California High-Speed Rail Change Orders — Updated July 1, 2020
PROJECT CONTRACT NO. CHANGE ORDER NO. APPROVED DATE CONTRACTOR CATEGORY TITLE AMOUNT ($) DESCRIPTION AUTHORITY APPROVER CONTRACTOR COUNTERPARTY CONSULTANT SUPPORT
CP 1 HSR 13-06 324 5/29/2020 Tutor Perini/Zachry/Parsons Differing Site Conditions Additional Labor and Equipment Cost for Installation of 16" COF Waterline Across Shaw Avenue Open Trench Installation $520,652.00 This is a change to a contract for construction services in the Central Valley. The reason for the change is to compensate the Contractor for the additional construction costs to proceed with the open trench installation of the waterline across Shaw Avenue under night time road closure in lieu of shifting traffic onto the Shaw detour due to delays in other utility relocations and subsequent availability of Right of Way. Garth Fernandez - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 330 5/26/2020 Tutor Perini/Zachry/Parsons Additional Scope Temporary Relocation of Herndon Yard Materials and Fencing for Fresno Metropolitan Flood Control District Construction Activities $422,860.72 This is a change to a contract for the construction services in the Central Valley. The reason for the change is to compensate the Contractor to relocate portions of the Contractor's Herndon storage yard and fencing in order to accommodate a 35-inch temporary construction easement for Fresno Metropolitan Flood Control District to construct a new drain from Golden State Boulevard to Basin EH per Authority requests. Garth Fernandez - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 329 5/26/2020 Tutor Perini/Zachry/Parsons Budget Adjustment Increase the Amount of the Construction Contract Work Provisional Sum $500,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to increase the amount of Construction Contract Work "Provisional Sums" as defined in the Contract to compensate the Contractor for Construction Contract Work. Garth Fernandez - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 328 5/26/2020 Tutor Perini/Zachry/Parsons Budget Adjustment Increase the Amount of the Utility Provisional Sum $2,500,000.00 This is a change to a contract for design and construction services for the Central Valley. The reason for the change is to increase the amount of the Utility "Provisional Sums" as defined by the Contract to compensate the Contractor for utility work. Garth Fernandez - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 327 5/26/2020 Tutor Perini/Zachry/Parsons Other FB-10-0233 Credit for Additional Demolition and Building Board-up on Excess Land ($16,707.10) This is a change to a contract for construction services in the Central Valley. The reason for the change is to credit the Authority for demolition work that was not performed and compensate the Contractor for incurred costs to board-up two buildings and perform asbestos testing in one of the buildings at parcel FB-10-0233. Garth Fernandez - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 321 5/26/2020 Tutor Perini/Zachry/Parsons Third party Requirements Belmont Switch 60% Revisions - Design $30,187.00 This is a change to a contract for design services in the Central Valley. The reason for this change is to compensate the Contractor for the design costs for revising the vertical alignment of Union Pacific Rail Road track 731 per design review comments to the 60% design of the Belmont Switch Relocation Package. Garth Fernandez - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 319 5/26/2020 Tutor Perini/Zachry/Parsons Third party Improvements Painting of Overhead Sign Structure at SR-180 - Construction $7,799.00 This is a change to a contract for construction services in the Central Valley. The reason for this change is to compensate the Contractor for painting an overhead sign structure at SR-180 as requested by Caltrans. Garth Fernandez - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 313 5/26/2020 Tutor Perini/Zachry/Parsons Third party Improvements Reinforced Concrete Pipe Casing or Restrained Joints for Union Pacific Railroad - Construction $261,880.00 This is a change to a contract for construction services in the Central Valley. The reason for the change is to compensate the Contractor for construction costs for the installation of restrained joints on drainage pipes at eleven locations as required by Union Pacific Rail Road and directed by the Authority via Directive Letter 0171 R1. Garth Fernandez - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 309 5/26/2020 Tutor Perini/Zachry/Parsons Additional Scope Caltrans 2-Mile Section - Design $1,000,000.00 This is a change to a contract for design in the Central Valley. The reason for the change is for the advanced payment towards completion of the design of the Caltrans 2-mile guide way portion along SR-99 which was originally excluded from the Contract. Elias Mahfoud - Director of Design and Construction Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 303 5/26/2020 Tutor Perini/Zachry/Parsons Third party Improvements California Department of Fish and Wildlife Addition of Wildlife Crossings - Design $409,313.82 This is a change to a contract for design services in the Central Valley. The reason for the change is to compensate the Contractor for the design of five Wildlife Crossings required by the California Department of Fish and Wildlife. Garth Fernandez - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 312 5/21/2020 Tutor Perini/Zachry/Parsons Design Revisions Intersection of West Avenue and Weber Avenue - Design $184,655.27 This is a change to a contract for design services in the Central Valley. The reason for the change to compensate the Contractor to design a controlled intersection of West and Weber Avenues that will provide a traffic signal in lieu of a roundabout within the existing City of Fresno Right of Way based on projected traffic flow data provided by High Speed Train and analyzed by the Contractor. Garth Fernandez - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 310 5/21/2020 Tutor Perini/Zachry/Parsons Design Revisions Golden State Boulevard Roadway City of Fresno Deal Points - Design $528,882.00 This is a change to a contract for design services in the Central Valley. The reason for the change is to compensate the Contractor for additional design to incorporate all changes pertaining to Golden State Boulevard between Ashlan and Herndon Avenues. Garth Fernandez - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 302 5/21/2020 Tutor Perini/Zachry/Parsons Additional Scope Design Impacts by Fresno Metropolitan Flood Control District at Multiple Locations $483,580.00 This is a change to a contract for design services in the Central Valley. The reason for the change is to compensate the Contractor for design impacts caused by Fresno Metropolitan Flood Control District request for additional submittals outside of the Master Agreement between the periods of March 3, 2019 to June 4, 2019. This is a pass-through claim for Blair Church and Flynn Consulting Engineers and respective Contractor administrative changes for processing submittals for impacted design packages. Garth Fernandez - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 301 5/21/2020 Tutor Perini/Zachry/Parsons Design Revisions City Of Fresno Water Line South of Shaw Avenue Full Length Jack & Bore Installation $126,296.00 This is a change to a contract for construction services in the Central Valley. The reason for the change is to compensate the Contractor for all labor, material and equipment to perform the additional scope of full length jack & bore installation work for the City Of Fresno water line under Golden State Boulevard. Garth Fernandez - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 295 5/21/2020 Tutor Perini/Zachry/Parsons Third party Improvements DL-00174 Design Refinement for PG&E E1-189 (Shaw Avenue) - Design only $65,970.00 This is a change to a contract for design services in the Central Valley. The reason for the change is to compensate the Contractor for the redesign of the Comcast line relocation under the High Speed Rail Right Of Way at Shaw Avenue as a result of the redesign of PG&E conflict E-1-189 per Directive Letter 0174. Garth Fernandez - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 294 5/21/2020 Tutor Perini/Zachry/Parsons Third party Improvements Design Refinement of Comcast at Mckinley Avenue due to PG&E E1-025 Relocation $65,970.00 This is a change to a contract for design services in the Central Valley. The reason for the change is to compensate the Contractor for the redesign of the Comcast utility line due to the relocation of PG&E conflict E1-025 at McKinley Avenue. Garth Fernandez - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 283 5/21/2020 Tutor Perini/Zachry/Parsons Design Revisions Comcast DP T2-010 (Florence Avenue) DL-174 $49,500.00 This is a change to a contract for design services in the Central Valley. The reason for this change is to compensate the Contractor for additional design cost to relocate a Comcast Utility Telecom line (T2-010) at Florence Avenue to avoid additional design variance from Union Pacific Rail Road per Directive Letter 0174. Garth Fernandez - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 280 5/21/2020 Tutor Perini/Zachry/Parsons Design Revisions Comcast DP T2-024 California & Cherry Avenue Crossing Redesign $81,333.00 This is a change to a contract for design services in the Central Valley. The reason for the change is for the redesign costs of the relocations for Comcast utility T2-024 crossing at California and Cherry Avenues to bring them in line with Union Pacific Railroad standards and avoid additional design variance. Garth Fernandez - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 279 5/21/2020 Tutor Perini/Zachry/Parsons Design Revisions Tuolumne Basin Redesign due to Hazardous Material, Directive Letter 180 - Design $32,199.00 This is a change to a contract for design services in the Central Valley. The reason for the change is to execute Authority Directive Letter 0180 in which the Contractor was directed to redesign two retention basins located in contaminated soil along G Street with a temporary 10-year High Density Polyethylene impermeable lining to prevent storm water from infiltrating through contaminated soil and potentially polluting groundwater. Garth Fernandez - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 318 5/12/2020 Tutor Perini/Zachry/Parsons Third party Improvements Level 3 Line T3-14 Conflict with Avenue 15 Abutment 3 Foundation $32,386.51 This is a change to a contract for construction services in the Central Valley. The reason for the change is to compensate the Contractor for the workaround in which the existing Level 3 line at Avenue 15 conflicts with the excavation of Abutment 3 foundation. Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 316 5/12/2020 Tutor Perini/Zachry/Parsons Additional Scope PCO 0864 DL 0175 Additional Scope Items (Elevated Structures & Trenches) - Design only $1,000,000.00 This is a change to a contract for design services in the Central Valley. The reason for the change is for the advanced payment towards the completion of the design of four additional scope items in connection to Type 1 elevated structures, trenches and cut and cover sections as identified in Directive Letter 0175, clarified at the scoping meeting held on 1/9/2020 and as documented in meeting minutes. Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 315 5/12/2020 Tutor Perini/Zachry/Parsons Additional Scope Fresno Trench Storm Drain Workaround - Construction $106,999.06 This is a change to a contract for construction services in the Central Valley. The reason for the change compensates the Contractor for the construction of the temporary connection between the scuppers on SR-180 and the existing storm drain line running in the Fresno Trench into Fresno Metropolitan Flood Control District systems to dispose runoff water from the overhead highway systems as mandated by Caltrans. Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 314 5/12/2020 Tutor Perini/Zachry/Parsons Other Reimbursement for Right Of Way Easement from Parallamo LLC at Mono Street $27,294.92 This is a change to a contract for construction services in the Central Valley. The reason for the change is to reimburse the Contractor for cost to obtain the Right Of Way easement from Parallamo LLC at Mono Street. The Authority directed the Contractor to make a one-time payment to Parallamo LLC in order to dedicate parcel FB-10-0170-001 to the City of Fresno for roadway purposes. Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 48.4 5/7/2020 Tutor Perini/Zachry/Parsons Administrative Additional Supplemental Funding for Excluded Third Party Provisional Sum $19,000,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the additional supplemental funding is to compensate the contractor to manage and subcontract all direct services required for the relocation of PG&E and AT&T Excluded Third Party Utilities. Joe Hedges - Chief Operations Officer Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 308 5/6/2020 Tutor Perini/Zachry/Parsons Third party Improvements Westside Shoofly Modifications - Trackwork Material and Installation Only $1,646,984.00 This is a change to a contract for construction services in the Central Valley. The reason for the change is to compensate the Contractor for a portion of work associated with the construction of the Westside Shoofly and to proceed with procurement and installation of all track material necessary to construct tracks TK# 114-SH, 115-SH, 114-SH(Final), 115-SH(Final) and 736(Final). Elias Mahfoud - Director of Design and Construction Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 287 4/30/2020 Tutor Perini/Zachry/Parsons Third party Improvements Kern and Mono Cul-de-Sacs - Design $136,659.97 This is a change to a contract for design services in the Central Valley. The reason for this change is to compensate the Contractor for the design efforts to reconstruct both Kern and Mono Street terminations as standard Cul-de-Sacs with sidewalks for local residential streets as specified in this Change Order. Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 290 4/30/2020 Tutor Perini/Zachry/Parsons Design Revisions Directive Letter 0171 R1 Reinforced Concrete Pipe Casing or Restrained Joints $340,195.34 This is a change to a contract for design services in the Central Valley. The reason for this change is for the design modification required by Union Pacific Rail Road due to the change to their design and construction standards which require solutions to protect the railroad Right of Way against leakage from storm and sewer applications installed in Union Pacific Rail Road right of way within CP1 project limits per Directive Letter 0171 R1 (11 locations). Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 317 4/29/2020 Tutor Perini/Zachry/Parsons Third party Improvements Road 27 Fiber Optic Relocation for Level 3 - Construction $2,312,446.85 This is a change to a contract for construction services in the Central Valley. The reason for this change is to compensate the Contractor to relocate Level 3 line at Road 27 in accordance with Directive Letter 0137 R2. Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 289 4/29/2020 Tutor Perini/Zachry/Parsons Design Revisions Merced Sewer Realignment - Design $16,315.33 This is a change to a contract for design services in the Central Valley. The reason for the change is to compensate the Contractor for the re-design of the sewer line that runs underneath the high-speed train right of way at Merced Street due to a change of construction sequence which resulted in a requirement to modify the City of Fresno sewer and other impacted designs. Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 284 R1 4/27/2020 Tutor Perini/Zachry/Parsons Additional Scope Burlington Northern Santa Fe Railway Access Plan - Design $305,592.36 This is a change to a contract for design services in the Central Valley. The reason for the change is to compensate the Contractor to prepare a Burlington Northern Santa Fe Railway Access Plan, inclusive of designing physical improvements for the purpose of providing access as was stipulated in the Authority/ Burlington Northern Santa Fe Railway "Relocation and Construction Agreement" dated 12/10/16. Directive Letter 135 authorized the Contractor to proceed with aforementioned scope of work. Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 299 4/23/2020 Tutor Perini/Zachry/Parsons Third party Improvements Road 27 Waterline Replacement for Madera Valley Water Company $1,773,899.40 This is a change to a contract for construction services in the Central Valley. The reason for the change is for the additional costs to relocate the Madera Valley Water Company water line at Road 27 as part of the roadway improvements required to allow the reopening of Road 27 for vehicular and pedestrian use in the North Extension segment. Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 306 4/8/2020 Tutor Perini/Zachry/Parsons Additional Scope Additional shoring at Fresno Trench Headwall Construction at Westside Wye South Leg - Construction $73,033.36 This is a change to a contract for construction services in the Central Valley. The reason for the change is to compensate the Contractor for the additional construction cost for the vertical shoring to construct the Fresno Metropolitan Flood Control District Headwalls on the Westside Wye south leg. Work was performed on Time & Material basis. Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 298 4/8/2020 Tutor Perini/Zachry/Parsons Additional Scope Import from Authority Borrow Site Avenue 7 Guideway Construction $4,937,881.74 This is a change to a contract for construction services in the Central Valley. The reason for the change is to compensate the Contractor for all labor, material and equipment costs necessary to excavate, load, haul and provide a rough grade of the basin slopes without finished work, as well as supporting operations such as traffic control, securing the cut sites with temporary fence, storm water pollution control requirements to be installed as needed and agreed upon. Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 297 4/8/2020 Tutor Perini/Zachry/Parsons Additional Scope Topographic Survey for Caltrans 99 Section $78,459.00 This is a change to a contract for construction services in the Central Valley. The reason for the change is for the Contractor to conduct a topographic survey on a 2-mile section within the high-speed rail Construction Package 1 project known as "Caltrans Project Section." Scope includes additional cost for the effort to import and process survey data into MicroStation. Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 307 3/31/2020 Tutor Perini/Zachry/Parsons Design Revisions California Department of Fish and Wildlife Addition of Wildlife Crossings $3,517,264.00 This is a change to a contract for construction services in the Central Valley. The reason for the change is to compensate the Contractor for the construction of five Wildlife Crossings at locations identified in this Change Order. Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 305 3/31/2020 Tutor Perini/Zachry/Parsons Design Revisions Intrusion Protection Barrier Addition and Revision - Design $13,898,322.64 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to compensate the Contractor for all additional design effort necessary to incorporate all required revisions to the Intrusion Protection Barrier. It also includes compensation for Extra Work as stipulated in this Change Order in a Time & Material basis per Contract. Joe Hedges - Chief Operations Officer Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 304 3/31/2020 Tutor Perini/Zachry/Parsons Other Madera Irrigation District Lateral 6.2 Box Culvert Divrsion $1,218,221.00 This is a change to a contract for construction services in the Central Valley. The reason for the change is for the construction of the canal diversion for the Madera Irrigation District Lateral 6.2 to allow the completion of the proposed Box Culvert outside of the normal non-irrigation season. The diversion work was accelerated to be completed prior to the start of the next irrigation season, February 22, 2021. Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 281 2/27/2020 Tutor Perini/Zachry/Parsons Differing Site Conditions Issue Resolution - Potential Change Orders 374, 518 and 543 $21,260.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the Settlement Agreement between the Authority and Contractor for the following Potential Change Orders: 0374, 0518 and 0543. This Change Order compensates the Contractor for providing all services, labor, material, equipment, tools and incidentals including all markups. Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 89.01 2/27/2020 Tutor Perini/Zachry/Parsons Scope Changes North Extension Revised Alignment $33,107,436.93 This is a change to a contract for construction services in the Central Valley. The reason for the change is to supplement Change Order 00089, North Extension Design and Construction executed on April 8, 2016, in order to compensate the Contractor for the supplemental construction costs on the North Extension. Joe Hedges - Chief Operations Officer Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 228 2/26/2020 Tutor Perini/Zachry/Parsons Design Criteria/Specification Change Settlement of Cost for Mechanically Stabilized Earth to Cast In Place $35,345,236.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to settle all cost related to conversion of 15 structures from Mechanically Stabilized Earth to Cast-In-Place concrete abutments and the Burlington North Santa Fe wing walls to protect Mechanically Stabilized Earth walls. Joe Hedges - Chief Operations Officer Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 288 2/10/2020 Tutor Perini/Zachry/Parsons Third party Improvements Fresno Street Road Classification Change $6,265.67 This is a change to a contract for design services in the Central Valley. The reason for the change is to compensate the Contractor for design efforts to change the road classification at Fresno Street from Collector to Arterial. Change include revising plans to reflect the new classification and thickness of pavement. Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 231.02 2/4/2020 Tutor Perini/Zachry/Parsons Impacts due to relocations of facilities owned by Third Parties City Of Fresno Utility Relocation Herndon to Carnegie $3,197,461.00 This is a change to a contract for construction services in the Central Valley. The reason for this change is to compensate the Contractor to construct water and sewer mains at Golden State Boulevard between Herndon and Carnegie Avenues per City of Fresno plans. Joe Hedges - Chief Operations Officer Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 252.01 1/31/2020 Tutor Perini/Zachry/Parsons Impacts due to relocations of facilities owned by Third Parties Parcels MF-20-0901, 0902, 0903 Irrigation Line Supply Change $213,513.94 This is a change to a contract for construction services in the Central Valley. The reason for the change is to provide supplemental compensation to the Contractor for construction to install six (6) 24-inch casings instead of the initial three (3) 36-inch casings at parcels MF-20-0901, 0902 and 0903. Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 286 1/17/2020 Tutor Perini/Zachry/Parsons Scope Changes Authority Additional Bizhub C558 Copiers $41,421.07 This is a change to a contract for project management services in the Central Valley. The reason for the change is to authorize a 48-month lease for three additional Bizhub C558 copiers from Caltronics for use by Authority during the CP1 Project. Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 282 1/17/2020 Tutor Perini/Zachry/Parsons Impacts due to relocations of facilities owned by Third Parties Calfifornia and Cherry Water Relocation $52,488.91 This is a change to a contract for design services in the Central Valley. The reason for this change is to redesign City of Fresno waterline as part of the California and Cherry water line relocation design packages. Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 285 1/8/2020 Tutor Perini/Zachry/Parsons Impacts due to relocations of facilities owned by Third Parties Third Party Property Rights Verification $5,956,386.19 This is a change to a contract for construction administration services in the Central Valley. The reason for the change is to compensate the Contractor for providing general administration services in support of Authority Right-of-Way engineering. Compensation covers all work that has been completed or is "In progress" as of the agreed cut-off date of July 26, 2019. Joe Hedges - Chief Operations Officer Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 133.03 1/8/2020 Tutor Perini/Zachry/Parsons Scope Changes Avenue 12 High Speed Train Overhead Structure - Release For Construction to Aproved For Construction $2,306,730.21 This is a change in contract for design and construction services in the Central Valley. The reason for the change is to compensate the Contractor for the change in scope of work between Release For Construction to Aproved For Construction drawings at Avenue 12 High Speed Train Overcrossing. Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 272 12/20/2019 Tutor Perini/Zachry/Parsons Differing Site Conditions Tank and Well Removal $24,514.84 This is a change to a contract for construction services in the Central Valley. The reason for the change is to compensate the Contractor for the removal of septic tank and two wells located in the right of way of parcel FB-10-0503. Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 165.1 12/6/2019 Tutor Perini/Zachry/Parsons Changes to Plans and Specifications Solid Barrier on Type 2 Overhead - Design $37,900.43 This is a change to a contract for design services in the Central Valley. The reason for the change is for additional redesign efforts to change the Overhead Structure Barrier design to a rigid traffic barrier with Access Deterrent Fence (AD) on all roadway and pedestrian overhead structures per Directive Letter DL-084 R3. Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 5.1 11/27/2019 Tutor Perini/Zachry/Parsons Administrative Local and Long Distance Phone Charges $50,410.40 This is a change to a contract for construction management services in the Central Valley. The reason for this change is for the reimbursement of additional local and long distance phone calls from April 15, 2018 to September 15, 2019 and includes projected costs through the end of the Contract. Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 277 11/22/2019 Tutor Perini/Zachry/Parsons Environmental Westside Wye Shoofly Dirt Contamination Testing $14,970.81 This is a change to a contract for materials testing in the Central Valley. The reason for the change is to compensate the Contractor to test and report on potential contaminated materials at the Westside Wye Shoofly, as well as recommendations from a registered geologist. Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 274 11/22/2019 Tutor Perini/Zachry/Parsons Third-Party Related Left Turn Channelization at Golden State Boulevard - Construction Only $886,440.91 This is a change to a contract for construction services in the Central Valley. The reason for this change is for the construction of the median opening and left turn channelization for southbound Golden State Boulevard, south of East Avenue, for California Legal Truck access to the relocated main driveway of Weir Floway (parcel FB-10-0220). The work is based on plan set for City of Fresno Public Works Department Weir Floway Median Opening Plans C-001-WFC. Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 177.1 11/22/2019 Tutor Perini/Zachry/Parsons Changes to Plans and Specifications Transfer of Funds Contingency to Construction Contract Work $500,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to increase the amount of "Provisional Sums" as defined in the Contract special provisions to compensate the Contractor for Construction Contract Work (CCW). Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 275 11/15/2019 Tutor Perini/Zachry/Parsons Third-Party Related Mono Street - San Joaquin Valley Railroad Track 118 Materi $110,320.59 This is a change to a contract for construction services in the Central Valley. The reason for this change is for the procurement and delivery of track, crossing panels and stockpiling of ballast rock necessary to allow Union Pacific Railroad to raise the existing San Joaquin Valley Railroad Spur Track #118 at the Mono Street at-grade crossing. (Installation of materials to be performed by Union Pacific Railroad) Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 273 11/15/2019 Tutor Perini/Zachry/Parsons Third-Party Related McKinley Avenue Storm Drain United Parcel Service (UPS) Tie-In $13,717.08 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to design a new required storm drain manhole within the vicinity of the proposed Golden State Blvd. and McKinley Ave. near HSR STA 10845+00, per Authority Letter PCM-TPZP-04005. Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 87.3 11/8/2019 Tutor Perini/Zachry/Parsons Third-Party Related Top Down Construction at State Route 180 Supplemental 3 $1,794,094.00 This is a change to a contract for construction services in the Central Valley. The reason for the change is to compensate the Contractor for additional unforeseen Third Party scope of work to execute Alternate Technical Concept #1A (top/down construction methodology) at Fresno Trench construction beneath highway State Route 180. This Change Order is a supplement to CO 00087 dated April 5,2016. Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 271 10/25/2019 Tutor Perini/Zachry/Parsons Changes to Plans and Specifications Emergency Closure State Route 180 West Bound $12,079.76 This is a change to a contract for construction services in the Central Valley. The reason for this change is to compensate the Contractor for completing an emergency closure of the SR-180 West bound #3 lane at the Fulton Street onramp for the purpose of installing K-Rail protection with crash barriers on June 19, 2019. Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 265.1 10/25/2019 Tutor Perini/Zachry/Parsons Changes to Plans and Specifications Union Pacific Railroad Homeless Encampment Cleanup $500,000.00 This is a change to a contract for construction services in the Central Valley. The reason for this change is to add funds to original CO 00265. The original amount including the supplemental is hereby increased by $500,000.00, from $100,000.00 to $600,000.00, as well as funding for cleanup for a homeless encampment. Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 262 10/25/2019 Tutor Perini/Zachry/Parsons Third-Party Related United States Bureau of Reclamation Agreement for Siphon Maintenance $144,920.04 This is a change to a contract for maintenance services in the Central Valley. The reason for this change is to compensate the United States Bureau of Reclamation for the cost involved in maintaining and cleaning proposed new siphon at Madera Irrigation District (MID) facility, Lateral 6.2 in perpetuity. Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 266 10/24/2019 Tutor Perini/Zachry/Parsons Right-of-Way (ROW) Related FB-10-0176 Secure Fresno Rescue Mission Structure $2,642.59 This is a change in contract for construction services in the Central Valley. The reason for the change is to compensate the Contractor for securing the Fresno Rescue Mission structure on parcel FB-10-0176. Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 270 10/22/2019 Tutor Perini/Zachry/Parsons Differing Site Conditions MF-10-0058 Keith's Automotive Sewer Leak $5,061.49 This is a change in contract for construction services in the Central Valley. The reason for the change is to provide compensation to the Contractor for performing sewer investigation work at Keith's Automotive at 5355 North Golden State Boulevard, parcel MF-10-0058, to determine the cause of a sewer leak. Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 233.2 10/22/2019 Tutor Perini/Zachry/Parsons Third-Party Related Deposit and Reimbursement for Madera Valley Water Company $5,447.50 This is a change to a contract for design services in the Central Valley. The reason for the change is to provide initial deposit and reimbursement of funds for Madera Valley Water Company per Authority request for agreement review services. Steven Milton - Design and Construction Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 260 10/10/2019 Tutor Perini/Zachry/Parsons Changes to Plans and Specifications Herndon Avenue - Construction $76,583,809.00 This is a change to a contract for construction services in the Central Valley. The reason for the change is compensate the Contractor for additional construction costs as a result of the approval of Alternate Technical Concept #8 for the Herndon Ave area development. Joe Hedges - Chief Operating Officer Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 149.1 10/4/2019 Tutor Perini/Zachry/Parsons Utility Relocation Credit from Change Order 00149 ($3,494.75) This is a change to a contract for construction services in the Central Valley. The reason for this change is to provide a credit to the Authority for the difference equivalent to -$3,494.75 due to a summation error in the Subcontractor's bid proposal for Change Order 00149, dated March 9, 2017. John Neri - Senior Contract Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 265 8/19/2019 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related UPRR Safety and Security $100,000.00 This is a change to the contract for design and construction services in the Central Valley. This change order allows the contractor to complete activities within the Union Pacific Railroad right of way. John Neri - Senior Contract Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 264 8/6/2019 Tutor Perini / Zachry/Parsons Utility Relocation Sprint Utility Work Subtask 1.05 $727,099.61 This is a change to the contract for design and construction services in the Central Valley. This change order allows for completion of the relocation of telecommunications facilities. John Neri - Senior Contract Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 261 8/6/2019 Tutor Perini / Zachry/Parsons Utility Relocation Switch Relo for UPRR Siding 729 $102,271.87 This is a change to the contract for design and construction services in the Central Valley. This change order designs the relocation of Union Pacific Railroad infrastructure to enable subsequent relocation of utilities. John Neri - Senior Contract Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 99.2 8/6/2019 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related Completion Deadline Ext / Resolution $126,000,000.00 This is a change to the contract for design and construction services in the Central Valley. The change order is to resolve all delays, claims and disputes from January 1, 2016 through May 1, 2019 and revise the date to complete the work to August 31, 2021. Joe Hedges - Chief Operating Officer Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 88.8 8/6/2019 Tutor Perini / Zachry/Parsons Environmental Environmental Staffing - Supplemental No 8 $9,000,000.00 This is a change to a contract for design and construction services in the Central Valley. This change order continues to provide environmental services to ensure the future high-speed rail system work complies with environmental requirements. William Grimsley - Director of Design & Construction Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 48.3 8/5/2019 Tutor Perini / Zachry/Parsons Utility Relocation PG&E & AT&T Facilities Relocation S3 $19,000,000.00 This is a change to the contract for design and construction services in the Central Valley. The change order enables utilities of PG&E and AT&T to be moved out of the way of the future high-speed rail system. Joe Hedges - Chief Operating Officer Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 263 7/31/2019 Tutor Perini / Zachry/Parsons Utility Relocation Utility Relocations to Accommodate UPRR - CCS - Sprint - Construction $77,064.23 This is a change to a contract for design and construction services in the Central Valley. The reason for the change order is for Sprint, a telecommunications company, to inspect, monitor, protect and verify if their services will need to be moved for the high-speed rail system. This work is being coordinated by the general contractor in Fresno responsible for designing and constructing the future system. John Neri - Senior Contract Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 231.1 7/12/2019 Tutor Perini / Zachry/Parsons Utility Relocation City of Fresno Utility Relocations Package 2 and 3 $4,221,684.30 This is a change to a contract for design and construction services in the Central Valley. The reason for the change order is for the City of Fresno to move its services out of the way of future high-speed rail system. The work is being coordinated by the general contractor in Fresno responsible for designing and constructing the future system. Joe Hedges - Chief Operating Officer Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 258 7/11/2019 Tutor Perini / Zachry/Parsons Third-party Related HSR CP1 - JMA Railroad Review and Consultation $88,755.50 This is a change to a contract for design and construction services in the Central Valley. The reason for the change order is to expedite all railroad related submittals and improve overall communication between Union Pacific Railroad, San Joaquin Valley Railroad, Tutor/Perini/Zachry/Parsons JV and the Authority. John Neri - Senior Contract Manager Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 48.2 7/11/2019 Tutor Perini/Zachry/Parsons Utility Relocation PG&E & AT&T Facilities Relocation S2 $5,000,000.00 This is a change to the contract for design and construction services in the Central Valley. This Supplemental change order increases the amount of the "Provisional Sums" as defined in Book 2, Part A, Subpart 2, Special Provisional, Section 6 Provisional Sums to compensate the contractor to manage and subcontract all direct services required for the relocation of Excluded Third Party Utilities. William Grimsley - Director of Design and Construction Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 10.1 6/19/2019 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related Weed Abatement - North Ext. CO 00089 $- This is a change to a contract for design and construction services in the Central Valley and authorizes the clearance of weeds, grass, trash and debris from Authority owned properties in an area of construction north of Fresno. The reason for this change is to authorize these clearance activities in an area known as the "Northern Extension", which was added to the construction contract in March, 2016. The original clearance activities authorized for $300,000 in change order 10 did not include the Northern Extension. John Neri, Senior Contract Manager Ghassan Ariqat, Project Manager/Director Mike Sheffield, D-B Oversight Manager
CP 1 HSR 13-06 259 6/12/2019 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related MF-20-0948 Two Conc. Slabs Ave 15.5 $4,105.88 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to demolish two concrete slabs at a property acquired by the Authority near Avenue 15 and a half in Madera County. John Neri, Senior Contract Manager Ghassan Ariqat, Project Manager/Director Mike Sheffield, D-B Oversight Manager
CP 1 HSR 13-06 88.7 6/7/2019 Tutor Perini / Zachry/Parsons Environmental Additional Environmental Services $1,000,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to continue to provide environmental services to ensure the future high-speed rail system work complies with environmental requirements. John Neri, Senior Contract Manager Ghassan Ariqat, Project Manager/Director Mike Sheffield, D-B Oversight Manager
CP 1 HSR 13-06 257 5/21/2019 Tutor Perini / Zachry/Parsons Utility Relocation UNI: Fresno Bridge Relo Costs DL0078 $87,165.44 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for Sprint, a telecommunications company, to move its services out of the way of the future high-speed rail system. This work is coordinated by the general contractor in Fresno responsible for designing and constructing the future system. Joe Hedges, Chief Operating Officer Ghassan Ariqat, Project Manager/Director Mike Sheffield, D-B Oversight Manager
CP 1 HSR 13-06 254 5/13/2019 Tutor Perini / Zachry/Parsons Utility Relocation UNI: ATT Wrkarnd Carnegie & Cornelia $39,241.64 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to temporarily move AT&T facilities and a fire hydrant until they can be installed in their permanent locations to enable the re-alignment of Golden State Boulevard in Fresno. Joe Hedges - Chief Operating Officer Ghassan Ariqat, Project Manager/Director Mike Sheffield, D-B Oversight Manager
CP 1 HSR 13-06 235 5/9/2019 Tutor Perini / Zachry/Parsons Third-party Related Fresno Trench IPB - Construction $8,350,000.00 This is a change to the contract for design and construction services in the Central Valley. The reason for the change is to do construction work in the Fresno trench associated with the new standards required to keep conventional trains out of the future high-speed rail system. William Grimsley - Director of Design and Construction Ghassan Ariqat, Project Manager/Director Mike Sheffield, D-B Oversight Manager
CP 1 HSR 13-06 255 5/7/2019 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications UNI: SR-180 S Slope Unknwn Obstruct $114,486.53 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to remove an unexpected obstruction found during the work at the State Route 180. Joe Hedges - Chief Operating Officer Ghassan Ariqat, Project Manager/Director Mike Sheffield, D-B Oversight Manager
CP 1 HSR 13-06 253 5/2/2019 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related UNI: MF-20-0935 Irr & Com Ln Ave 12 $83,876.44 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to install an irrigation pipeline and a communication line across Avenue 12, to complete property acquisition requirements.   Joe Hedges - Chief Operating Officer Ghassan Ariqat, Project Manager/Director Mike Sheffield, D-B Oversight Manager
CP 1 HSR 13-06 252 5/2/2019 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related UNI: MF-20-0901, 0902, 0903 Irrig Ln $243,225.06 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to install three 36-inch irrigation casings as part of the construction work to enable the future high-speed rail system to be built. Joe Hedges, Chief Operating Officer Ghassan Ariqat, Project Manager/Director Mike Sheffield, D-B Oversight Manager
CP 1 HSR 13-06 233.1 5/2/2019 Tutor Perini / Zachry/Parsons Utility Relocation UNI: MVWC Waterline Relocation Rd 27 $2,179.00 This is a change to a contract for design and construction services in the Central Valley. The change is additional to change 233 and is for the inclusion of Federal flow down conditions into work performed by Giersch & Associates related to moving the water line owned by the Madera Valley Water Company. Joe Hedges, Chief Operating Officer Ghassan Ariqat, Project Manager/Director Mike Sheffield, D-B Oversight Manager
CP 1 HSR 13-06 250 4/24/2019 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related UNI: MF-20-0917 Irrgtn Pipe & Condt $239,060.74 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to install irrigation pipelines and conduits in three locations, to complete property acquisition requirements.   Joe Hedges - Chief Operating Officer Ghassan Ariqat, Project Manager/Director Mike Sheffield, D-B Oversight Manager
CP 1 HSR 13-06 248 4/24/2019 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related UNI: FB-10-0233 Additional Demo $20,814.14 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to complete additional demolition of a building on an Authority-owned property at South Railroad Avenue. Joe Hedges, Chief Operating Officer Ghassan Ariqat, Project Manager/Director Mike Sheffield, D-B Oversight Manager
CP 1 HSR 13-06 249 4/17/2019 Tutor Perini / Zachry/Parsons Third-party Related UNI: Basin EE Rcycld Irrigtn Pmp Mod $17,884.82 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for additional design to an irrigation water pump. This includes replacing the power and control cables and relocating the irrigation line. William Grimsley - Director of Design & Construction Ghassan Ariqat, Project Manager/Director Mike Sheffield, D-B Oversight Manager
CP 1 HSR 13-06 246 4/17/2019 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related UNI: FB-10-0256 South Bldg Addl Demo $13,147.48 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to complete additional demolition of a building on an Authority-owned property at South Cedar Avenue. William Grimsley, Director of Design & Construction Ghassan Ariqat, Project Manager/Director Mike Sheffield, D-B Oversight Manager
CP 1 HSR 13-06 244 4/17/2019 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications UNI: Rdside Barriers at OC Deal Pts $31,265.62 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to design modifications related to structures and roadways at Central, Church, Tuolumne, Belmont, Olive, McKinley, and Shaw in the City of Fresno. William Grimsley, Director of Design & Construction Ghassan Ariqat, Project Manager/Director Mike Sheffield, D-B Oversight Manager
CP 1 HSR 13-06 239 4/15/2019 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications UNI: North Ext Rescoping 2 - Design $10,649,178.47 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to complete additional design work in the area known as the "Northern Extension", north of Fresno. This design work will move third party facilities and utilities out of the way of the future high-speed rail system. Joe Hedges, Chief Operating Officer Ghassan Ariqat, Project Manager/Director Mike Sheffield, D-B Oversight Manager
CP 1 HSR 13-06 242 4/11/2019 Tutor Perini / Zachry/Parsons Utility Relocation UNI: American Ave Facility Plan $224,384.33 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to design modifications to the new locations of PG&E and Comcast facilities at American Avenue. William Grimsley, Director of Design & Construction Ghassan Ariqat, Project Manager/Director Mike Sheffield, D-B Oversight Manager
CP 1 HSR 13-06 247 4/9/2019 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related UNI: MF-10-0083 Addtl. Mobilization $24,015.30 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to re-start construction work at a specific property at West Shaw Avenue due to delays in receiving correct data on a fire service line. William Grimsley, Director of Design & Construction Ghassan Ariqat, Project Manager/Director Mike Sheffield, D-B Oversight Manager
CP 1 HSR 13-06 243 4/4/2019 Tutor Perini / Zachry/Parsons Third-party Related UNI: Dry Creek Canal Culvert Redsgn $51,641.30 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to design modifications to the Dry Creek Canal culvert, over which the future high-speed rail system will travel. William Grimsley, Director of Design & Construction Ghassan Ariqat, Project Manager/Director Mike Sheffield, D-B Oversight Manager
CP 1 HSR 13-06 241 4/4/2019 Tutor Perini / Zachry/Parsons Third-party Related UNI: McKinley & Basin EE Refinements $552,350.18 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to complete additional design work related to road way work at McKinley Avenue in Fresno and a nearby drainage basin. William Grimsley - Director of Design and Construction Ghassan Ariqat, Project Manager/Director Mike Sheffield, D-B Oversight Manager
CP 1 HSR 13-06 240 4/4/2019 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications UNI: North Ext Supplement 1 - Design $3,573,973.79 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to complete additional design work in the area known as the "Northern Extension", north of Fresno. This additional design work was triggered by changes initiated by the Authority to the final alignment of the future high-speed rail system. William Grimsley - Director of Design and Construction Ghassan Ariqat, Project Manager/Director Mike Sheffield, D-B Oversight Manager
CP 1 HSR 13-06 237 4/4/2019 Tutor Perini / Zachry/Parsons Third-party Related UNI: Church Ave Overcrossing Sunland $285,430.57 This is a change to the contract for design and construction services in the Central Valley. The reason for the change is to complete additional design work at Church and Sunland Avenues in Fresno. William Grimsley - Director of Design and Construction Ghassan Ariqat, Project Manager/Director Mike Sheffield, D-B Oversight Manager
CP 1 HSR 13-06 234 4/4/2019 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications UNI: North Ext Supplement 2 - Design $1,142,390.46 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to complete additional design work in the area known as the "Northern Extension", north of Fresno. William Grimsley - Director of Design and Construction Ghassan Ariqat, Project Manager/Director Mike Sheffield, D-B Oversight Manager
CP 1 HSR 13-06 232 4/4/2019 Tutor Perini / Zachry/Parsons Utility Relocation UNI: AT&T Workaround for Belmont Ave $1,032,551.05 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to design work arounds to address delays in AT&T design and construction work of new facility locations. William Grimsley, Director of Design & Construction Ghassan Ariqat, Project Manager/Director Mike Sheffield, D-B Oversight Manager
CP 1 HSR 13-06 188 4/4/2019 Tutor Perini / Zachry/Parsons Third-party Related UNI: UPRR Bridge AREMA Ver. Switch $36,394.49 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is new American Railway Engineering and Maintenance-of-Way Association (AREMA) standards. These standards triggered the re-design of certain future high-speed rail system work. William Grimsley - Director of Design and Construction Ghassan Ariqat, Project Manager/Director Mike Sheffield, D-B Oversight Manager
CP 1 HSR 13-06 122 4/4/2019 Tutor Perini / Zachry/Parsons Third-party Related UNI: Lighting Mod due to UPRR $23,731.75 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is new lighting requirements required by the Union Pacific Rail Road at Blemont and McKinley Avenues in Fresno. William Grimsley - Director of Design and Construction Ghassan Ariqat, Project Manager/Director Mike Sheffield, D-B Oversight Manager
CP 1 HSR 13-06 245 4/3/2019 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related UNI: FB-10-0216 Demo Stages Asphalt ($10,006.36) This is a change to a contract for design and construction services in the Central Valley. The reason for the change is a removal of demolition scope from the construction contractor. William Grimsley - Director of Design and Construction Ghassan Ariqat, Project Manager/Director Mike Sheffield, D-B Oversight Manager
CP 1 HSR 13-06 238 4/3/2019 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related UNI: FB-10-0256 Demo Credit Fambro ($7,437.94) This is a change to the contract for design and construction services in the Central Valley. The reason for the change is to receive a credit to the Authority from the contractor for a billing error. William Grimsley - Director of Design and Construction Ghassan Ariqat, Project Manager/Director Mike Sheffield, D-B Oversight Manager
