE II) at ROWE@hsr.ca.gov または(916)324-1541。