CP 1 HSR 13-06 236 3/19/2019 Tutor Perini/Zachry/Parsons Third Party Requirements Reimbursement to City of Fresno for remaining project work $1,817,000.00 This is a change to a contract for design services in the Central Valley. The reason for the change is for the additional compensation for the required City Of Fresno review fees on all current and anticipated California High-Speed Rail Authority directed changes. Joe Hedges - Chief Operations Officer Ghassan Ariqat - Project Manager/Director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 229 2/1/2019 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related UNI: GSB Realignment Demo Credit ($975,774.47) This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to revise the demolition requirements on a number of Authority-owned properties and to receive a net credit to the Authority from the contractor. William Grimsley - Director of Design and Construction Ghassan Ariqat, Project Manager/Director Mike Sheffield, D-B Oversight Manager
CP 1 HSR 13-06 219 1/17/2019 Tutor Perini / Zachry/Parsons Third-party Related UNI: Kinder Morgan Valve Relo Herndn $569,699.95 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to move a Kinder Morgan 12" valve at Herndon Avenue to enable construction of the future high-speed rail system. William Grimsley, Director of Design & Construction Ghassan Ariqat, Project Manager/Director Mike Sheffield, D-B Oversight Manager
CP 1 HSR 13-06 233 1/15/2019 Tutor Perini / Zachry/Parsons Utility Relocation UNI: MVWC Waterline Relocation Rd 27 $149,578.49 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to develop the design to move a water line owned by the Madera Valley Water Company out of the way of the future high-speed rail system. Joe Hedges, Chief Operating Officer Ghassan Ariqat, Project Manager/Director Mike Sheffield, D-B Oversight Manager
CP 1 HSR 13-06 133 S2 12/10/2018 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications UNI: Ave 12 MSE to CIP Chg - Const. $6,334,334.65 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to incorporate design changes into the construction of Avenue 12. Joe Hedges, Chief Operating Officer Ghassan Ariqat, Project Manager/Director Mike Sheffield, D-B Oversight Manager
CP 1 HSR 13-06 225 12/8/2018 Tutor Perini / Zachry/Parsons Utility Relocation UNI: CPUC Conduits Ave 8 & 11 Const. $431,101.80 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to construct conduits and other elements at Avenue 8 and Avenue 11 structures for public utilities. William Grimsley, Director of Design & Construction Ghassan Ariqat, Project Manager/Director Mike Sheffield, D-B Oversight Manager
CP 1 HSR 13-06 6.1 11/26/2018 Tutor Perini / Zachry/Parsons Administrative DRB Expenses - Supplemental $100,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to increase the amount of funds in Change Order 00006 from $180,000 to $280,000. These funds are used to pay the Authority’s share of Dispute Resolution Board expenses. William Grimsley, Director of Design & Construction Ghassan Ariqat, Project Manager/Director Mike Sheffield, D-B Oversight Manager
CP 1 HSR 13-06 230 10/31/2018 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related FB-10-0219 Remediation Work $308,536.20 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to remove and dispose of contaminated soils. William Grimsley - Director of Design & Construction Ghassan Ariqat - Project Manager/Director Mike Sheffield - D-B Oversight Manager
CP 1 HSR 13-06 88.6 10/4/2018 Tutor Perini / Zachry/Parsons Environmental Additional Environmental Services $4,000,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to continue to provide environmental services to ensure the future high-speed rail system work complies with environmental requirements. William Grimsley, Director of Design & Construction Ghassan Ariqat, Project Manager/Director Mike Sheffield, D-B Oversight Manager
CP 1 HSR 13-06 223 10/2/2018 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications MSE to CIP Abutments at Avenue 7 $2,449,186.70 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to make changes to the bridge at Avenue 7. William Grimsley - Director of Design & Construction Ghassan Ariqat - Project Manager/Director Glenn Suitor - D-B Oversight Manager
CP 1 HSR 13-06 221 10/2/2018 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications Herndon Area Changes - Design $7,942,301.24 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to conduct design related to the alternative designs for the high-speed rail system around Herndon Avenue and related designs to resolve UPRR impacts. Joe Hedges - Cheif Operating Officer Ghassan Ariqat - Project Manager/Director Mike Sheffield - D-B Oversight Manager
CP 1 HSR 13-06 231 9/18/2018 Tutor Perini / Zachry/Parsons Utility Relocation COF Utility Relocation Changes Part1 $2,343,757.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to meet additional requirements for four locations of water and sewer facilities in the Utility Relocation Cooperative Agreement with the City of Fresno. William Grimsley - Director of Design & Construction Ghassan Ariqat - Project Manager/Director Mike Sheffield - D-B Oversight Manager
CP 1 HSR 13-06 224 9/11/2018 Tutor Perini / Zachry/Parsons Administrative Dispute Review - Executive $- This is a change to a contract for design and construction services in the Central Valley. The reason for this no cost change is to streamline the dispute resolution process. Terry Ogle - Director of Design & Construction Ghassan Ariqat - Project Manager/Director Mike Sheffield - D-B Oversight Manager
CP 1 HSR 13-06 214 8/28/2018 Tutor Perini / Zachry/Parsons Environmental American Avenue Changes $9,497,470.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to provide a longer bridge over the future high-speed rail system to reach the future high-speed rail maintenance facility. Joe Hedges - Cheif Operating Officer Ghassan Ariqat - Project Manager/Director Mike Sheffield - D-B Oversight Manager
CP 1 HSR 13-06 222 8/23/2018 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications Aesthetic Treatment at Type 1 Struct $1,515,077.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to provide aesthetic treatment of several future high-speed rail bridges in the Fresno area to make them look consistent. Terry Ogle - Director of Design & Construction Ghassan Ariqat - Project Manager/Director Mike Sheffield - D-B Oversight Manager
CP 1 HSR 13-06 218 8/17/2018 Tutor Perini / Zachry/Parsons Differing Site Conditions FB-10-0235 Unknown Brick Struct Rev $14,489.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to pay for the contractor to demolish and fill the hole from two unexpected brick structures. These structures are in the way of moving an irrigation line to enable future high-speed rail construction. Terry Ogle - Design & Construction Manager Ghassan Ariqat - Project manager/director Mike Sheffield - DB Oversight Manager
CP 1 HSR 13-06 208 7/11/2018 Tutor Perini / Zachry/Parsons Differing Site Conditions SR-180 Phase 2 Differing Site Cond. $16,086.08 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is due to unexpected obstructions that require additional drilling at the tunnel under State Route 180. Terry Ogle - Design & Construction Manager Ghassan Ariqat - Project manager/director Glenn Suitor - DB Oversight Manager
CP 1 HSR 13-06 175 S1 6/28/2018 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications Flagging And Temp Signal Rd26 Suppl $11,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to pave a pedestrian detour route at Club Drive. Steve Milton - Design & Construction Manager Ghassan Ariqat - Project Manager/Director Glenn Suitor - D-B Oversight Manager
CP 1 HSR 13-06 216 6/27/2018 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related FB-10-0231 Additional Demolition $51,805.69 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to demolish structures to make way for the future high-speed rail system. Terry Ogle - Director of Design & Construction Ghassan Ariqat - Project Manager/Director Glenn Suitor - D-B Oversight Manager
CP 1 HSR 13-06 215 6/27/2018 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related PAUC Parichan Farms - Construction $2,466,824.86 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to provide a crossing under the future high-speed rail system so a property owner can access their property on both sides of the train line. Terry Ogle - Director of Design and Construction Ghassan Ariqat - Project Manager/Director Glenn Suitor - D-B Oversight Manager
CP 1 HSR 13-06 213 6/27/2018 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related FB-10-0495 Tulare St. Building PIP $951,400.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to protect the access to a building instead of demolishing the building during construction of the future high-speed rail system. Terry Ogle - Director of Design and Construction Ghassan Ariqat - Project Manager/Director Glenn Suitor - D-B Oversight Manager
CP 1 HSR 13-06 48.1 6/11/2018 Tutor Perini / Zachry/Parsons Utility Relocation PG&E & AT&T Facilities Relocation S1 $40,000,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is provide additional funds for the transfer services from the Authority to the contractor. The transferred services are to manage the design and construction of PG&E and AT&T facilities to move them out of the way of future high-speed rail construction. Joe Hedges, Chief Operating Officer Ghassan Ariqat, Project Manager/Director Glenn Suitor, D-B Oversight Manager
CP 1 HSR 13-06 217 6/7/2018 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related MF-10-0258 Additional Demo $135,662.32 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to demolish structures to make way for the future high-speed rail system. Terry Ogle - Director of Design & Construction Ghassan Ariqat - Project Manager/Director Glenn Suitor - D-B Oversight Manager
CP 1 HSR 13-06 212 6/7/2018 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related MF-10-0210 Additional Demolition $32,353.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to demolish structures to make way for the future high-speed rail system. Terry Ogle - Director of Design and Construction Ghassan Ariqat - Project Manager/Director Glenn Suitor - D-B Oversight Manager
CP 1 HSR 13-06 211 6/7/2018 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related MF-10-0208 and 0209 Additional Demo $57,881.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to demolish structures to make way for the future high-speed rail system. Steve Milton - Design & Construction Manager Ghassan Ariqat - Project Manager/Director Glenn Suitor - D-B Oversight Manager
CP 1 HSR 13-06 209 6/7/2018 Tutor Perini / Zachry/Parsons Environmental FB-10-0229 PARC Environmental $44,293.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to demolish an office building to make way for the future high-speed rail system. Terry Ogle - Director of Design & Construction Ghassan Ariqat - Project Manager/Director Glenn Suitor - D-B Oversight Manager
CP 1 HSR 13-06 201 6/7/2018 Tutor Perini / Zachry/Parsons Third-party Related Kinder Morgan Relocation at McKinley $4,100,988.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to design and construct the Kinder Morgan 12 inch petroleum pipeline that is in the way of UPRR’s 3rd track and Centralized Traffic Control improvements. Terry Ogle - Design & Construction Manager Ghassan Ariqat - Project manager/director Glenn Suitor - DB Oversight Manager
CP 1 HSR 13-06 210 6/1/2018 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related FB-10-0044-01 Redesign Drainage Sys $27,121.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to complete redesign work of a drainage system due to a change in right of way availability. Terry Ogle - Director of Design & Construction Ghassan Ariqat - Project Manager/Director Glenn Suitor - D-B Oversight Manager
CP 1 HSR 13-06 207 5/24/2018 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related CCW FB-10-0001 Additional Demo $43,619.71 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to demolish a building and to make site improvements. Terry Ogle - Design & Construction Manager Ghassan Ariqat - Project manager/director Glenn Suitor - DB Oversight Manager
CP 1 HSR 13-06 206 5/24/2018 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related MF-10-0024 6745 N. GSB Add Demo $55,205.02 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to demolish a building and to make site improvements. Terry Ogle - Design & Construction Manager Ghassan Ariqat - Project manager/director Glenn Suitor - DB Oversight Manager
CP 1 HSR 13-06 167 5/23/2018 Tutor Perini / Zachry/Parsons Third-party Related Utility Reloc UPRR CTC Sys - Design $244,208.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to move utilities due to construction impacts to Union Pacific Railroad Centralized Traffic Control System in various locations. Terry Ogle - Design & Construction Manager Ghassan Ariqat - Project manager/director Glenn Suitor - DB Oversight Manager
CP 1 HSR 13-06 70 5/23/2018 Tutor Perini / Zachry/Parsons Third-party Related Fresno St UPRR Bridge Struc - Design $349,138.00 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to design the Union Pacific Railroad Bridge over Fresno Street. Terry Ogle, Director of Design & Construction Ghassan Ariqat, Project Manager/Director Glenn Suitor, D-B Oversight Manager
CP 1 HSR 13-06 205 5/16/2018 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications Painting Fresno Viaduct $80,476.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to apply aesthetic paint to exposed surfaces of the Fresno River Viaduct to make the structure look the same throughout. Terry Ogle - Design & Construction Manager Ghassan Ariqat - Project manager/director Glenn Suitor - DB Oversight Manager
CP 1 HSR 13-06 204 5/16/2018 Tutor Perini / Zachry/Parsons Third-party Related Church Ave BNSF & HST OH Structure $176,404.90 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for additional design at the Church Avenue Grade Separation in Fresno. Terry Ogle - Design & Construction Manager Ghassan Ariqat - Project manager/director Glenn Suitor - DB Oversight Manager
CP 1 HSR 13-06 179 5/16/2018 Tutor Perini / Zachry/Parsons Third-party Related Maintain Access to Road 33 at Ave 7 $401,421.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to design Avenue 7 overcrossing as a two span bridge instead of a single span bridge and to provide access to Madera County Road 33 west of the future high-speed rail system. Terry Ogle - Design & Construction Manager Ghassan Ariqat - Project manager/director Glenn Suitor - DB Oversight Manager
CP 1 HSR 13-06 42.2 5/16/2018 Tutor Perini / Zachry/Parsons Administrative Credit for Addtl Space 1401 Fulton ($2,453.74) This is a change to a contract for design and construction services in the Central Valley. The contractor is leasing office space at 1401 Fulton Street in Fresno to the Authority. A previous change order had provided $50,000 for a five-month lease extension. This change credits the Authority a portion of those costs. Terry Ogle, Director of Design & Construction Ghassan Ariqat, Project Manager/Director Glenn Suitor, D-B Oversight Manager
CP 1 HSR 13-06 200 4/18/2018 Tutor Perini / Zachry/Parsons Third-party Related K. Morgan Relocation - Belmont $2,204,171.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to design and construct the Kinder Morgan 12 inch petroleum pipeline that is in the way of the Belmont bridge work. Terry Ogle - Design & Construction Manager Ghassan Ariqat - Project manager/director Glenn Suitor - DB Oversight Manager
CP 1 HSR 13-06 197 4/18/2018 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications Opaque Solid Test Panels $14,218.00 This is a change to the contract for design and construction services in the Central Valley. The reason for the change is for design and construction of fence test panels. Terry Ogle - Design & Construction Manager Ghassan Ariqat - Project manager/director Glenn Suitor - DB Oversight Manager
CP 1 HSR 13-06 7.1 4/18/2018 Tutor Perini / Zachry/Parsons Environmental UNI: CL1/CL2 HazMat Supp1 $- This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to adjust the Hazardous Waste Removal quantities for the project. Terry Ogle - Director of Design & Construction Ghassan Ariqat - Project Manager/Director Glen Suitor - DB Oversight Manager
CP 1 HSR 13-06 199 4/11/2018 Tutor Perini / Zachry/Parsons Third-party Related K. Morgan Relocation - Herndon $5,883,644.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for design and construction services to move the Kinder Morgan 12 inch petroleum pipeline that is in the way of the Herndon underpass work. Joe Hedges, Chief Operating Officer Ghassan Ariqat - Project manager/director Glenn Suitor - DB Oversight Manager
CP 1 HSR 13-06 88.5 4/11/2018 Tutor Perini / Zachry/Parsons Environmental Additional Environmental Services $4,000,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to continue to provide environmental services to ensure the future high-speed rail system work complies with environmental requirements. Joseph Hedges - Chief Operating Officer Ghassan Ariqat, Project Manager/Director Glen Suitor - DB Oversight Manager
CP 1 HSR 13-06 192 4/3/2018 Tutor Perini / Zachry/Parsons Third-party Related UPRR Signal House at Herndon Avenue $43,786.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for redesign of the UPRR temporary signal system to avoid moving the UPRR operational facilities near Herndon Avenue and Golden State Boulevard. Terry Ogle - Design & Construction Manager Ghassan Ariqat - Project manager/director Glenn Suitor - DB Oversight Manager
CP 1 HSR 13-06 154 4/3/2018 Tutor Perini / Zachry/Parsons Third-party Related DL-0089 Clear Span BNSF ROW $432,025.43 This is a change to the contract for design services in the City of Fresno. The reason for this change is that the bent location of the Downtown Fresno Viaduct needed to be re-designed. Terry Ogle - Director of Design and Construction Ghassan Ariqat, Project Manager/Director Glenn Suitor, D-B Oversight Manager
CP 1 HSR 13-06 176 2/9/2018 Tutor Perini / Zachry/Parsons Utility Relocation COF Weber Ave. Realignment Affecting $47,544.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for additional design work for AT&T facilities between Ashlan and McKinley Avenues in Fresno impacted by the City of Fresno redesign of Webber Avenue. Terry Ogle - Design & Construction Manager Ghassan Ariqat - Project manager/director David Vallejos - DB Oversight Manager
CP 1 HSR 13-06 142 1/25/2018 Tutor Perini / Zachry/Parsons Third-party Related CHP Escort Reimbursement - COF Reqt. $300,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is a City of Fresno requirement for California Highway Patrol to escort large delivery loads within City of Fresno limits. Terry Ogle - Design & Construction Manager Ghassan Ariqat - Project manager/director David Vallejos - DB Oversight Manager
CP 1 HSR 13-06 184 1/24/2018 Tutor Perini / Zachry/Parsons Third-party Related BNSF Schmidt Creek Tributary Box $18,382.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for design services and third-party coordination to redesign Schmidt Creek Tributary culvert across the future high-speed rail system resulting from movement to the planned rail route. Terry Ogle - Design & Construction Manager Ghassan Ariqat - Project manager/director David Vallejos - DB Oversight Manager
CP 1 HSR 13-06 183 1/24/2018 Tutor Perini / Zachry/Parsons Third-party Related Accommodate 10' Access Road for UPRR $108,726.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for design services and third-party coordination activities to provide a 10-foot wide access road across Herndon Canal for UPRR access. Terry Ogle - Design & Construction Manager Ghassan Ariqat - Project manager/director David Vallejos - DB Oversight Manager
CP 1 HSR 13-06 180 1/24/2018 Tutor Perini / Zachry/Parsons Third-party Related Westside Shoofly single Track Shift $85,585.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for design costs to protect the existing Kinder Morgan pipeline and to modify the UPRR shoefly (rail bypass) at that location. Terry Ogle - Design & Construction Manager Ghassan Ariqat - Project manager/director David Vallejos - DB Oversight Manager
CP 1 HSR 13-06 141 1/24/2018 Tutor Perini / Zachry/Parsons Third-party Related Intrusion Protection Barrier Design $399,153.64 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to redesign a barrier preventing derailed conventional freight trains intruding into the high-speed rail system and portions of the Fresno Trench to comply with updated design criteria. Terry Ogle - Design & Construction Manager Ghassan Ariqat - Project manager/director David Vallejos - DB Oversight Manager
CP 1 HSR 13-06 120 1/24/2018 Tutor Perini / Zachry/Parsons Third-party Related General Order and Settlement Aggree $345,531.51 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to move AT&T facilities out of the way of the future high-speed rail system. Terry Ogle, Director of Design & Construction Ghassan Ariqat, Project Manager/Director David Vallejos, DB Oversight Manager
CP 1 HSR 13-06 14.1 1/19/2018 Tutor Perini / Zachry/Parsons Administrative Revised Design Variance Request Form $- This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to an administrative change to revise the form used to request variances to the design criteria used on the project. Steven Milton - Design & Construction Manager Ghassan Ariqat, Project Manager/Director David Vallejos - DB Oversight Manager
CP 1 HSR 13-06 127 1/18/2018 Tutor Perini / Zachry/Parsons Third-party Related Downtown HST Track Alignment- Design $360,183.01 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for design services to revise the future track allignment and associated facilities at Fresno Station. Terry Ogle, Director of Design & Construction Ghassan Ariqat, Project Manager/Director David Vallejos, DB Oversight Manager
CP 1 HSR 13-06 182 1/12/2018 Tutor Perini / Zachry/Parsons Third-party Related Relocation of the Kinder Morgan Pipe $1,825,656.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to move the Kinder Morgan pipeline near Dry Creek Canal out of the way of the future high-speed rail system. Steve Milton - Design & Construction Manager Ghassan Ariqat - Project manager/director David Vallejos - DB Oversight Manager
CP 1 HSR 13-06 181 12/20/2017 Tutor Perini / Zachry/Parsons Environmental WEF for the Exclusion of CTS $1,607,740.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for new fence material to protect the California Tiger Salamander along the construction zone. Terry Ogle - Design & Construction Manager Ghassan Ariqat - Project manager/director David Vallejos - DB Oversight Manager
CP 1 HSR 13-06 74 12/20/2017 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications Maintain Access to Road 33 at Ave 7 $1,615,455.00 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to construct a wider bridge to take Avenue 7 over the future high-speed rail system. Terry Ogle, Design & Construction Manager Ghassan Ariqat, Project Manager/Director David Vallejos, D-B Oversight Manager
CP 1 HSR 13-06 160 12/19/2017 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications Construction Grounding and Bonding $702,843.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for additional electrical grounding and bonding at intermediate support columns for all bridges over which high-speed trains will travel. Terry Ogle - Design & Construction Manager Ghassan Ariqat - Project manager/director David Vallejos - DB Oversight Manager
CP 1 HSR 13-06 175 12/7/2017 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications Flagging And Temperary Signal Rd.26 $229,159.76 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to provide temporary flagging and provide and operate a temporary traffic signal at a road intersection as requested by County of Madera during construction activities. Terry Ogle - Design & Construction Manager Ghassan Ariqat - Project manager/director David Vallejos - DB Oversight Manager
CP 1 HSR 13-06 169 12/7/2017 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications Excluded ICE Assessments for Execute $144,088.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for additional independent engineering assessments that were excluded from several previous change orders, potential change orders, and task order proposals. Terry Ogle - Design & Construction Manager Ghassan Ariqat - Project manager/director David Vallejos - DB Oversight Manager
CP 1 HSR 13-06 168 12/7/2017 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications DL-00130 R1 AR Fence Reqts - Design $83,683.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to pay for additional design related to revised design criteria for fence to keep people out of the future high-speed rail system. Terry Ogle - Design & Construction Manager Ghassan Ariqat - Project manager/director David Vallejos - DB Oversight Manager
CP 1 HSR 13-06 87.2 11/10/2017 Tutor Perini / Zachry/Parsons Third-party Related Top Down Const SR 180 Supplemental 2 $300,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to continue to perform Construction Zone Enhanced Enforcement Program (enhanced traffic mangement using California Highway Patrol) at State Route 180. Terry Ogle, Director of Design & Construction Ghassan Ariqat, Project Manager/Director David Vallejos, D-B Oversight Manager
CP 1 HSR 13-06 166 11/9/2017 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications Drainage Basins at E Muscat - Design $25,459.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to re-design the drainage basins under East Muscat Avenue Viaduct. Terry Ogle - Design & Construction Manager Ghassan Ariqat - Project manager/director David Vallejos - DB Oversight Manager
CP 1 HSR 13-06 178 10/23/2017 Tutor Perini / Zachry/Parsons Third-party Related Partial Comp. for COF Utility Agrmnt $2,000,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for additional construction as a result of the final utility agreement with the City of Fresno. This agreement, executed after the construction contract was awarded included additional work due to update City of Fresno standards. Steve Milton - Design & Construction Manager Ghassan Ariqat - Project manager/director David Vallejos - DB Oversight Manager
CP 1 HSR 13-06 177 10/11/2017 Tutor Perini / Zachry/Parsons Administrative UNI: Transfer Funds from Provisional ($35,000,000.00) This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to credit the Authority from the contractor's Utility Provisional Sum and the Construction Contract Work Provisional Sum. Scott Jarvis, Chief Engineer Ghassan Ariqat - Project manager/director David Vallejos - DB Oversight Manager
CP 1 HSR 13-06 133 10/11/2017 Tutor Perini / Zachry/Parsons Third-party Related Madera Settlement Ave 9,12,13 OH $18,629,963.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to design and construct Avenue 9 and Avenue 12 as four-lane bridges and to remove the requirement to construct Avenue 13. Scott Jarvis, Chief Engineer Ghassan Ariqat, Project Manager/Director David Vallejos, DB Oversight Manager
CP 1 HSR 13-06 151 9/27/2017 Tutor Perini / Zachry/Parsons Environmental Environmental Scope Reduction ($1,375,000.00) This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to credit the Authority for environmental work. This work will be paid under change order 88. Terry Ogle, Director of Design & Construction Ghassan Ariqat, Project Manager/Director David Vallejos, DB Oversight Manager
CP 1 HSR 13-06 174 9/21/2017 Tutor Perini / Zachry/Parsons Dispute Resolution Settlement of disputed PCO's $383,889.00 This is a change to a contract for design and construction services in the Central Valley. This change concludes negotiations regarding 20 disputed items relating to design services. Steve Milton - Design & Construction Manager Ghassan Ariqat - Project manager/director David Vallejos - DB Oversight Manager
CP 1 HSR 13-06 55 9/19/2017 Tutor Perini / Zachry/Parsons Third-party Related UPRR Boundary Fence $57,266.00 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to conduct additional work associated with a fence along the east side of land owned by Union Pacific Railroad. Steve Milton, Design & Construction Manager Ghassan Ariqat, Project Manager/Director David Vallejos, D-B Oversight Manager
CP 1 HSR 13-06 170.1 9/13/2017 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications Shaw Vertical Clearance- Design Supp $44,902.33 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to supplement Change Order number 170 to pay for redesign for the West Shaw Avenue bridge and related road design. Steven Milton - Design and Construction Manager Ghassan Ariqat - Project manager/director David Vallejos - DB Oversight Manager
CP 1 HSR 13-06 69 9/13/2017 Tutor Perini / Zachry/Parsons Third-party Related UPRR 10 foot Access Road $128,602.12 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to design an access road along Union Pacific Railroad land. This access road is required by a maintenance agreement between Union Pacific Railroad and the Authority. Steven Milton - Design & Construction Manager Ghassan Ariqat, Project Manager/Director David Vallejos, D-B Oversight Manager
CP 1 HSR 13-06 62 9/13/2017 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications Methacrylate Overlay - Tuolumne Deck $46,366.06 This is a change to a contract for construction services in the Central Valley. The reason for this change is to apply a protective coating to the Tuolumne Street bridge deck. Steven Milton - Design and Construction Manager Ghassan Ariqat, Project Manager/Director David Vallejos, D-B Oversight Manager
CP 1 HSR 13-06 173 8/29/2017 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related Addtl Trestle Work SJRV Oberti Farms $1,592,832.40 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to redesign and construct a continuous trestle from the south bank to the north bank of the San Joaquin River to provide access to the San Joaquin River Viaduct. Terry Ogle - Design & Construction Manager Ghassan Ariqat - Project manager/director John C. Lee DB Oversight Manager
CP 1 HSR 13-06 136 8/29/2017 Tutor Perini / Zachry/Parsons Third-party Related Reconfig Stanislaus and Tuolumne St $12,866,824.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to design and construct a bridge at Toulumne Street instead of Stanislaus Street and associated road way modifications. Terry Ogle, Director of Design & Construction Ghassan Ariqat, Project Manager/Director John C. Lee, DB Oversight Manager
CP 1 HSR 13-06 80.1 8/29/2017 Tutor Perini / Zachry/Parsons Administrative Continued Site Camera Hosting Fees $30,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to continue to provide time-lapse documentation of the construction of the future high-speed rail system at Fresno River Viaduct, Tuolumne Bridge and Starte Route 180 trench. Terry Ogle, Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee, D-B Oversight Manager
CP 1 HSR 13-06 171 8/23/2017 Tutor Perini / Zachry/Parsons Third-party Related SR-145 Caltrans Project Report $200,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for design and construction services required to implement the changes for the State Route 145 bridge from 90 feet to 125 feet 3 inches in length. Terry Ogle - Design & Construction Manager Ghassan Ariqat - Project manager/director John C. Lee DB Oversight Manager
CP 1 HSR 13-06 170 8/14/2017 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications UNI: Shaw Vertical Clearance- Design $127,506.17 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to prepare a report to vary the design from the 27-foot vertical clearance requirements in the specification to 24-foot and to redesign the West Shaw Avenue bridge and road design. Terry Ogle - Design & Construction Manager Ghassan Ariqat - Project manager/director John C. Lee DB Oversight Manager
CP 1 HSR 13-06 172 8/10/2017 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications Safety and Security Certification $180,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to perform safety and security planning activities during final design, including revising the plan and providing a certification package prior to work starting. Terry Ogle - Design & Construction Manager Ghassan Ariqat - Project manager/director John C. Lee DB Oversight Manager
CP 1 HSR 13-06 88.4 8/1/2017 Tutor Perini / Zachry/Parsons Environmental Additional Environmental Services $3,000,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to continue to provide environmental services to ensure the future high-speed rail system work complies with environmental requirements. Terry Ogle, Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee, D-B Oversight Manager
CP 1 HSR 13-06 48 6/26/2017 Tutor Perini / Zachry/Parsons Utility Relocation PG&E & AT&T Facilies Relocations $92,804,594.26 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to transfer responsibility of services from the Authority to the contractor. The transferred services are to manage the design and construction of PG&E and AT&T facilities to move them out of the way of future high-speed rail construction. Scott Jarvis, Chief Engineer Ghassan Ariqat, Project Manager/Director John C. Lee, D-B Oversight Manager
CP 1 HSR 13-06 97.1 6/19/2017 Tutor Perini / Zachry/Parsons Third-party Related Westside Wye Shoofly Alt 1 - Design $269,984.28 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to design the railroad detour (shoofly) from the chosen alternative evaluated in contract change order number 97 to make way for the high-speed rail system. Terry Ogle, Director of Design & Construction Ghassan Ariqat, Project Manager/Director John C. Lee, D-B Oversight Manager
CP 1 HSR 13-06 163 6/13/2017 Tutor Perini / Zachry/Parsons Third-party Related Ventura Street Underpass UPRR Bridge $144,970.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to perform design required to widen the Union Pacific Railroad Ventura Street underpass to enable the construction of the future high-speed rail system. Terry Ogle - Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee, DB Oversight Manager
CP 1 HSR 13-06 162 6/13/2017 Tutor Perini / Zachry/Parsons Third-party Related Tulare Street Underpass UPRR Bridge $137,189.50 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to perform design required to widen the Union Pacific Railroad Tulare Street underpass to enable the construction of the future high-speed rail system. Terry Ogle - Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee, DB Oversight Manager
CP 1 HSR 13-06 121 6/13/2017 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications Combined Horizontal & Vertical Curve $120,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to redesign the high-speed rail alignment where horizontal and vertical curves overlap and for track infrastructure at the future Fresno station. Terry Ogle, Director of Design & Construction Ghassan Ariqat, Project Manager/Director John C. Lee, DB Oversight Manager
CP 1 HSR 13-06 165 6/1/2017 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications Solid Barrier on Type 2 Overhead $186,957.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to design new barriers on all bridges that span the future high-speed rail system. Terry Ogle - Design and Construction Manager (Acting) Ghassan Ariqat, Project Manager/Director John C. Lee, DB Oversight Manager
CP 1 HSR 13-06 132 6/1/2017 Tutor Perini / Zachry/Parsons Utility Relocation HST Drainage Modifications - Design $31,814.96 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to provide design services to modify designs for drainaige of the future high-speed rail system. Terry Ogle - Design and Construction Manager (Acting) Ghassan Ariqat, Project Manager/Director John C. Lee, DB Oversight Manager
CP 1 HSR 13-06 164 5/26/2017 Tutor Perini / Zachry/Parsons Environmental Final Determination of Environmental ($1,082,684.94) This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to provide the Authority credit for settlement of 10 previous change orders. Terry Ogle, Director of Design & Construction Ghassan Ariqat, Project Manager/Director John C. Lee, DB Oversight Manager
CP 1 HSR 13-06 128 5/23/2017 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications Grounding and Bonding Project Struct $85,280.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to provide additional design services for electrical grounding and bonding at a bridge. Terry Ogle, Director of Design & Construction Ghassan Ariqat, Project Manager/Director John C. Lee, DB Oversight Manager
CP 1 HSR 13-06 158 5/17/2017 Tutor Perini / Zachry/Parsons Utility Relocation BP-12 Road 27 $374,345.62 This is a change to the contract for design and construction services in the Central Valley. The reason for the change is to move AT&T facilities out of the way of the future high-speed rail system at Road 27 in Madera County. Terry Ogle, Director of Design & Construction Ghassan Ariqat, Project Manager/Director John C. Lee, DB Oversight Manager
CP 1 HSR 13-06 157 5/17/2017 Tutor Perini / Zachry/Parsons Utility Relocation BP-8 Hardy, Muscat, Central & Ameri $640,033.74 This is a change to the contract for design and construction services in the Central Valley. The reason for the change is to move AT&T facilities out of the way of the future high-speed rail system at Hardy, Muscat, Central and American Avenues in the City of Fresno. Terry Ogle, Director of Design & Construction Ghassan Ariqat, Project Manager/Director John C. Lee, DB Oversight Manager
CP 1 HSR 13-06 156 5/17/2017 Tutor Perini / Zachry/Parsons Utility Relocation BP-07 Herndon Canal to Ashlan $7,251,599.50 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to pay AT&T to move its services out of the way of the future high-speed rail system. This work is coordinated by the general contractor who is responsible for designing and constructing the future system from Herndon Canal to Ashlan Avenue in the City of Fresno. Scott Jarvis, Chief Engineer Ghassan Ariqat, Project Manager/Director John C. Lee, DB Oversight Manager
CP 1 HSR 13-06 159 5/16/2017 Tutor Perini / Zachry/Parsons Utility Relocation Belmont Avenue OH - Relocate Column $750,000.00 This is a change to the contract for design services in the Central Valley. The reason for the change is to complete additional design work related to the bridge at Belmont Avenue and the requirements of the Union Pacific Rail Road. Terry Ogle, Director of Design & Construction Ghassan Ariqat, Project Manager/Director John C. Lee, DB Oversight Manager
CP 1 HSR 13-06 161 5/15/2017 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications Muscat Revised Spans - Design $446,965.80 This is a change to the contract for design services in the Central Valley. The reason for the change is to revise the design for the bridge over the future high-speed rail system at Muscat Avenue. Terry Ogle, Director of Design & Construction Ghassan Ariqat, Project Manager/Director John C. Lee, DB Oversight Manager
CP 1 HSR 13-06 126 5/15/2017 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications N. Golden State Realignment - Design $69,006.51 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to perform design for the movement of Golden State Boulevard. Terry Ogle, Director of Design & Construction Ghassan Ariqat, Project Manager/Director John C. Lee, DB Oversight Manager
CP 1 HSR 13-06 153 5/8/2017 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications Collision Pushover Analysis for SJRV $42,808.64 This is a change to the contract for design services in the Central Valley. The reason for the change is for additional engineering analysis to evaluate the amount of force the San Joaquin River Viaduct structure can withstand. Terry Ogle, Acting Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee, DB Oversight Manager
CP 1 HSR 13-06 42.1 5/5/2017 Tutor Perini / Zachry/Parsons Administrative Supplemental Addtl Space 1401 Fulton $50,000.00 This is a change to a contract for design and construction services in the Central Valley. The contractor is leasing office space at 1401 Fulton Street in Fresno to the Authority. The reason for this change is to extend the current leasing agreement by five months. Terry Ogle, Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee, D-B Oversight Manager
CP 1 HSR 13-06 152 5/2/2017 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications Olive OH Relocate Column Out of UPRR $413,984.07 This is a change to the contract for design services in the Central Valley. The reason for this change is to complete additional design work related to the bridge at Olive Avenue and the requirements of the Union Pacific Rail Road. Terry Ogle, Director of Design & Construction Ghassan Ariqat, Project Manager/Director John C. Lee, DB Oversight Manager
CP 1 HSR 13-06 88.3 5/1/2017 Tutor Perini / Zachry/Parsons Environmental Additional Environmental Services $3,000,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to continue to provide environmental services to ensure the future high-speed rail system work complies with environmental requirements. Terry Ogle, Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee, D-B Oversight Manager
CP 1 HSR 13-06 134 4/26/2017 Tutor Perini / Zachry/Parsons Third-party Related UNI: Permanent Fence at SJRV $27,237.67 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to construct a chain link fence between the future high-speed rail system and Camp Pashayan. Terry Ogle, Director of Design & Construction Ghassan Ariqat, Project Manager/Director John C. Lee, DB Oversight Manager
CP 1 HSR 13-06 131 4/26/2017 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications UNI: System Site Revisions $33,215.62 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to incorporate underground rail System Site Facility changes into the design. Terry Ogle, Director of Design & Construction Ghassan Ariqat, Project Manager/Director John C. Lee, DB Oversight Manager
CP 1 HSR 13-06 147 4/17/2017 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications Belmont Overcrossing Design Simulat $12,901.47 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to prepare a design simulation for the West Belmont Avenue Overcrossing to show what it would look like when finished. Terry Ogle - Director of Design and Construction Ghassan Ariqat - Project Manager/Director John C. Lee - DB Oversight Manager
CP 1 HSR 13-06 129 4/6/2017 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications Train Control Facilities $36,399.87 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to design additional Train Control Facility Sites at two locations. Terry Ogle, Director of Design & Construction Ghassan Ariqat, Project Manager/Director John C. Lee, DB Oversight Manager
CP 1 HSR 13-06 88.2 3/30/2017 Tutor Perini / Zachry/Parsons Environmental Additional Environmental Services $1,200,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to continue to perform environmental services as part of the Authority's environmental commitments. Terry Ogle, Director of Design & Construction Ghassan Ariqat, Project Manager/Director John C. Lee, D-B Oversight Manager
CP 1 HSR 13-06 71 3/22/2017 Tutor Perini / Zachry/Parsons Environmental Building HazMat PS Budget Increase $8,000,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to increase the budget for the removal of hazardous materials from properties acquired by the Authority. Scott Jarvis - Chief Engineer Chassan Ariqat - Project Manager/Director John C. Lee - DB Oversight Manager
CP 1 HSR 13-06 149 3/21/2017 Tutor Perini / Zachry/Parsons Utility Relocation PG&E Const. Electrical Package K $1,535,027.90 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to move PG&E electrical distribution lines in the County of Fresno and County of Madera, to make way for the future high-speed rail system. Hugo Mejia, Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee, D-B Oversight Manager
CP 1 HSR 13-06 148 3/21/2017 Tutor Perini / Zachry/Parsons Utility Relocation PG&E Gas Distribution Const. Pkg. J $115,730.87 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to move PG&E gas distribution lines near Hardy Avenue in the City of Fresno, to make way for the future high-speed rail system. Hugo Mejia, Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee, D-B Oversight Manager
CP 1 HSR 13-06 68 3/21/2017 Tutor Perini / Zachry/Parsons Third-party Related Grade & Reloc. Pump Stn. at Basin EE $81,080.35 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to move storm water infrastructure out of the way of the future high-speed rail system at the Fresno Metropolitan Flood Control District Basin EE. Hugo Mejia, Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee, D-B Oversight Manager
CP 1 HSR 13-06 63 3/21/2017 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications Belmont Avenue Design Refinement $103,900.58 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to do additional roadway design and re-design at Belmont Avenue. Hugo Mejia, Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee, D-B Oversight Manager
CP 1 HSR 13-06 144 3/20/2017 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related ROW Access Lawson Prop. MF-10-0041 $1,373.06 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to move the high-speed train access restricting fence 15 feet east of an acquired parcel to provide access to an adjacent business owner. Hugo Mejia, Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee, D-B Oversight Manager
CP 1 HSR 13-06 97 3/15/2017 Tutor Perini / Zachry/Parsons Third-party Related Westside Wye Shoofly Design Study $89,697.99 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to evaluate two alternatives for temporary freight rail detours (shoofly) while building the high-speed rail trench in the City of Fresno. Hugo Mejia, Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee, D-B Oversight Manager
CP 1 HSR 13-06 100 3/14/2017 Tutor Perini / Zachry/Parsons Third-party Related DL-0097 City of Fresno Well Site 162 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to move the City of Fresno (COF) well site 162 to to a more secure location then previously agreed. This is a zero-cost change order. Hugo Mejia, Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee, D-B Oversight Manager
CP 1 HSR 13-06 146 3/10/2017 Tutor Perini / Zachry/Parsons Utility Relocation PG&E Gas Transmission Design Pkg. Z $116,123.57 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to move PG&E gas transmission utilities in the County of Madera and the City of Fresno to make way for the future high-speed rail system. Hugo Mejia, Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee, D-B Oversight Manager
CP 1 HSR 13-06 143 3/10/2017 Tutor Perini / Zachry/Parsons Utility Relocation PGE Design Elec Packages S, T and U $693,932.44 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to move PG&E electrical utilities at three locations in the County of Madera and the City of Fresno to make way for the future high-speed rail system Hugo Mejia, Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee, D-B Oversight Manager
CP 1 HSR 13-06 145 3/9/2017 Tutor Perini / Zachry/Parsons Utility Relocation PG&E Design Gas Dist. Pkg. W, X & Y $427,925.36 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to move PG&E gas utilities at three locations in the County of Madera and the City of Fresno to make way for the future high-speed rail system. Hugo Mejia, Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee, D-B Oversight Manager
CP 1 HSR 13-06 88.1 2/9/2017 Tutor Perini / Zachry/Parsons Environmental Additional Environmental Services $3,000,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to continue to perform environmental services as part of the Authority's environmental commitments. Terry Ogle, Director of Design & Construction Ghassan Ariqat, Project Manager/Director John C. Lee, D-B Oversight Manager
CP 1 HSR 13-06 124 2/2/2017 Tutor Perini / Zachry/Parsons Utility Relocation COF 24" and 30" Waterline Ventura $26,216.40 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is change is to provide design services to meet the new standards of the City of Fresno to resolve conflicts between Ventura Street and City of Fresno water mains. Hugo Mejia, Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee, DB Oversight Manager
CP 1 HSR 13-06 79 2/2/2017 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications GS Blvd 68' Widening(West Ave-SR99) $375,880.19 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to widen Golden State Boulevard and re-design the McKinley bridge over the future high-speed rail system. Hugo Mejia, Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee, D-B Oversight Manager
CP 1 HSR 13-06 59 2/2/2017 Tutor Perini / Zachry/Parsons Utility Relocation Belmont Ave Final Facilty Plan $72,331.71 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to provide roadway design services on Belmont Avenue. The designs are to include ADA-compliant ramps, accommodate truck deliveries, and modify intersections. Designs are to follow City of Fresno standards. Hugo Mejia, Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee, D-B Oversight Manager
CP 1 HSR 13-06 57 2/2/2017 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications CuldaSac at East Ave Desig Refinemen $5,462.34 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to design a cul-de-sac on East Avenue in accordance with City of Fresno standards. Hugo Mejia, Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee, D-B Oversight Manager
CP 1 HSR 13-06 137 1/31/2017 Tutor Perini / Zachry/Parsons Utility Relocation Tuolumne Vault Relocation $1,464,552.45 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to move PG&E electrical distribution lines along Tuolumne Street in the City of Fresno out of the way of the future high-speed rail system. Hugo Mejia, Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee, D-B Oversight Manager
CP 1 HSR 13-06 13.3 1/31/2017 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related BETP Implementation Cost Komoto Bldg $42,725.84 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to conduct surveys and monitoring of construction activities on the Komoto’s Department Store building in Fresno. Hugo Mejia - Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee - DB Oversight Manager
CP 1 HSR 13-06 13.2 1/31/2017 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related BETP Implementation Cost B of A $52,810.41 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to conduct surveys and monitoring of construction activities on the Bank of America building in Fresno. Hugo Mejia - Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee - DB Oversight Manager
CP 1 HSR 13-06 72 1/26/2017 Tutor Perini / Zachry/Parsons Utility Relocation ATT BP-04 Ashlan to McKinley $9,694,318.86 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to move AT&T facilities out of the way of the future high-speed rial system between Ashlan and McKinley Avenues in Fresno. Scott Jarvis, Chief Engineer Ghassan Ariqat, Project Manager/Director John C. Lee, D-B Oversight Manager
CP 1 HSR 13-06 51 12/22/2016 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications Design Changes for Various CO $613,341.51 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to complete additional design work at 14 locations. Terry Ogle, Director of Design & Construction Ghassan Ariqat, Project Manager/Director John C. Lee, DB Oversight Manager
CP 1 HSR 13-06 94 12/21/2016 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications Subcontract with Ferreira Coastal $110,968.69 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is move an AT&T facility out of the way of the future high-speed rail system. Hugo Mejia, Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee, D-B Oversight Manager
CP 1 HSR 13-06 64 12/21/2016 Tutor Perini / Zachry/Parsons Utility Relocation Installation of an Underground Elect $30,963.46 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to move AT&T facilities out of the way of the future high-speed rial system at North Golden State Boulevard. Hugo Mejia, Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee, D-B Oversight Manager
CP 1 HSR 13-06 82.2 12/15/2016 Tutor Perini / Zachry/Parsons Utility Relocation Valverde Construction for Pothole $377,454.46 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to preform potholing to identify a 24 inch PG&E Gas Transmission Line. Hugo Mejia, Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee, D-B Oversight Manager
CP 1 HSR 13-06 37 12/15/2016 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications Golden State Blvd. Widening Design $7,644.97 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to design roadway and drainage for Golden State Boulevard in Fresno. Hugo Mejia - Design & Construction Manager Ghassan Ariqat, Interim Project Manager/Director John C. Lee - DB Oversight Manager
CP 1 HSR 13-06 110 12/13/2016 Tutor Perini / Zachry/Parsons Utility Relocation PGE GT Conflict Designs1-003,005,018 $215,350.25 This is a change to the contract for design and construction services in the Central Valley. The reason for the change is to move PG&E facilities out of the way of the future high-speed rail system. Hugo Mejia, Design & Construction Manager Ghassan Ariqat, Interim Project Manager/Director John C. Lee, DB Oversight Manager
CP 1 HSR 13-06 73 12/13/2016 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications G St Realignment Impacts Design $53,006.53 This is a change to a contract for design and construction services in the Central Valley.The reason for this change is to redesign the future high-speed rail alignment due to changes related to the location of G Street in Fresno. Hugo Mejia, Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee, D-B Oversight Manager
CP 1 HSR 13-06 123 12/8/2016 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related Service Disconnects $3,000,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to pay for utility disconnection fees for PG&E and AT&T utilities prior to their removal. Terry Ogle, Director of Design & Construction Ghassan Ariqat, Interim Project Manager/Director John C. Lee, DB Oversight Manager
CP 1 HSR 13-06 140 11/23/2016 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related Conceptual Design for Eminent Domain $7,644.09 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to relocate a Fresno Metropolitan Flood Control District (FMFCD) storm drain. FMFCD is a public entity that provides flood control and urban storm water services in the City of Fresno. Hugo Mejia, Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee, D-B Oversight Manager
CP 1 HSR 13-06 99.1 10/12/2016 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related Completion Deadline Ex/Res.- Suppl. $13,612,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to accelerate work in the contract by 7 months to recover from delays in buying land. Scott Jarvis - Chief Engineer Ghassan Ariqat, Project Manager/Director
CP 1 HSR 13-06 108 10/10/2016 Tutor Perini / Zachry/Parsons Utility Relocation Additional Design Work PGE Conflicts $279,188.75 This is a change to the contract for design services in the Central Valley. The reason for the change is to move PG&E facilities out of the way of the future high-speed rail system at Avenue 17 and Roads 26 and 27 in Madera County. Hugo Mejia, Design & Construction Manager Ghassan Ariqat, Interim Project Manager/Director John C. Lee, DB Oversight Manager
CP 1 HSR 13-06 104 10/10/2016 Tutor Perini / Zachry/Parsons Utility Relocation PG&E Elec 8 Central Malaga America $145,569.55 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to move 8 PG&E electrical utilities at Central, Malaga and American Avenues in Fresno out of the way of the of the future high-speed rail system. Hugo Mejia - Design & Construction Manager Ghassan Ariqat - Interim Project Manager/Director John C. Lee - DB Oversight Manager
CP 1 HSR 13-06 103 10/10/2016 Tutor Perini / Zachry/Parsons Utility Relocation PGE Design Package G $444,116.88 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to move PG&E utilities out of the way of the future high-speed rail system. Hugo Mejia - Design & Construction Manager Ghassan Ariqat - Interim Project Manager/Director John C. Lee - DB Oversight Manager
CP 1 HSR 13-06 47 10/10/2016 Tutor Perini / Zachry/Parsons Utility Relocation Project Scoping for the New PG&E $17,250.00 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to prepare a Planning Information Package for a new PG&E Gas Regulator Station. Hugo Mejia, Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee, D-B Oversight Manager
CP 1 HSR 13-06 119 9/26/2016 Tutor Perini / Zachry/Parsons Third-party Related Railroad Utility App. License Fees $860,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to acquire utility crossing, right of entry and permit fees to railroads. Hugo Mejia, Design & Construction Manager Ghassan Ariqat, Interim Project Manager/Director John C. Lee, DB Oversight Manager
CP 1 HSR 13-06 117 9/26/2016 Tutor Perini / Zachry/Parsons Administrative Bond & Insurance Resolution $379,751.28 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is is for additional bonding and insurance costs for previous change orders issued through July 1, 2016. Hugo Mejia, Design & Construction Manager Ghassan Ariqat, Interim Project Manager/Director John C. Lee, DB Oversight Manager
CP 1 HSR 13-06 116 9/26/2016 Tutor Perini / Zachry/Parsons Third-party Related Signalized Intersection at Olive Ave $34,844.60 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to perform design required to add a traffic signal at Olive Avenue and Roeding Park Entrance according to City of Fresno requirements. Hugo Mejia, Design & Construction Manager Ghassan Ariqat, Interim Project Manager/Director John C. Lee, DB Oversight Manager
CP 1 HSR 13-06 115 9/26/2016 Tutor Perini / Zachry/Parsons Third-party Related Ventura Street and F Street Inter. $43,024.31 This is a change to a contract for design services in the Central Valley. The reason for the change is to design the traffic signals at the intersection of Ventura Street and F Street according to City of Fresno requirements. Hugo Mejia, Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee, DB Oversight Manager
CP 1 HSR 13-06 113 9/26/2016 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications Steel Structures Inc. Building Fire $32,076.00 This is a change to a contract for design services in the Central Valley. The reason for this change is to design fencing to keep people out of the future high-speed rail system at a specific property in Madera County. Hugo Mejia, Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee, DB Oversight Manager
CP 1 HSR 13-06 111 9/26/2016 Tutor Perini / Zachry/Parsons Utility Relocation Add Design Work PGE 21 Conflicts $370,082.07 This is a change to a contract for design services in the Central Valley. The reason for the change is to pay Pacific Gas and Electric Company to move its facilities out of the way of the future high-speed rail system. This work is coordinated by the general contractor who is responsible for designing and constructing the future system in the in the City of Fresno. Hugo Mejia, Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee, DB Oversight Manager
CP 1 HSR 13-06 60 9/26/2016 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications SE Ave Geometric Changes FB FEIR $14,110.08 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to do additional design for sidewalks and turning lanes on East Belgravia Avenue. Hugo Mejia, Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee, D-B Oversight Manager
CP 1 HSR 13-06 114 9/23/2016 Tutor Perini / Zachry/Parsons Third-party Related Signalized Intersection at Belmont $34,844.60 This is a change to a contract for design services in the Central Valley. The reason for the change is to design the traffic signals at the intersection of Belmont Street and Stafford Street according to City of Fresno requirements. Hugo Mejia, Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee, DB Oversight Manager
CP 1 HSR 13-06 105 9/7/2016 Tutor Perini / Zachry/Parsons Utility Relocation AT&T Ductbank Install Madera Co. $2,287,112.23 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to move AT&T facilities at Avenues 7, 8, 9, 10, 12, and 13 out of the way of the future high-speed rail system. Terry Ogle - Director of Design and Construction Ghassan Ariqat - Project Manager/Director John C. Lee - DB Oversight Manager
CP 1 HSR 13-06 109 9/2/2016 Tutor Perini / Zachry/Parsons Utility Relocation Const. Services ATT Barrel Vault $6,427.79 This is a change to the contract for design and construction services in the Central Valley. The reason for the change is to move AT&T facilities out of the way of the future high-speed rail system at the intersection of Raymond Road and State Route 145 in Madera County. Hugo Mejia, Design & Construction Manager Ghassan Ariqat, Interim Project Manager/Director John C. Lee, DB Oversight Manager
CP 1 HSR 13-06 112 8/23/2016 Tutor Perini / Zachry/Parsons Utility Relocation ATT Ductbank Muscat Ave $19,509.17 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to pay AT&T to move its facilities out of the way of the future high-speed rail system. This work is coordinated by the general contractor who is responsible for designing and constructing the future system at Muscat Avenue in the City of Fresno. Hugo Mejia, Design & Construction Manager Ghassan Ariqat, Interim Project Manager/Director John C. Lee, DB Oversight Manager
CP 1 HSR 13-06 107 7/21/2016 Tutor Perini / Zachry/Parsons Utility Relocation AT&T Duct Bank Installation On Yale $167,826.04 This is a change to the contract for design and construction services in the Central Valley. The reason for the change is to move AT&T facilities out of the way of the future high-speed rail system at Yale Avenue in Fresno. Terry Ogle for Huge Mejia, Design & Construction Manager Ghassan Ariqat, Interim Project Manager/Director John C. Lee, DB Oversight Manager
CP 1 HSR 13-06 106 7/21/2016 Tutor Perini / Zachry/Parsons Utility Relocation ATT Facilities Relocate Rd 27 $166,636.98 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to move AT&T facilities at Road 27 out of the way of the future high-speed rail system. Hugo Mejia - Design & Construction Manager Ghassan Ariqat - Interim Project Manager/Director John C. Lee - DB Oversight Manager
CP 1 HSR 13-06 101 7/21/2016 Tutor Perini / Zachry/Parsons Utility Relocation ATT Vault Relocal Tuolumne OC $129,740.36 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to move AT&T facilities at the end of the Tuolumne Street Bridge in the City of Fresno, to make way for the future high-speed rail system. Hugo Mejia, Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee, D-B Oversight Manager
CP 1 HSR 13-06 92 7/21/2016 Tutor Perini / Zachry/Parsons Utility Relocation Design Electrical ET1-5,6,8,9 $671,540.77 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to move PG&E electrical transmission line services out of the way of the future high-speed rail system. Hugo Mejia, Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee, D-B Oversight Manager
CP 1 HSR 13-06 83 7/20/2016 Tutor Perini / Zachry/Parsons Utility Relocation PG&E Gas Distribution Relocations $897,162.06 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to relocate PG&E gas distribution lines out of the way of the future high-speed rail system. Hugo Mejia, Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee, D-B Oversight Manager
CP 1 HSR 13-06 98 7/5/2016 Tutor Perini / Zachry/Parsons Utility Relocation Install Ductbank Clinton & Belmont $26,428,542.16 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to move AT&T underground utilities at Clinton Avenue to Belmont Avenue, in the City of Fresno, to make way for the future high-speed rail system. Scott Jarvis - Chief Engineer Jim Laing, Project Manager/Director John C. Lee - DB Oversight Manager
CP 1 HSR 13-06 29.3 7/1/2016 Tutor Perini / Zachry/Parsons Environmental Extra Work Bio Services $600,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to continue to implement requirements of the California Department of Fish and Wildlife permits as part of the Authority's environmental commitments. Hugo Mejia - Design & Construction Manager James Laing - Project Director John C. Lee - DB Oversight Manager
CP 1 HSR 13-06 96 6/22/2016 Tutor Perini / Zachry/Parsons Utility Relocation UNI: UG Duct Bank Ave15 1/2, 15 $2,845,133.50 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to move AT&T underground utilities at Avenues 11, 15, and 15-1/2, in Madera Count to make way for the future high-speed rail system. Terry Ogle, Director of Design & Construction Jim Laing, Project Manager/Director John C. Lee, D-B Oversight Manager
CP 1 HSR 13-06 90 6/21/2016 Tutor Perini / Zachry/Parsons Utility Relocation PGE-Utility Conflict E1-116 Road 1/2 $1,624,717.55 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to move PG&E underground electrical utilities out of the way of the future high-speed rail system. Terry Ogle, Director of Design & Construction Jim Laing, Project Manager/Director John C. Lee, D-B Oversight Manager
CP 1 HSR 13-06 75.1 6/21/2016 Tutor Perini / Zachry/Parsons Utility Relocation UNI: Design PGE Dist. Conflicts $1,031,028.90 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to move PG&E utilities out of the way of the future high-speed rail system at 49 locations. Terry Ogle, Director of Design & Construction Jim Laing, Project Manager/Director John C. Lee, D-B Oversight Manager
CP 1 HSR 13-06 99 6/14/2016 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related Completion Deadline Ext/Resolution $49,900,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to add 17 months and additional budget to the contract to recognize the impact to the contractor caused by delays in buying land. Jeff Morales - Chief Executive Officer Ronald N. Tutor - Managing Partner
CP 1 HSR 13-06 82.1 6/8/2016 Tutor Perini / Zachry/Parsons Utility Relocation Additional Services SR 99 Realign $100,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to conduct surveying and potholing to identify PG&E and AT&T utility locations with the future high-speed rail system. This supplements change order 82 to add the State Route 99 project area. Hugo Mejia, Design & Construction Manager Jim Laing, Project Manager/Director John C. Lee, D-B Oversight Manager
CP 1 HSR 13-06 91 6/1/2016 Tutor Perini / Zachry/Parsons Utility Relocation Design - PGE Utility Conflict E1 $33,016.50 This is a change to a contract for design and construction services in the Central Valley. The reason for the change to move PG&E electric and gas utilities in Madera County out of the way of the future high-speed rail system. Terry Ogle, Director of Design & Construction Jim Laing, Project Manager/Director John C. Lee, D-B Oversight Manager
CP 1 HSR 13-06 93 5/31/2016 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related Property Modification Design Only $63,933.20 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to provide design services for modifications to a property that the Authority has bought. Terry Ogle, Director of Design & Construction Jim Laing, Project Manager/Director John C. Lee, D-B Oversight Manager
CP 1 HSR 13-06 44.1 5/31/2016 Tutor Perini / Zachry/Parsons Utility Relocation PG&E Utility Conflict (CO 44) $221,984.44 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to move PG&E facilities out of the way of future high-speed rail construction. The designs for these relocations were changed during the PG&E approval process. Terry Ogle, Director of Design & Construction Jim Laing, Project Manager/Director John C. Lee, D-B Oversight Manager
CP 1 HSR 13-06 95 5/12/2016 Tutor Perini / Zachry/Parsons Utility Relocation AT&T Design-Underground Ductbank $868,479.70 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to move AT&T underground utilities from the south of Santa Clara Street to south of East American Avenue in the City of Fresno to make room for the future high-speed rail system. Terry Ogle, Director of Design & Construction Jim Laing, Project Manager/Director John C. Lee, D-B Oversight Manager
CP 1 HSR 13-06 2.1 5/4/2016 Tutor Perini / Zachry/Parsons Administrative Partnering Costs Supplemental $100,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to continue partnering meetings between the contractor and the Authority for the project. Hugo Mejia - Design & Construction Manager James Laing - Project Director John C. Lee - DB Oversight Manager
CP 1 HSR 13-06 87.1 4/29/2016 Tutor Perini / Zachry/Parsons Third-party Related Top Down Const SR 180 Supplmtl $470,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to implement and perform Construction Zone Enhanced Enforcement Program (enhanced traffic mangement using California Highway Patrol) during construction at State Route 180. Hugo Mejia, Design & Construction Manager Jim Laing, Project Manager/Director John C. Lee, D-B Oversight Manager
CP 1 HSR 13-06 84 4/20/2016 Tutor Perini / Zachry/Parsons Third-party Related Top of Rail Survey - UPRR $4,866.22 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to survey the top of each Union Pacific Railroad rail on all their mainline tracks between 1000 feet either side of Ashlan and Clinton Avenues to satisfy the conditions of the Authority's agreement with UPRR. Hugo Mejia, Design & Construction Manager Jim Laing, Project Manager/Director John C. Lee, D-B Oversight Manager
CP 1 HSR 13-06 85 4/19/2016 Tutor Perini / Zachry/Parsons Third-party Related Fresno River VECP ($1,243,975.50) This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to provide a credit to the Authority for incorporation of the Fresno River Value Engineering Change Proposal. Hugo Mejia, Design & Construction Manager Jim Laing, Project Manager/Director John C. Lee, D-B Oversight Manager
CP 1 HSR 13-06 89 4/7/2016 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications North Extension $153,399,844.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to add approximately 2.72 miles of additional future high-speed rail system to this contract, to the northern boundary. This additional scope is mostly flat and is adjacent to the west side of the Burlington Northern Santa Fe tracks in the County of Madera. Scott Jarvis, Chief Engineer Jim Laing, Project Manager/Director John C. Lee, D-B Oversight Manager
CP 1 HSR 13-06 87 4/5/2016 Tutor Perini / Zachry/Parsons Third-party Related Top Down Const SR 180/ Fresno Trench $3,765,141.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to design and construct the tunnel under State Route 180 using the Top-Down Construction Method. Terry Ogle, Director of Design & Construction Jim Laing, Project Manager/Director John C. Lee, D-B Oversight Manager
CP 1 HSR 13-06 88 4/4/2016 Tutor Perini / Zachry/Parsons Environmental Additional Environmental Services $1,800,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to perform environmental services as part of the Authority's environmental commitments. Hugo Mejia, Design & Construction Manager Jim Laing, Project Manager/Director John C. Lee, D-B Oversight Manager
CP 1 HSR 13-06 86 3/7/2016 Tutor Perini / Zachry/Parsons Utility Relocation AT&T UG Ductbank Relocate Ashlan /SJ $313,454.10 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to contribute to moving AT&T facilities out of the way of the future high-speed rail alignment between Ashlan Avenue and the San Joaquin River. Hugo Mejia, Design & Construction Manager Jim Laing, Project Manager/Director John C. Lee, D-B Oversight Manager
CP 1 HSR 13-06 54 3/7/2016 Tutor Perini / Zachry/Parsons Utility Relocation Design AT&T Relocation-Madera County $341,291.46 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to move AT&T facilities out of the way of the future high-speed rail system at Avenues 7, 8 , 9, 10, 11, 12, 13, 15, 15-1/2. Hugo Mejia, Design & Construction Manager Jim Laing, Project Manager/Director John C. Lee, D-B Oversight Manager
CP 1 HSR 13-06 38 3/7/2016 Tutor Perini / Zachry/Parsons Utility Relocation ATT Design-Belmont to Santa Clara $245,868.06 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to complete plans to move AT&T facilities out of the way of the future high-speed rail system. Hugo Mejia - Design & Construction Manager James Laing - Project Director John C. Lee - DB Oversight Manager
CP 1 HSR 13-06 81 3/4/2016 Tutor Perini / Zachry/Parsons Utility Relocation PG&E / AT&T Managemt Team/Bid Solic $2,262,678.07 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to transfer responsibility of management services from the Authority to the contractor to move PG&E and AT&T facilities out of the way of future high-speed rail system. PG&E and provides gas and electric services in California. AT&T provides telecommunications services. Terry Ogle, Design & Construction Manager Jim Laing, Project Manager/Director John C. Lee, D-B Oversight Manager
CP 1 HSR 13-06 56 3/1/2016 Tutor Perini / Zachry/Parsons Utility Relocation PG&E Gas Relocate Kern / F St. $11,039.85 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to move PG&E facilities out of the way of the future high-speed rail system. Hugo Mejia, Design & Construction Manager Jim Laing, Project Manager/Director John C. Lee, D-B Oversight Manager
CP 1 HSR 13-06 82 2/22/2016 Tutor Perini / Zachry/Parsons Utility Relocation Miscellaneous Survey & Pothole Work $100,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to conduct surveying and potholing to identify PG&E and AT&T utility locations with the future high-speed rail alignment. Hugo Mejia, Design & Construction Manager Jim Laing, Project Manager/Director John C. Lee, D-B Oversight Manager
CP 1 HSR 13-06 75 2/22/2016 Tutor Perini / Zachry/Parsons Utility Relocation EEI Engineering Design for Unit 2 $508,875.25 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to move PG&E utilities out of the way of the future high-speed rail system at West Shaw Avenue, Tuolumne Street, Fresno-Tulare Street, Kern Street, Ventura Street in Fresno County and Avenues 11, 15 and 15 1/2 in Madera County. Hugo Mejia, Design & Construction Manager Jim Laing, Project Manager/Director John C. Lee, D-B Oversight Manager
CP 1 HSR 13-06 32.1 1/25/2016 Tutor Perini / Zachry/Parsons Environmental Pedestrian Arch Field Surveys $- This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to continue to perform Pedestrian Archaeological Field Inventory Surveys. Hugo Mejia - Design & Construction Manager James Laing - Project Director John C. Lee - DB Oversight Manager
CP 1 HSR 13-06 29.2C 1/22/2016 Tutor Perini / Zachry/Parsons Environmental Extra work Biological Servies for CP1C $- This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to continue to implement requirements of the California Department of Fish and Wildlife permits as part of the Authority's environmental commitments. Hugo Mejia - Design & Construction Manager James Laing - Project Director John C. Lee - DB Oversight Manager
CP 1 HSR 13-06 29.1A 1/22/2016 Tutor Perini / Zachry/Parsons Environmental Extra work Biological Servies for CP1A/1B $300,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to continue to implement requirements of the California Department of Fish and Wildlife permits as part of the Authority's environmental commitments. Hugo Mejia - Design & Construction Manager James Laing - Project Director John C. Lee - DB Oversight Manager
CP 1 HSR 13-06 77 1/14/2016 Tutor Perini / Zachry/Parsons Utility Relocation Valverde Const. AT&T Conflict $38,654.27 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to move AT&T utilities out of the way of the future high-speed rail system at Raymond Road and State Route 145 in Madera County. Hugo Mejia, Design & Construction Manager Jim Laing, Project Manager/Director John C. Lee, D-B Oversight Manager
CP 1 HSR 13-06 49 1/14/2016 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications OCS Structural Connections $1,874,151.32 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to design and install fittings on bridges into which future high-speed rail system components will be attached. Hugo Mejia, Design & Construction Manager Ghassan Ariqat, Project Manager/Director John C. Lee, D-B Oversight Manager
CP 1 HSR 13-06 43 12/29/2015 Tutor Perini / Zachry/Parsons Environmental EMMA and Sustainability $72,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to authorize the additional level of effort required for entering data into the Environmental Mitigation Management & Assessment database. Hugo Mejia, Design & Construction Manager Jim Laing, Project Manager/Director John C. Lee, D-B Oversight Manager
CP 1 HSR 13-06 80 12/21/2015 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications CHSR Std. Spec Revision Photographic $50,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to provide time-lapse documentation of the construction of the future high-speed rail system at Fresno River Viaduct, Tuolumne Bridge and Starte Route 180 trench. Hugo Mejia, Design & Construction Manager Jim Laing, Project Manager/Director John C. Lee, D-B Oversight Manager
CP 1 HSR 13-06 65 12/10/2015 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications OnSite Circulation Analysis FB100079 $7,817.12 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to conduct analysis of tractor/trailer movements on property impacted by the future high-speed rail system. Hugo Mejia, Design & Construction Manager Jim Laing, Project Manager/Director John C. Lee, D-B Oversight Manager
CP 1 HSR 13-06 78 11/20/2015 Tutor Perini / Zachry/Parsons Utility Relocation Potholing for Caltrans in SR99 ROW $15,706.44 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to identify udnerground energy and telecommunications facilities that are within the project limits of the future high-speed rail system. Hugo Mejia, Design & Construction Manager Jim Laing, Project Manager/Director John C. Lee, D-B Oversight Manager
CP 1 HSR 13-06 12.2 11/20/2015 Tutor Perini / Zachry/Parsons Environmental Archaeological Field Inventory $- This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to conduct archaeological field surveys of additional properties. Hugo Mejia - Design & Construction Manager James Laing - Project Director John C. Lee - DB Oversight Manager
CP 1 HSR 13-06 50 10/21/2015 Tutor Perini / Zachry/Parsons Third-party Related COF Relocation Agreement $1,161,633.19 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to do additional design identified in the final agreement between the Authority and the City of Fresno. Hugo Mejia, Design & Construction Manager Jim Laing, Project Manager/Director John C. Lee, D-B Oversight Manager
CP 1 HSR 13-06 53.1 10/13/2015 Tutor Perini / Zachry/Parsons Third-party Related Additional Assessments UPRR Parcels $5,462.09 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to conduct environmental assessment on Union Pacific Railroad owned land. Hugo Mejia, Design & Construction Manager Jim Laing, Project Manager/Director John C. Lee, D-B Oversight Manager
CP 1 HSR 13-06 34 10/6/2015 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications Trackway & Structures - Chapter 12 $589,533.66 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to revise the design requirements for future high-speed rail bridges under 1000 feet in length. Hugo Mejia - Design & Construction Manager James Laing - Project Director John C. Lee - DB Oversight Manager
CP 1 HSR 13-06 52 10/1/2015 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications E. American Ave Design Speed Var $63,874.94 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to complete traffic studies on East American Avenue to prepare a request to the City of Fresno to reduce the speed on East American Avenue from 65 to 45 miles per hour. Hugo Mejia, Design & Construction Manager Jim Laing, Project Manager/Director John C. Lee, D-B Oversight Manager
CP 1 HSR 13-06 53 9/29/2015 Tutor Perini / Zachry/Parsons Third-party Related Phase 2 Enviro Site Assessmt UPRR $36,723.62 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to conduct environmental assessment on Union Pacific Railroad owned land. Hugo Mejia, Design & Construction Manager Jim Laing, Project Manager/Director John C. Lee, D-B Oversight Manager
CP 1 HSR 13-06 40 9/8/2015 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related CP 1 Parcel Mgt & Security $56,001.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to provide property management and site security prior to construction. Michael Leonardo - Acting Director of Design & Construction James Laing - Project Director John C. Lee - DB Oversight Manager
CP 1 HSR 13-06 45 9/4/2015 Tutor Perini / Zachry/Parsons Differing Site Conditions Site Specific Response Analysis FRV $55,968.56 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to provide a seismic analysis for the structural design of the Fresno River Viaduct. Hugo Mejia, Design & Construction Manager Jim Laing, Project Manager/Director John C. Lee, D-B Oversight Manager
CP 1 HSR 13-06 44 8/20/2015 Tutor Perini / Zachry/Parsons Utility Relocation PG&E Raymond Rd & SR 145 $392,495.35 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to move electrical distribution facilities out of the way of the future high-speed rail construction over the Fresno River. Mike Leonardo, Acting Director of Design & Construction Jim Laing, Project Manager/Director John C. Lee, D-B Oversight Manager
CP 1 HSR 13-06 42 8/19/2015 Tutor Perini / Zachry/Parsons Administrative Additional Space at 1401 Fulton $235,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to provide the Authority with an additional 5,113 square feet of rentable office space at 1401 Fulton Street in Fresno. Mike Leonardo, Acting Director of Design & Construction Jim Laing, Project Manager/Director John C. Lee, D-B Oversight Manager
CP 1 HSR 13-06 12.1 7/31/2015 Tutor Perini / Zachry/Parsons Environmental Archaeological Field Inventory $- This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to provide additional archeological inventories to meet environmental requirements. Michael Leonardo - Acting Director of Design & Construction James Laing - Project Director John C. Lee - DB Oversight Manager
CP 1 HSR 13-06 35.1 7/21/2015 Tutor Perini / Zachry/Parsons Environmental Archaeological Monitoring in 1C $100,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to continue to perform Archaeological Monitoring and related reporting. Mike Leonardo - Director of Design & Construction James Laing - Project Director John C. Lee - DB Oversight Manager
CP 1 HSR 13-06 29.2 7/21/2015 Tutor Perini / Zachry/Parsons Environmental Post Permit Monitoring Efforts 1C $100,000.00 This is a change to a contract for design and construction services in the Central Valley. TThe reason for the change is to continue to implement requirements of the California Department of Fish and Wildlife permits as part of the Authority's environmental commitments. Mike Leonardo - Director of Design & Construction James Laing - Project Director John C. Lee - DB Oversight Manager
CP 1 HSR 13-06 29.1 7/21/2015 Tutor Perini / Zachry/Parsons Environmental Post Permit Monitoring Efforts 1A/1B $150,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to continue to implement requirements of the California Department of Fish and Wildlife permits as part of the Authority's environmental commitments. Mike Leonardo - Director of Design & Construction James Laing - Project Director John C. Lee - DB Oversight Manager
CP 1 HSR 13-06 28 5/29/2015 Tutor Perini / Zachry/Parsons Environmental 956 China-Additional Scope of Work $11,221.08 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to provide design services and monitoring for the restoration of the historical building at 956 China Alley in Fresno. Ofelia Alacantara - Director of Design and Construction James Laing - Project Director John C. Lee - DB Oversight Manager
CP 1 HSR 13-06 13.1 5/29/2015 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related BETP Task 2 and Task 3 $60,714.86 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to develop a pland to protect important elements of the built environment identified in the environmental documents. Ofelia Alacantara - Director of Design and Construction James Laing - Project Director John C. Lee - DB Oversight Manager
CP 1 HSR 13-06 41 5/27/2015 Tutor Perini / Zachry/Parsons Differing Site Conditions Ground Penetrating Radar - Kern St $9,567.91 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to provide subsurface images of Kern Street at Ofelia's Barber Shop/Restaurant and Dick's Store in Fresno. Ofelia P. Alcantara, P.E., Director of Design & Construction Jim Laing, Project Manager/Director John C. Lee, D-B Oversight Manager
CP 1 HSR 13-06 35 5/4/2015 Tutor Perini / Zachry/Parsons Environmental Archaeological Monitoring in 1C $50,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to perform Archaeological Monitoring and related reporting. Ofelia Alacantara - Director of Design and Construction James Laing - Project Director John C. Lee - DB Oversight Manager
CP 1 HSR 13-06 31 5/4/2015 Tutor Perini / Zachry/Parsons Environmental Archaeological Monitoring 1A & 1B $500,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to perform archaeological monitoring services and related reporting. Ofelia Alacantara - Director of Design and Construction James Laing - Project Director John C. Lee - DB Oversight Manager
CP 1 HSR 13-06 30 5/4/2015 Tutor Perini / Zachry/Parsons Environmental Biological Monitoring Services in 1C $50,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to perform biological monitoring services prior to construction. Ofelia Alacantara - Director of Design and Construction James Laing - Project Director John C. Lee - DB Oversight Manager
CP 1 HSR 13-06 29 5/4/2015 Tutor Perini / Zachry/Parsons Environmental Post Permit Monitoring Efforts 1A/1B $96,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to implement requirements of the California Department of Fish and Wildlife permits as part of the Authority's environmental commitments. Ofelia Alacantara - Director of Design and Construction James Laing - Project Director John C. Lee - DB Oversight Manager
CP 1 HSR 13-06 39 4/22/2015 Tutor Perini / Zachry/Parsons Differing Site Conditions 1528-1548 Tulare Street $2,791.83 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to prepare a report describing how to repair buildings. Ofelia Alacantara - Director of Design and Construction James Laing - Project Director John C. Lee - DB Oversight Manager
CP 1 HSR 13-06 32 3/26/2015 Tutor Perini / Zachry/Parsons Environmental Pedestrian Arch Field Surveys $150,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to perform Pedestrian Archaeological Field Inventory Surveys. Ofelia Alacantara - Director of Design and Construction James Laing - Project Director John C. Lee - DB Oversight Manager
CP 1 HSR 13-06 33 3/4/2015 Tutor Perini / Zachry/Parsons Environmental Native American Monitoring for 1C $100,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to perform Native American Monitoring and Archaeological Monitoring. Ofelia Alacantara - Director of Design and Construction James Laing - Project Director John C. Lee - DB Oversight Manager
CP 1 HSR 13-06 27 2/26/2015 Tutor Perini / Zachry/Parsons Environmental Biological Monitoring $50,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to provide biological monitoring services prior to construction. Ofelia Alacantara - Director of Design and Construction James Laing - Project Director John C. Lee - DB Oversight Manager
CP 1 HSR 13-06 26 2/25/2015 Tutor Perini / Zachry/Parsons Environmental Archaeological Monitoring Services $250,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to perform archaeological monitoring. Ofelia Alacantara - Director of Design and Construction James Laing - Project Director John C. Lee - DB Oversight Manager
CP 1 HSR 13-06 25 2/25/2015 Tutor Perini / Zachry/Parsons Environmental Native American Monitoring $250,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to perform Native American Monitoring. Ofelia Alacantara - Director of Design and Construction James Laing - Project Director John C. Lee - DB Oversight Manager
CP 1 HSR 13-06 24 2/4/2015 Tutor Perini / Zachry/Parsons Environmental Main Canal Survey Report $12,354.25 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to prepare environmental documents as part of the Authority's environmental commitments. Ofelia Alacantara - Director of Design and Construction James Laing - Project Director John C. Lee - DB Oversight Manager
CP 1 HSR 13-06 23 2/4/2015 Tutor Perini / Zachry/Parsons Changes to Plans and Specifications COF Convert Data Points $14,943.66 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to convert design data prior to submitting designs to the City of Fresno. Ofelia Alacantara - Director of Design and Construction James Laing - Project Director John C. Lee - DB Oversight Manager
CP 1 HSR 13-06 22 2/2/2015 Tutor Perini / Zachry/Parsons Administrative DRB Process Revision $- This is a change to a contract for design and construction services in the Central Valley. The reason for this no cost change is to streamline the dispute resolution process. Ofelia Alacantara - Director of Design and Construction James Laing - Project Director John C. Lee - DB Oversight Manager
CP 1 HSR 13-06 20 1/8/2015 Tutor Perini / Zachry/Parsons Environmental Small Mammal Burrow Excavation $480,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to dig small burrows for mammals by hand, as part of the Authority's environmental commitments. Ofelia Alcantara - Director of Design & Construction James Laing - Project Director John C. Lee - DB Oversight Manager
CP 1 HSR 13-06 18 1/8/2015 Tutor Perini / Zachry/Parsons Environmental GIS Habitat Tracking $244,811.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to set up a habitat tracking system as part of the Authority's environmental commitments. Ofelia Alcantara - Director of Design & Construction James Laing - Project Director John C. Lee - DB Oversight Manager
CP 1 HSR 13-06 16 10/30/2014 Tutor Perini / Zachry/Parsons Administrative CBA Administrative Addendum 1 $- This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to update the contract to include revisions to the Community Benefits Agreement. Ofelia Alacantara - Director of Design and Construction James Laing - Project Director PCM DB Oversight Manager
CP 1 HSR 13-06 19 10/21/2014 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related DL 00004 - BETP Task 4 $28,662.76 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to complete histoical architectural surveying work at Belmont Avenue subway. Ofelia Alacantara - Director of Design and Construction James Laing - Project Director John Foster - Project Controls Oversight Manager
CP 1 HSR 13-06 15 10/21/2014 Tutor Perini / Zachry/Parsons Utility Relocation Design for AT&T Relocation $97,656.76 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to move AT&T facilities relocation plans at Stanislaus Bridge and Fresno River Viaduct out of the way of the future high-speed rail system. Ofelia Alacantara - Director of Design and Construction James Laing - Project Director Rick Stead - DB Oversight Manager
CP 1 HSR 13-06 14 10/21/2014 Tutor Perini / Zachry/Parsons Administrative Revised Design Variance Request Form $- This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to an administrative change to revise the form used to request variances to the design criteria used on the project. Ofelia Alacantara - Director of Design and Construction James Laing - Project Director John Houseman - DB Oversight Manager
CP 1 HSR 13-06 9 10/21/2014 Tutor Perini / Zachry/Parsons Environmental Revised Shear Wave 500-ft Boring $275,227.04 This is a change to a contract for design and construction services in the Central Valley. The reason for the change provides environmental and design services at Fresno and San Joaquin rivers. Ofelia Alacantara - Director of Design and Construction James Laing - Project Director John Foster - Project Controls Oversight Manager
CP 1 HSR 13-06 17 10/13/2014 Tutor Perini / Zachry/Parsons Administrative Subcontractor Mobilization Expense A $- This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to revise the language in the contract that determines mobilization requirements of contractor staff to the project. Ofelia Alacantara - Director of Design and Construction James Laing - Project Director John Foster - Project Controls Oversight Manager
CP 1 HSR 13-06 13 9/4/2014 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related DL 00004 - BETP Task 1 $280,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to perform pre-construction assessments at 8 properties. Ofelia Alcantara - Director of Design & Construction James Laing - Project Director Rick Stead - DB Oversight Manager
CP 1 HSR 13-06 12 9/4/2014 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related Archaeological Field Inventory $180,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to provide archeological inventories to meet the Authority's environmental commitments. Ofelia Alcantara - Director of Design & Construction James Laing - Project Director Rick Stead - DB Oversight Manager
CP 1 HSR 13-06 7 9/4/2014 Tutor Perini / Zachry/Parsons Environmental CL1/CL2 HazMat $5,250,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to define the quantity and price for hazardous material removal and disposal in the contract. Ofelia Alacantara - Director of Design and Construction James Laing - Project Director Rick Stead - DB Oversight Manager
CP 1 HSR 13-06 10 8/7/2014 Tutor Perini / Zachry/Parsons Right-of-Way (ROW) Related Weed Abatement - Various Locations $300,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to cleanup vegetation and debris at property owned by the Authority. Ofelia Alacantara - Director of Design and Construction James Laing - Project Director Rick Stead - DB Oversight Manager
CP 1 HSR 13-06 8 8/7/2014 Tutor Perini / Zachry/Parsons Administrative DRB 3rd Member $- This is a change to a contract for design and construction services in the Central Valley. The reason for the change revises the contract language regarding Dispute Resolution Board membership. Ofelia Alacantara - Director of Design and Construction James Laing - Project Director Rick Stead - DB Oversight Manager
CP 1 HSR 13-06 5 8/7/2014 Tutor Perini / Zachry/Parsons Administrative Local/ Long Distance Phone Charges $79,546.85 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to pay for Authority phone costs at office space provided by the general contractor for Authority's use per the contract. Ofelia Alacantara - Director of Design and Construction James Laing - Project Director Rick Stead - DB Oversight Manager
CP 1 HSR 13-06 6 7/3/2014 Tutor Perini / Zachry/Parsons Administrative DRB Expenses $180,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to pay the Authority’s share of Dispute Resolution Board costs for the project. Ofelia Alacantara - Director of Design and Construction James Laing - Project Director Rick Stead - DB Oversight Manager
CP 1 HSR 13-06 3 6/30/2014 Tutor Perini / Zachry/Parsons Administrative SP20 Invoicing Changes $- This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to revise the Special Provisions Section 20 of the contract. Ofelia Alacantara - Director of Design and Construction James Laing - Project Director Rick Stead - DB Oversight Manager
CP 1 HSR 13-06 4 6/19/2014 Tutor Perini / Zachry/Parsons Administrative IBM Rational Doors $7,987.34 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to provide one IBM Rational Doors authorized user license to the Authority (requirements management software). Ofelia Alacantara - Director of Design and Construction James Laing - Project Director Rick Stead - DB Oversight Manager
CP 1 HSR 13-06 2 6/19/2014 Tutor Perini / Zachry/Parsons Administrative Partnering Costs $108,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to conduct partnering workshops and meetings between the contractor and the Authority for the project. Ofelia Alacantara - Director of Design and Construction James Laing - Project Director Rick Stead - DB Oversight Manager
CP 1 HSR 13-06 1 6/2/2014 Tutor Perini / Zachry/Parsons Administrative Addition of Copiers and Printer $40,527.99 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to provide two copiers and a printer for Authority use. Ofelia Alacantara - Director of Design and Construction James Laing - Project Director James Hanningan - Construction Oversight Manager
CP 2-3 HSR 13-57 45.6 5/14/2020 Dragados/Flatiron Joint Venture Administrative Escalation Costs - February 2020 $1,388,381.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for all the accumulative escalation costs for the month of February 2020 described in and pursuant to executed Change Order 00045.1. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
CP 2-3 HSR 13-57 45.7 5/14/2020 Dragados/Flatiron Joint Venture Administrative Escalation Costs - March 2020 $1,171,420.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for all the accumulative escalation costs for the month of March 2020 described in and pursuant to executed Change Order 00045.1. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
CP 2-3 HSR 13-57 144 5/14/2020 Dragados/Flatiron Joint Venture Third Party Related Jack and Bore Irrigation Facilities - Design Only $531,533.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the Final Design Work to redesign the (8) Irrigation facilities that require modification as part of incorporating a maintenance access road on the western edge of the BNSF existing and future rights-of-way Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
CP 2-3 HSR 13-57 45.5 5/6/2020 Dragados/Flatiron Joint Venture Administrative Escalation Costs - January 2020 $1,646,117.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for all the accumulative escalation costs for the month of January 2020 described in and pursuant to executed Change Order 00045.1. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
CP 2-3 HSR 13-57 142 5/5/2020 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Jackson Avenue and Idaho Avenue Detour/Bypass $1,180,909.00 This is a change to a contract for design and construction services in the Central Valley.  The reasons for the change is for the install and for the complete removal of the temporary detour/bypass for the construction of Jackson Avenue and Idaho Avenue bridges as a mitigation measure to construct the bridges to progress work sooner and to prevent the compaction of work activities later with other critical path activities. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
CP 2-3 HSR 13-57 135 5/4/2020 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Kie Con Pile Storage Fees-Adams Avenue $31,030.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the costs of the storage fees to store the concrete pile for the Adams Avenue Bridge. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
CP 2-3 HSR 13-57 139 4/29/2020 Dragados/Flatiron Joint Venture Change to the Plans and Specifications Elimination of Iona Avenue Overcrossing - DESIGN ONLY $9,000.00 This is a change to a contract for design and construction services in the Central Valley. The reasons for the change is for the elimination of Iona Avenue Overcrossings and to design cul-de-sacs on each side of the High-Speed-Rail Tracks on Iona Avenue as required per Authority Directive Letter No.00073, Elimination of Iona Avenue Overcrossing. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
CP 2-3 HSR 13-57 10.11 4/29/2020 Dragados/Flatiron Joint Venture Third-Party Related Ave. 136 Extension East to SR 43 - DESIGN ONLY $34,470.00 This is a change to a contract for design and construction services in the Central Valley.  The reason for the change is because of Avenue 136 extending east to SR 43 per RFI 00587 response “Tulare County Utility Agreement that 0.43 miles is the length of the roadway improvements that the improvements shall extend east to SR 43”. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
CP 2-3 HSR 13-57 24.1.3 4/29/2020 Dragados/Flatiron Joint Venture Changes to Plans and Specifications HazMat Abatement UST/NAC Disposal FB-10-0388 $8,455.00 This is a change to a contract for design and construction services in the Central Valley. The reasons for the change is for the added scope resulting from remediation costs associated with abatement of hazardous materials due to an underground storage tank (UST), located at 2287 E. Floral Avenue, Fresno, CA (FB-10-0388), as identified in property assessment on September 1, 2017 and the Moore Twining lab tests for the UST and surrounding soils taken on August 31, 2018 and for the disposal of the Vac Tank Contents and UST disposal. The UST identified needed to be rinsed and removed from the site. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
CP 2-3 HSR 13-57 24.17 4/28/2020 Dragados/Flatiron Joint Venture Changes to Plans and Specifications HazMat – Treated Wood Waste at Hwy.43/FB-10-0479 $194,174.00 This is a change to a contract for design and construction services in the Central Valley.  The reasons for the change is for the added scope resulting from remediation costs associated for the abatement of hazardous waste materials to remove and dispose of the Treated Wood Waste at Hwy. 43 and (FB-10-0479). Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
CP 2-3 HSR 13-57 129 4/28/2020 Dragados/Flatiron Joint Venture Third-Party Related BNSF Westside Maintenance Road - DESIGN ONLY $1,375,913.00 This is a change to a contract for design and construction services in the Central Valley. The reasons for the change is to design and prepare construction plans for the BNSF Westside Access Road in reference to the Authority's Directive Letter No. 00078, Implementation of BNSF Westside Access Maintenance Road within BNSF right-of-way. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
CP 2-3 HSR 13-57 143 4/27/2020 Dragados/Flatiron Joint Venture Change to the Plans and Specifications Reduce Impact to Dairy @ Houston Ave. - DESIGN ONLY $87,393.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to design a 300-foot-long retaining wall on the southeast quadrant of the Houston Avenue Grade Separation per Authority Directive Letter No. 00071.1 to Reduce Impact to Dairy at Houston Avenue Grade Separation. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
CP 2-3 HSR 13-57 24.16 4/27/2020 Dragados/Flatiron Joint Venture Changes to Plans and Specifications HazMat - Treated Wood Waste at Davis Avenue $49,637.00 This is a change to a contract for design and construction services in the Central Valley.  The reasons for the change is for the added scope resulting from remediation costs associated for the abatement of hazardous waste materials to remove and dispose of the Treated Wood Waste at Davis Avenue (FB-10-0474-1, -3, -4, -6, -7). Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
CP 2-3 HSR 13-57 141 4/24/2020 Dragados/Flatiron Joint Venture Change to the Plans and Specifications Kings River Complex Trestle $4,796,474.00 This is a change to a contract for design and construction services in the Central Valley. The reasons for the change is for the construction work to install, maintain and the complete removal of the temporary Trestle for the construction of the Kings River Viaduct as a mitigation measure to construct the viaduct in less time than originally anticipated. Construction impacts, if any, associated with the construction of the Kings River Viaduct from the temporary Trestle are not included in this Change Order. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
CP 2-3 HSR 13-57 65.1 4/7/2020 Dragados/Flatiron Joint Venture Change to the Plans and Specifications GTC - Flint Avenue $995,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is because of the impact on the construction of the bridge structures. DFJV will construct the west side embankment and to start the bridge settlement period. DFJV will remobilize to complete the west embankment once the utility has been relocated and will construct the remaining embankment. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
CP 2-3 HSR 13-57 113 3/30/2020 Dragados/Flatiron Joint Venture Third-Party Related Flow Capacity at Wristen Ditch $5,739,371.00 This is a change to a contract for design and construction services in the Central Valley. The reasons for the change is a change in law to require doubling the flow capacities at several areas by the Consolidated Irrigation District (CID) resulting in an increase in the scope of the contract. Elias Mahfoud, Director of Infrastructure Delivery (CEA B) Vicente Alberola Project Manager Patrick E Jolly, PE DB Oversight Manager
CP 2-3 HSR 13-57 121.1 3/28/2020 Dragados/Flatiron Joint Venture Administrative Hanford Viaduct Reallocation $0.00 This is a change to a contract for design and construction services in the Central Valley.  The reasons for the change is for reallocation of budgets within the contract amount. This is a net zero cost change order. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Troy Tambay, PE DB Oversight Manager
CP 2-3 HSR 13-57 109.1 3/26/2020 Dragados/Flatiron Joint Venture Change to the Plans and Specifications Project Floodplain Limit Increases $22,283,480.00 This is a change to a contract for design and construction services in the Central Valley.  The reason for the change is because there was a change in the limits of the FEMA floodplain within the project limits resulting in an increase in the scope of the contract. Joe Hedges, COO, CHSRA Vicente Alberola Project Manager Patrick E Jolly, PE DB Oversight Manager
CP 2-3 HSR 13-57 136 3/26/2020 Dragados/Flatiron Joint Venture Change to the Plans and Specifications GTC - Embankment Const Nevada-Ave144 $14,666,140.00 This is a change to a contract for design and construction services in the Central Valley. The reasons for the change is for the additional costs to utilize on road trucking and additional mobilizations to complete the construction work for constructing the embankment from Nevada Avenue to Avenue 144. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Patrick E Jolly, PE DB Oversight Manager
CP 2-3 HSR 13-57 132 3/20/2020 Dragados/Flatiron Joint Venture Administrative ROI Acquisition Addtl ROW Utl. Reloc $387,272.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the additional work associated with the Report of Investigation (ROI) Reports for ROW Utility Relocations. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Patrick E Jolly, PE DB Oversight Manager
CP 2-3 HSR 13-57 133 3/20/2020 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Barcelos Water Service Connection $375,236.00 This is a change to a contract for design and construction services in the Central Valley. The reasons for the change is to furnish and install up to 3,200 linear feet of 16in diameter permanent PVC water line adjacent to the existing basin within Parcels HSR# FB-54-0003-2 and 0003-3 and to backfill and compact 1,100 linear feet of existing irrigation ditch as needed. The property owner north of Avenue 144 requires a private water service connection to a private irrigation ditch. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Patrick E Jolly, PE DB Oversight Manager
CP 2-3 HSR 13-57 137 3/20/2020 Dragados/Flatiron Joint Venture Administrative Precast Girders Storage $4,925,000.00 This is a change to a contract for design and construction services in the Central Valley. This change was executed as a mitigation to on-going project delays, to develop a secondary storage area for the Project precast girder elements (467 each), including transportation of these precast girder elements from an existing precast yard to a secondary storage area, and unloading of these girders at the secondary storage area. This change allows the Contractor to continue production of precast elements for the project. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Patrick E Jolly, PE DB Oversight Manager
CP 2-3 HSR 13-57 80.1 3/20/2020 Dragados/Flatiron Joint Venture Change to the Plans and Specifications Unidentified Additional Waterline at 4 1/2 Avenue $377,858.00 This is a change to a contract for design and construction services in the Central Valley. The reasons for the change is for an unidentified additional waterline that was not shown in the RFP documents. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Patrick E Jolly, PE DB Oversight Manager
CP 2-3 HSR 13-57 124 3/20/2020 Dragados/Flatiron Joint Venture Change to the Plans and Specifications 10" HDPE Level 3 Sumner-Huntsman Avenues $606,248.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is BNSF changed its pre-bid requirements, requiring casings for utilities crossing the BNSF right-of-way, resulting in an increase in the scope of the contract. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Patrick E Jolly, PE DB Oversight Manager
CP 2-3 HSR 13-57 125 3/20/2020 Dragados/Flatiron Joint Venture Change to the Plans and Specifications 10" HDPE Level 3 - Conejo Avenue $189,428.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is BNSF changed its pre-bid requirements, requiring casings for utilities crossing the BNSF right-of-way, resulting in an increase in the scope of the contract. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Patrick E Jolly, PE DB Oversight Manager
CP 2-3 HSR 13-57 126 3/20/2020 Dragados/Flatiron Joint Venture Change to the Plans and Specifications 10" HDPE Level 3 Overholser-Kamm Ave $492,048.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is BNSF changed its pre-bid requirements, requiring casings for utilities crossing the BNSF right-of-way, resulting in an increase in the scope of the contract. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Patrick E Jolly, PE DB Oversight Manager
CP 2-3 HSR 13-57 127 3/20/2020 Dragados/Flatiron Joint Venture Change to the Plans and Specifications Maintenance Access Roads Under Type 2 Structures $2,100,413.00 This is a change to a contract for design and construction services in the Central Valley. The reasons for the change is because of the requirement for a maintenance access ramp and a maintenance access bench at the Type 2 Bridge Structures, a change in the requirements from the Directive Drawings, resulting in an increase in scope of the contract. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Patrick E Jolly, PE DB Oversight Manager
CP 2-3 HSR 13-57 131 3/20/2020 Dragados/Flatiron Joint Venture Change to the Plans and Specifications South Ave. Jack Bore RC Agrmnt TM $42,055.00 This is a change to a contract for design and construction services in the Central Valley. The reasons for the change is because BNSF had not executed a Relocation and Construction Agreement (“R&C”). This change compensates the Contractor for additional mobilization costs incurred due to the delay in execution of the R&C Agreement. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Patrick E Jolly, PE DB Oversight Manager
CP 2-3 HSR 13-57 138 3/20/2020 Dragados/Flatiron Joint Venture Administrative Secondary Pre-Cast Girders Storage -- Police Escorts. $652,000.00 This is a change to a contract for design and construction services in the Central Valley. The reasons for the change work for Police escorts required to transport the Project precast elements from the existing precast yard location to the secondary precast storage yard through Fresno County to be paid on a Time and Material (T&M) basis as costs are incurred. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Patrick E Jolly, PE DB Oversight Manager
CP 2-3 HSR 13-57 10.10 2/12/2020 Dragados/Flatiron Joint Venture Third-Party Related TCO Ave 24 Redsgn GW Above Elevation $306,448.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the additional out of scope design work for the Avenue 24 Underpass. This change order is pursuant to an Authority agreement with Tulare County to add an underpass at Avenue 24. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Patrick E Jolly, PE DB Oversight Manager
CP 2-3 HSR 13-57 45.2 2/12/2020 Dragados/Flatiron Joint Venture Administrative Escalation Costs_Aug Sept Oct 2019 $2,509,853.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to resolve delay related escalation costs for the months of August, September and October 2019 due to late delivery of the Project right-of-way by the Authority. CO 45.1 allowed for payment of escalation costs beginning August 1, 2019 thru the end of the project.” Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Patrick E Jolly, PE DB Oversight Manager
CP 2-3 HSR 13-57 45.3 2/12/2020 Dragados/Flatiron Joint Venture Administrative Escalation Costs_November 2019 $1,427,172.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to resolve delay related escalation costs for the month of November 2019 due to late delivery of the Project right-of-way by the Authority. CO 45.1 allowed for payment of escalation costs beginning August 1, 2019 thru the end of the project.” Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Patrick E Jolly, PE DB Oversight Manager
CP 2-3 HSR 13-57 94 2/12/2020 Dragados/Flatiron Joint Venture Environmental Conejo Viaduct CIDH Test Pile $1,031,196.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the inefficiencies associated with the Authority directed early installation of three test piles at the Conejo Viaduct within the restricted area of the incidental take permit footprint. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Patrick E Jolly, PE DB Oversight Manager
CP 2-3 HSR 13-57 117 2/12/2020 Dragados/Flatiron Joint Venture Third-Party Related Corcoran Design Speed Reduction $74,900.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the additional design costs resulting from a change in local agency design standards for local agency roadways. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Patrick E Jolly, PE DB Oversight Manager
CP 2-3 HSR 13-57 119 2/12/2020 Dragados/Flatiron Joint Venture Change to the Plans and Specifications Wristen Ditch - Design $105,037.00 This is a change to a contract for design and construction services in the Central Valley.  The reason for the change is for the additional design work resulting from a change in design standards due to new legislation regarding groundwater sustainability. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Patrick E Jolly, PE DB Oversight Manager
CP 2-3 HSR 13-57 120 2/12/2020 Dragados/Flatiron Joint Venture Change to the Plans and Specifications New Caltrans Requirements for ITS , Barrier and Traffic Lines $35,310.00 This is a change to a contract for design and construction services in the Central Valley.  The reason for the change is a revision in Caltrans design standards for ITS, Traffic Barriers, and Traffic Lines. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Patrick E Jolly, PE DB Oversight Manager
CP 2-3 HSR 13-57 24.15 2/8/2020 Dragados/Flatiron Joint Venture Environmental Haz Mat Abatement - FB-10-0398 $23,315.00 This is a change to a contract for design and construction services in the Central Valley.  The reasons for the change is for the added scope resulting from remediation costs associated with abatement of hazardous materials as identified in an Asbestos and Lead Survey report (ASR). The ASR identified lead based paint in the structure to be demolished, requiring lead abatement. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Patrick E Jolly, PE DB Oversight Manager
CP 2-3 HSR 13-57 86.9 2/8/2020 Dragados/Flatiron Joint Venture Change to the Plans and Specifications Private Irrigation Crossings Segment 2, Parcel FB-16-0006 $165,385.00 This is a change to a contract for design and construction services in the Central Valley.  The reason for the change is addition in scope to install steel casings in the trackway embankment for the crossings of privately owned irrigation facilities at Parcel FB-16-0006. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Patrick E Jolly, PE DB Oversight Manager
CP 2-3 HSR 13-57 60.1 1/30/2020 Dragados/Flatiron Joint Venture Administrative Alpaugh Irrigation District Permit $80,000.00 This is a change to a contract for design and construction services in the Central Valley. The reasons for the change is to allow the Contractor access to complete work in coordination with the Alpaugh Irrigation District. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Patrick E Jolly, PE DB Oversight Manager
CP 2-3 HSR 13-57 86.6 1/30/2020 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Private Irrigation Crossing Segments 1, 2, and 3 $468,392.00 This is a change to a contract for design and construction services in the Central Valley. The reasons for the change is required to install the steel casings in the trackway embankment for the crossings of privately owned irrigation facilities.. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Patrick E Jolly, PE DB Oversight Manager
CP 2-3 HSR 13-57 86.8 1/30/2020 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Private Irrigation Crossing Segment 2, Parcel FB-16-0063 $106,930.00 This is a change to a contract for design and construction services in the Central Valley.  The reasons for the change is required to install steel casings in the trackway embankment for crossings of privately owned irrigation facilities at Parcel FB-16-0063. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Patrick E Jolly, PE DB Oversight Manager
CP 2-3 HSR 13-57 121 12/14/2019 Dragados/Flatiron Joint Venture Administrative Hanford Viaduct Reallocation of Activity ID's Budgeted Amount. $0.00 This is a change to a contract for design and construction services in the Central Valley.  The reasons for the change is for reallocation of Activity ID's Budgeted Amount. This is a net zero cost change order. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Patrick E Jolly, PE DB Oversight Manager
CP 2-3 HSR 13-57 10.9 12/6/2019 Dragados/Flatiron Joint Venture Third-Party Related Tulare County Roadway Improvement in compliance with Sub-Utility Agreement $1,343,756.00 This is a change to a contract for design and construction services in the Central Valley. The reasons for the change is for the construction costs related to Avenue 24 reconstruction Work from Road 72 to Road 80 as part of Tulare County Sub-Utility Agreement 1.07. Alberto Lopez - Senior Contract Manager Vicente Alberola - Project Director Patrick Jolly - PCM Design Build Oversight Manager
CP 2-3 HSR 13-57 86.5 12/6/2019 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Private Irrigation Crossings Design $255,685.00 This is a change to a contract for design and construction services in the Central Valley. The reasons for the change is for the design for Private Irrigation Crossings Casings per the Authority’s Construction Memos. Alberto Lopez - Senior Contract Manager Vicente Alberola - Project Director Patrick Jolly - PCM Design Build Oversight Manager
CP 2-3 HSR 13-57 86.7 12/6/2019 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Private Irrigation Crossing Segment 1 $244,872.00 This is a change to a contract for design and construction services in the Central Valley. The reasons for the change is for relocation of privately owned irrigation facilities. Alberto Lopez - Senior Contract Manager Vicente Alberola - Project Director Patrick Jolly - PCM Design Build Oversight Manager
CP 2-3 HSR 13-57 106 12/5/2019 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Caltrans Median Study $133,750.00 This is a change to a contract for design and construction services in the Central Valley. The reasons for the change is Caltrans changed both its Standard Specifications and Transportation Concept Report after the Proposal Deadline. Alberto Lopez - Senior Contract Manager Vicente Alberola - Project Director Patrick Jolly - PCM Design Build Oversight Manager
CP 2-3 HSR 13-57 111 12/5/2019 Dragados/Flatiron Joint Venture Changes to Plans and Specifications State Route 43 Crossing near Tule River-3H-17 $1,123,500.00 This is a change to a contract for design and construction services in the Central Valley. The reasons for the change is for the design work as required to revise the design (change in law) to meet Caltrans future expansion of State Route 43 crossing near the Tule River (Bridge 3H-17). Alberto Lopez - Senior Contract Manager Vicente Alberola - Project Director Patrick Jolly - PCM Design Build Oversight Manager
CP 2-3 HSR 13-57 116 12/5/2019 Dragados/Flatiron Joint Venture Third-Party Related Davis Avenue Ancillary Redesign $40,219.00 This is a change to a contract for design and construction services in the Central Valley. The reasons for the change is to accommodate relocating the Pacific Gas and Electric relocation within the existing right-of-way. Alberto Lopez - Senior Contract Manager Vicente Alberola - Project Director Patrick Jolly - PCM Design Build Oversight Manager
CP 2-3 HSR 13-57 118 11/23/2019 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Hanford Viaduct Precast Concrete Piling Order $2,898,450.00 This is a change to a contract for design and construction services in the Central Valley. The reasons for the change is a time and material change of precast conrete pile to be used for construction of the Hanford Viaduct structure. Alberto Lopez - Senior Contract Manager Vicente Alberola - Project Director Patrick Jolly - PCM Design Build Oversight Manager
CP 2-3 HSR 13-57 45.1 11/20/2019 Dragados/Flatiron Joint Venture Administrative Agreement for Settlement, Release and Waiver for (1) Time Impacts and Delays Through July 31, 2019; (2) Certain Disputes $133,930,912.00 This is a change to a contract for design and construction services in the Central Valley. The reasons for the change order is to resolve delays, delay related impacts and specific disputes with the contractor. Please see the change order for an explicit listing of resolved disputes. Joe Hedges - Chief Operating Officer Jose Luiz Mendez - President, Dragados/Flatiron Alberto Lopez - State Senior Contract Manager
CP 2-3 HSR 13-57 114 10/12/2019 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Ancillary Facility Site Changes $137,214.00 This is a change to a contract for design and construction services in the Central Valley. The reasons for the change is for the design work for the modified ancillary facility locations, as well as the additional design effort to finalize the ancillary facility locations. Alberto Lopez - Senior Contract Manager Vicente Alberola - Project Director Patrick Jolly - PCM Design Build Oversight Manager
CP 2-3 HSR 13-57 105 9/27/2019 Dragados/Flatiron Joint Venture Changes to Plans and Specifications State Route 43 Crossing Kings River (1H-03) $791,800.00 This is a change to a contract for design and construction services in the Central Valley. The reasons for the change is for redesign work. Caltrans issued the State Route 43 Ultimate Transportation Concept Report (TCR) which included implications for the design of California High Speed Rail Authority Bridge 1H-03 after Dragados/Flatiron Joint Venture (DFJV) was awarded the project. A study was performed by DFJV to determine the specific impacts of the TCR at the Kings River (DFJV Bridge 1H-03). The optimum Alternative identified in the DFJV study that facilitated the required Caltrans 62’ median width at this location and did not affect the California High Speed Rail profile was a single span concrete tied arch bridge type. Alberto Lopez - Senior Contract Manager Vicente Alberola - Project Director Patrick Jolly - PCM Design Build Oversight Manager
CP 2-3 HSR 13-57 115 9/23/2019 Dragados/Flatiron Joint Venture Third-Party Related Department of Toxic Substance Control Reimbursement Agreement $13,876.00 This is a change to a contract for design and construction services in the Central Valley. The reasons for the change is for reimbursement of paid services to the Department of Toxic Substances Control . Alberto Lopez - Senior Contract Manager Vicente Alberola - Project Director Patrick Jolly - PCM Design Build Oversight Manager
CP 2-3 HSR 13-57 10.8 9/6/2019 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Tulare County Avenue 136 - Concrete Box Structure and Roadway $5,846,353.00 This is a change to a contract for design and construction services in the Central Valley. The reasons for the change is for redesign for a new box structure undercrossing for the High-Speed Rail alignment at Avenue 136 in Tulare County. Joe Hedges - Chief Operating Officer Vicente Alberola - Project Director Patrick Jolly - PCM Design Build Oversight Manager
CP 2-3 HSR 13-57 109 9/6/2019 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Project Floodplain Limit Increases $18,809,463.00 This is a change to a contract for design and construction services in the Central Valley. The reasons for the change is because there was a change in the limits of the floodplain within the project limits and this change occurred well after Contractor could have planned it into its original scope of work. Joe Hedges - Chief Operating Officer Vicente Alberola - Project Director Patrick Jolly - PCM Design Build Oversight Manager
CP 2-3 HSR 13-57 24.1.2 9/2/2019 Dragados/Flatiron Joint Venture Environmental Credit from Change Order 24.1 ($2,412.04) This is a change to a contract for design and construction services in the Central Valley. The reasons for the change is for remediation costs associated with the abatement of hazardous materials located at 2310 E. Floral Avenue, Selma, CA (FB-10-0708), as identified in the Asbestos Survey Report (ASR) for subject property. Alberto Lopez - Senior Contract Manager Vicente Alberola - Project Director Patrick Jolly - PCM Design Build Oversight Manager
CP 2-3 HSR 13-57 103 9/2/2019 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Fargo Redsgn Due Rev ROW Acq. Limits $33,170.00 This is a change to the contract for design and construction services in the Central Valley. The change order fits the design for Fargo Avenue within new land constraints. Alberto Lopez - Senior Contract Manager Vicente Alberola — Project Director Patrick Jolly - PCM Design Build Oversight Manager
CP 2-3 HSR 13-57 107 9/2/2019 Dragados/Flatiron Joint Venture Utility Relocation CID 200pct Flow - Davis Ditch $844,191.00 This is a change to the contract for design and construction services in the Central Valley. The change order increases the size of an irrigation facility under the future high-speed rail system. Alberto Lopez - Senior Contract Manager Vicente Alberola — Project Director Patrick Jolly - PCM Design Build Oversight Manager
CP 2-3 HSR 13-57 108 9/2/2019 Dragados/Flatiron Joint Venture Utility Relocation CID 200pct Flow - Iowa Ditch $1,431,274.00 This is a change to the contract for design and construction services in the Central Valley. The change order allows for the relocation of an irrigation facility out of the way of the future high-speed rail system. Alberto Lopez - Senior Contract Manager Vicente Alberola — Project Director Patrick Jolly - PCM Design Build Oversight Manager
CP 2-3 HSR 13-57 110 9/2/2019 Dragados/Flatiron Joint Venture Utility Relocation CTC FB160291 10" Carrier Pipe $28,355.00 This is a change to the contract for design and construction services in the Central Valley. The change order allows for the installation of a pipe on a specific property. Alberto Lopez - Senior Contract Manager Vicente Alberola — Project Director Patrick Jolly - PCM Design Build Oversight Manager
CP 2-3 HSR 13-57 24.11 8/30/2019 Dragados/Flatiron Joint Venture Environmental Haz Mat Abatement FB-10-0398 $17,969.18 This is a change to a contract for design and construction services in the Central Valley. The change order allows for the removal of hazardous materials from buildings located on high-speed rail right of way on E. Nebraska Avenue in the city of Fresno. Alberto Lopez - Senior Contract Manager Vicente Alberola — Project Director Patrick Jolly - PCM Design Build Oversight Manager
CP 2-3 HSR 13-57 24.12.1 8/30/2019 Dragados/Flatiron Joint Venture Environmental Haz Mat Abatement Conc. Slab Removal $30,998.00 This is a change to a contract for design and construction services in the Central Valley. The change order allows for the removal of hazardous materials located on high-speed rail right of way Oregon Avenue and Road 19 near Corcoran, CA. Alberto Lopez - Senior Contract Manager Vicente Alberola — Project Director Patrick Jolly - PCM Design Build Oversight Manager
CP 2-3 HSR 13-57 24.14 8/30/2019 Dragados/Flatiron Joint Venture Environmental Haz Mat Abatement COP 0088.14 $98,094.00 This is a change to a contract for design and construction services in the Central Valley. The change order allows for the removal of hazardous materials from buildings located on high-speed rail right of way on E. Clarkson Avenue and Elkhorn Avenue in the city of Fresno. Alberto Lopez - Senior Contract Manager Vicente Alberola — Project Director Patrick Jolly - PCM Design Build Oversight Manager
CP 2-3 HSR 13-57 100 8/30/2019 Dragados/Flatiron Joint Venture Utility Relocation Elkhorn Ditch Relocation Final Dsgn $165,850.00 This is a change to the contract for design and construction services in the Central Valley. The change order is to move an irrigation ditch out of the way of the future high-speed rail system. Alberto Lopez - Senior Contract Manager Vicente Alberola — Project Director Patrick Jolly - PCM Design Build Oversight Manager
CP 2-3 HSR 13-57 101 8/30/2019 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Dover Intersection Sight Distance $42,800.00 This is a change to the contract for design and construction services in the Central Valley. The change order is to design the North 8th Avenue Connector Road to Dover Avenue to miss and protect a tree located along the road. Alberto Lopez - Senior Contract Manager Vicente Alberola — Project Director Patrick Jolly - PCM Design Build Oversight Manager
CP 2-3 HSR 13-57 104 8/30/2019 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Type 2 Structure Concrete Barrier $839,950.00 This is a change to the contract for design and construction services in the Central Valley. This change order allows for a re-design of a concrete barrier to a new specification. Alberto Lopez - Senior Contract Manager Vicente Alberola — Project Director Patrick Jolly - PCM Design Build Oversight Manager
CP 2-3 HSR 13-57 112 8/30/2019 Dragados/Flatiron Joint Venture Changes to Plans and Specifications South Ave. Grade Separation $982,667.00 This is a change to a contract for design and construction services in the Central Valley. The change order changes the shoulder width of the South Avenue bridge over the high-speed rail system in accordance with Authority’s Directive Letter number 65. Alberto Lopez - Senior Contract Manager Vicente Alberola — Project Director Patrick Jolly - PCM Design Build Oversight Manager
CP 2-3 HSR 13-57 95 8/30/2019 Dragados/Flatiron Joint Venture Third-Pary Related Doubling Flow Capacity of Consolidated Irrigation District at Elkhorn Ditch $4,460,874.00 This is a change to a contract for design and construction services in the Central Valley. The reasons for the change is change in law to require doubling the flow capacities to facilities of the Consolidated Irrigation District (CID), which resulted in additional scope to the contract. Alberto Lopez - Senior Contract Manager Vicente Alberola Project Manager Patrick E Jolly, PE DB Oversight Manager
CP 2-3 HSR 13-57 87 8/27/2019 Dragados/Flatiron Joint Venture Changes to Plans and Specifications E. Lincoln Ave Grade Separation $58,088.16 This is a change to a contract for design and construction services in the Central Valley. The change order develops a design for an underpass for Lincoln Avenue in accordance with Authority’s Directive Letter number 28. Alberto Lopez - Senior Contract Manager Vicente Alberola — Project Director Patrick Jolly - PCM Design Build Oversight Manager
CP 2-3 HSR 13-57 98 8/27/2019 Dragados/Flatiron Joint Venture Changes to Plans and Specifications SR43 Hesse Ave Dsgn Struct.CT UTC $84,263.00 This is a change to a contract for design and construction services in the Central Valley. The change order incorporates the 2015 update to the Caltrans Standard Specifications and the Transportation Concept Report for State Route 43 into the construction contract for the design of the Hesse Avenue bridge. Alberto Lopez - Senior Contract Manager Vicente Alberola — Project Director Patrick Jolly - PCM Design Build Oversight Manager
CP 2-3 HSR 13-57 99 8/27/2019 Dragados/Flatiron Joint Venture Changes to Plans and Specifications SR43 Ave 88 Struct.Dsgn CALTRANS UTC $84,263.00 This is a change to a contract for design and construction services in the Central Valley. The change order incorporates the 2015 update to the Caltrans Standard Specifications and the Transportation Concept Report for State Route 43 into the construction contract for the design of the Avenue 88 bridge. Alberto Lopez - Senior Contract Manager Vicente Alberola — Project Director Patrick Jolly - PCM Design Build Oversight Manager
CP 2-3 HSR 13-57 102 8/27/2019 Dragados/Flatiron Joint Venture Changes to Plans and Specifications City Corcoran Increased Dsgn Speed $124,950.00 This is a change to the contract for design and construction services in the Central Valley. The change order allows for the design of new connector roadways at County roads 5 1/2 Avenue to Niles Avenue; and 5th Avenue to Orange Avenue to comply with the change in criteria for a higher vehicle speed limit. Alberto Lopez - Senior Contract Manager Vicente Alberola — Project Director Patrick Jolly - PCM Design Build Oversight Manager
CP 2-3 HSR 13-57 73 7/25/2019 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Primary Type 2 Open Abutments-Const $30,773,032.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change order is to implement new design requirements for bridges over the future high-speed rail system. Joe Hedges - Chief Operating Officer Vicente Alberola — Project Director Patrick Jolly - PCM Design Build Oversight Manager
CP 2-3 HSR 13-57 86.3 7/17/2019 Dragados/Flatiron Joint Venture Third-party Related Segment 2 - Private Irrigation Cross $2,285,989.00 This is a change to a contract for design and construction services in the Central Valley. This change order pays for installation of steel casings to protect private irrigation pipes that cross under the future high-speed rail system. Alberto Lopez - Senior Contract Manager Vicente Alberola — Project Director Patrick Jolly - PCM Design Build Oversight Manager
CP 2-3 HSR 13-57 97 7/17/2019 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Engineering Solutions to Stay within ROW $1,712,000.00 This is a change to a contract for design and construction services in the Central Valley. This change order allows for completion of the design of trackway drainage, intrusion protection barriers and utility relocations based on revised standards in Directive Letter no. 00035 (DL 35) to stay within Authority's right-of-way. Alberto Lopez - Senior Contract Manager Vicente Alberola — Project Director Patrick Jolly - PCM Design Build Oversight Manager
CP 2-3 HSR 13-57 10.5.1 7/16/2019 Dragados/Flatiron Joint Venture Third-party Related Tulare Co.Force Account Fees $100,000.00 This is a change to a contract for design and construction services in the Central Valley. This change order is for design services and third-party coordination to provide roadway improvements at Avenue 120 and Avenue 24, and reconstruction of a waterline in Tulare County. The work is coordinated by the general contractor in Wasco responsible for designing and constructing the future system. Alberto Lopez - Senior Contract Manager Vicente Alberola — Project Director Patrick Jolly - PCM Design Build Oversight Manager
CP 2-3 HSR 13-57 70 7/16/2019 Dragados/Flatiron Joint Venture Changes to Plans and Specifications GTC - Kent & Kansas E/W Embankment $459,495.00 This is a change to a contract for design and construction services in the Central Valley. The change order allow for completion of construction on the embankment between Kent Avenue and Kansas Avenue in Kings County for the future high-speed rail system. Alberto Lopez - Senior Contract Manager Vicente Alberola — Project Director Patrick Jolly - PCM Design Build Oversight Manager
CP 2-3 HSR 13-57 78 7/16/2019 Dragados/Flatiron Joint Venture Third-party Related Traffic Studies at Mountain View $4,225.00 This is a change to a contract for design and construction services in the Central Valley. This change order allows for completion of traffic studies on Mountain View Avenue Alberto Lopez - Senior Contract Manager Vicente Alberola — Project Director Patrick Jolly - PCM Design Build Oversight Manager
CP 2-3 HSR 13-57 81 7/16/2019 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Kings Co. Underpasses at Cairo & 9th $38,520.00 This is a change to a contract for design and construction services in the Central Valley. This change order provides roadway design services for underpasses at Cairo Avenue and 9th Avenue. Alberto Lopez - Senior Contract Manager Vicente Alberola — Project Director Patrick Jolly - PCM Design Build Oversight Manager
CP 2-3 HSR 13-57 91 7/16/2019 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Undertrack Conduits $255,291.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to design undertrack conduits and implement revised standards in Directive Letter no. 00091 (DL 91).   Alberto Lopez - Senior Contract Manager Vicente Alberola — Project Director Patrick Jolly - PCM Design Build Oversight Manager
CP 2-3 HSR 13-57 90 5/27/2019 Dragados/Flatiron Joint Venture Utility Relocation UG Ductbanks-Manholes System Sites $236,924.00 This is a change to a contract for design services in the Central Valley. The reason for the change is to complete the design of ductbanks and manholes for the future high-speed rail system. Alberto Lopez, Senior Contract Manager Vicente Alberola, Project Director Patrick E. Jolly, PCM Design-Build Oversight Manager
CP 2-3 HSR 13-57 80 5/22/2019 Dragados/Flatiron Joint Venture Utility Relocation Add'l Waterline at 4 1/2 Ave -Design $32,100.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to for additional design associated with an unexpected water line. Alberto Lopez, Senior Contract Manager Vincente Alberola - Project Director Patrick Jolly - DB Oversight Manager
CP 2-3 HSR 13-57 86.4 5/22/2019 Dragados/Flatiron Joint Venture Third-party Related Segment 1, 2, 3 - Private Irrigation $1,055,726.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to construct 10 steel casings to protect private irrigation pipes that cross under the future high-speed rail system. Alberto Lopez, Senior Contract Manager Vicente Alberola, Project Director Patrick E. Jolly, PCM Design-Build Oversight Manager
CP 2-3 HSR 13-57 89 5/9/2019 Dragados/Flatiron Joint Venture Third-party Related Caltrans 2015-16 6th Edition Update $17,883.00 This is a change to a contract for final design services in the Central Valley. The reason for the change is to complete the design work to implement updates to design required by the 2015 and 2016 changes to the 6th Edition of the Caltrans Highway Design Manual. Alberto Lopez, Senior Contract Manager Vicente Alberola, Project Director Patrick E. Jolly, PCM Design-Build Oversight Manager
CP 2-3 HSR 13-57 93 5/3/2019 Dragados/Flatiron Joint Venture Right-of-Way (ROW) Related GTC - HOUSTON/IONA TO LANSING $4,700,329.00 This is a change to a contract for construction services in the Central Valley. The reason for the change is to complete construction on the embankment between Iona Avenue and Lansing Avenue in Kings County for the future high-speed rail system. Alberto Lopez, Senior Contract Manager Vicente Alberola, Project Director Patrick E. Jolly, PCM Design-Build Oversight Manager
CP 2-3 HSR 13-57 24.13 4/24/2019 Dragados/Flatiron Joint Venture Environmental Haz Mat Abatement COP 88.17-FB100876 $11,431.43 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to remove asbestos in one of the structures to be demolished for the construction of high-speed rail. William Grimsley - Director of Design & Construction Vicente Alberola - Project Director Patrick E. Jolly, P.E.- PCM Design Build Oversight Manager
CP 2-3 HSR 13-57 50.1 4/24/2019 Dragados/Flatiron Joint Venture Changes to Plans and Specifications AAAT Bike Pedestrian U/P Design $413,483.31 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to finalize the design of the bike and pedestrian underpass at the White River crossing. William Grimsley - Director of Design & Construction Vicente Alberola - Project Director Patrick E. Jolly, P.E.- PCM Design Build Oversight Manager
CP 2-3 HSR 13-57 75 4/24/2019 Dragados/Flatiron Joint Venture Third-party Related Special Trk Work Crossover Turnouts $60,545.28 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to complete the design of track work based on revised standards for train speeds in areas not on the main line track. William Grimsley - Director of Design & Construction Vincente Alberola - Project Director Patrick Jolly - DB Oversight Manager
CP 2-3 HSR 13-57 76 4/24/2019 Dragados/Flatiron Joint Venture Third-party Related GTC - Wristen Ditch Bypass $392,924.00 This is a change to the contract for design and construction services in the Central Valley. The reason for the change is to complete the design and construction work to build a temporary bypass for a drainage ditch to allow construction of a bridge embankment. William Grimsley - Director of Design & Construction Vincente Alberola - Project Director Patrick Jolly - DB Oversight Manager
CP 2-3 HSR 13-57 77 4/24/2019 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Maint. Access Under Type2 Structures $339,242.43 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to complete the design of maintenance access for future high-speed rail under bridges. William Grimsley - Director of Design & Construction Vincente Alberola - Project Director Patrick Jolly - DB Oversight Manager
CP 2-3 HSR 13-57 85 4/18/2019 Dragados/Flatiron Joint Venture Differing Site Conditions Subsidence Impacts Various Locations $989,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to purchase, haul and place additional embankment materials to address subsidence at specific locations. William Grimsley - Director of Design & Construction Vincente Alberola - Project Director Patrick Jolly - DB Oversight Manager
CP 2-3 HSR 13-57 1.1 3/12/2019 Dragados/Flatiron Joint Venture Administrative DFJV-HSRA Partnering Costs $100,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for the Authority to meet their contractual obligations to pay 50% of the costs associated with partnering activities. William Grimsley - Director of Design & Construction Michael Costa - Project Director Patrick E. Jolly, P.E.- PCM Design Build Oversight Manager
CP 2-3 HSR 13-57 44.1 3/12/2019 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Increase One Span at Nebraska Ave $- This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to revise the design of the Nebraska Avenue overcrossing to make it longer. The costs for this change order, $134,426.51, were paid in change order number 48. William Grimsley - Director of Design & Construction Michael Costa - Project Director Patrick E. Jolly, P.E.- PCM Design Build Oversight Manager
CP 2-3 HSR 13-57 88 3/9/2019 Dragados/Flatiron Joint Venture Third-party Related Minnewawa Ave. RDWY Improvements $48,150.00 This is a change to a contract for final design services in the Central Valley. The reason for the change is to complete the design of a roadway based on revised standards in Directive Letter no. 00093 (DL 93) to improve Minnewawa Avenue Roadway. Alberto Lopez, Senior Contract Manager Vicente Alberola, Project Director Patrick E. Jolly, PCM Design-Build Oversight Manager
CP 2-3 HSR 13-57 86.2 3/4/2019 Dragados/Flatiron Joint Venture Third-party Related Segment 3 - Private Irrigation $469,325.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to pay for installation of steel casings to protect private irrigation pipes that cross under the future high-speed rail system. William Grimsley, Director of Design & Construction Michael Costa, Project Director Patrick E. Jolly, PCM Design-Build Oversight Manager
CP 2-3 HSR 13-57 86 3/1/2019 Dragados/Flatiron Joint Venture Third-party Related Segment 1 - Private Irrigation $1,014,708.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to pay for installation of steel casings to protect private irrigation pipes that cross under the future high-speed rail system. William Grimsley - Director of Design & Construction Michael Costa - Project Director Patrick Jolly - DB Oversight Manager
CP 2-3 HSR 13-57 86.1 3/1/2019 Dragados/Flatiron Joint Venture Third-party Related Segment 2 - Private Irrigation $3,082,679.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to pay for installation of steel casings to protect private irrigation pipes that cross under the future high-speed rail system. William Grimsley - Director of Design & Construction Michael Costa - Project Director Patrick Jolly - DB Oversight Manager
CP 2-3 HSR 13-57 10.5 2/20/2019 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Ave 120 and Ave 24 Reconstruction $4,679,109.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to complete construction of road improvements in the County of Tulare. William Grimsley - Director of Design & Construction Michael Costa - Project Director Patrick E. Jolly, P.E.- PCM Design Build Oversight Manager
CP 2-3 HSR 13-57 83 2/20/2019 Dragados/Flatiron Joint Venture Differing Site Conditions Undisclosed Dump Site $370,446.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to complete removal and disposal of debris from a dump site that was discovered after the contract was executed. William Grimsley - Director of Design & Construction Michael Costa - Project Director Patrick Jolly - DB Oversight Manager
CP 2-3 HSR 13-57 53.1 2/8/2019 Dragados/Flatiron Joint Venture Right-of-Way (ROW) Related Lawrence (Te Velde) Canal $- This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to finalize the design for the realignment of the Lawrence (Te Velde) canal through the Te Velde Dairy property. The costs for this change order, $179,602.92, were paid in change order number 48. 1 William Grimsley - Director of Design & Construction Michael Costa - Project Director Patrick E. Jolly, P.E.- PCM Design Build Oversight Manager
CP 2-3 HSR 13-57 62 2/8/2019 Dragados/Flatiron Joint Venture Environmental BNSF Bowles Re-Exam $- This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to complete the work required to environmentally clear a change to the design negotiated with BNSF. The costs for this change order, $36,916, were paid in Change Order number 48. William Grimsley - Director of Design & Construction Michael Costa - Project Director Patrick Jolly - DB Oversight Manager
CP 2-3 HSR 13-57 72 2/8/2019 Dragados/Flatiron Joint Venture Third-party Related CID 200% of Existing Flow Capacity $- This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to complete the design of irrigation facilities based on revised standards for flow capacity. The costs for this change order, $34,233, were paid in Change Order number 48. William Grimsley - Director of Design & Construction Michael Costa - Project Director Patrick Jolly - DB Oversight Manager
CP 2-3 HSR 13-57 41.1 1/31/2019 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Install Spare Conduits_CONSTRUCTION $3,943,136.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to install spare conduits for future use by communication companies. William Grimsley - Director of Design & Construction Michael Costa - Project Director Patrick E. Jolly, P.E.- PCM Design Build Oversight Manager
CP 2-3 HSR 13-57 63 1/16/2019 Dragados/Flatiron Joint Venture Environmental Rare Plant Salvage $- This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to comply with environmental requirement to preserve and store plant seeds for replanting after the construction. The costs for this change order, $7,500, were paid in Change Order number 48. William Grimsley - Director of Design & Construction Michael Costa - Project Director Patrick Jolly - DB Oversight Manager
CP 2-3 HSR 13-57 71 1/15/2019 Dragados/Flatiron Joint Venture Changes to Plans and Specifications GTC - CP Bowles Embankment $285,686.00 This is a change to the contract for design and construction services in the Central Valley. The reason for the change is to move BNSF railroad track out of the way of the future high-speed rail track. William Grimsley - Director of Design & Construction Michael Costa - Project Director Patrick Jolly - DB Oversight Manager
CP 2-3 HSR 13-57 24.10 11/1/2018 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Haz Mat Abatement COP 88.14, 2 Sites $98,713.19 This is a change to a contract for design and construction services in the Central Valley.  The reasons for the change is for the added scope resulting from remediation costs associated with abatement of hazardous materials as identified in an Asbestos and Lead Survey report (ASR). The ASR identified lead based paint in the structure to be demolished, requiring lead abatement. William Grimsley, Director of Infrastructure Delivery (CEA B) Michael Cost Project Manager Patrick E Jolly, PE DB Oversight Manager
CP 2-3 HSR 13-57 24.6.1 11/1/2018 Dragados/Flatiron Joint Venture Environmental Haz Mat Abatement COP 0088.10.1 $24,399.92 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to remove hazardous materials from a property acquired by the Authority. William Grimsley - Interim Deputy Director of Infrastructure Delivery Michael Costa - Project Director Patrick Jolly - DB Oversight Manager
CP 2-3 HSR 13-57 74 10/16/2018 Dragados/Flatiron Joint Venture Utility Relocation PG&E Facility Work Settlement CO $- This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to finalize negotiations of disputes regarding PG&E work, specifically regarding sub contractor coordination fees (mark ups), insurance costs and liability, including delays that would impact the contractor's ability to finish on time. William Grimsley - Interim Deputy Director of Infrastructure Delivery Michael Costa - Project Director Patrick Jolly - DB Oversight Manager
CP 2-3 HSR 13-57 24.10.1 9/11/2018 Dragados/Flatiron Joint Venture Environmental Haz Mat Abatement COP 88.1 $32,074.62 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to remove hazardous waste from a property owned by the Authority and make the sites safe for work. William Grimsley - Director of Design and Construction Michael Costa - Project Director Patrick Jolly - DB Oversight Manager
CP 2-3 HSR 13-57 24.12 9/11/2018 Dragados/Flatiron Joint Venture Environmental Haz Mat Abatement COP 0088.16 $60,050.70 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to remove hazardous materials from a property acquired by the Authority. Terry Ogle - Director of Design & Construction Michael Costa - Project Director Patrick Jolly - DB Oversight Manager
CP 2-3 HSR 13-57 24.1.1 7/20/2018 Dragados/Flatiron Joint Venture Environmental Haz Mat Abatement COP 88.9 - 1 Site $15,120.39 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to remove hazardous materials from a property acquired by the Authority. Terry Ogle - Director of Design & Construction Michael Costa - Project Director Patrick Jolly - DB Oversight Manager
CP 2-3 HSR 13-57 24.4.1 7/20/2018 Dragados/Flatiron Joint Venture Environmental HazMat Lead Abatement COP 88.7.1 $286,431.52 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to remove hazardous materials from a property acquired by the Authority. Terry Ogle - Director of Design & Construction Michael Costa - Project Director Patrick Jolly - DB Oversight Manager
CP 2-3 HSR 13-57 59 7/20/2018 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Study Shift Avenue 56 GS Alignment $- This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to conduct an impact study of moving the Avenue 56 bridge further south. The costs for this change order, $26,665.39, were paid in Change Order number 48. Terry Ogle - Director of Design & Construction Michael Costa - Project Director Patrick Jolly - DB Oversight Manager
CP 2-3 HSR 13-57 60 7/20/2018 Dragados/Flatiron Joint Venture Third-party Related Alpaugh Irrigation District Permit $75,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to finalize negotiations with Alpaugh Irrigation District. Terry Ogle - Director of Design & Construction Michael Costa - Project Director Patrick Jolly - DB Oversight Manager
CP 2-3 HSR 13-57 64 7/20/2018 Dragados/Flatiron Joint Venture Right-of-Way (ROW) Related GTC-Excelsior Ave E/W Embankments $3,299,700.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to bring in material for construction at Excelsior Avenue by a longer route with additional trucking costs. Terry Ogle - Director of Design & Construction Michael Costa - Project Director Patrick Jolly - DB Oversight Manager
CP 2-3 HSR 13-57 65 7/20/2018 Dragados/Flatiron Joint Venture Right-of-Way (ROW) Related GTC-Flint Avenue East Embankment $1,126,716.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to bring in material for construction at Flint Avenue by a longer route with additional trucking costs. Terry Ogle - Director of Design & Construction Michael Costa - Project Director Patrick Jolly - DB Oversight Manager
CP 2-3 HSR 13-57 66 7/20/2018 Dragados/Flatiron Joint Venture Right-of-Way (ROW) Related GTC-Fargo Avenue East Embankment $1,715,322.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to bring in material for construction at Fargo Avenue by a longer route with additional trucking costs. Terry Ogle - Director of Design & Construction Michael Costa - Project Director Patrick Jolly - DB Oversight Manager
CP 2-3 HSR 13-57 67 7/20/2018 Dragados/Flatiron Joint Venture Right-of-Way (ROW) Related GTC-Avenue 88 E/W Embankments $1,858,935.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to bring in material for construction at Avenue 88 by a longer route with additional trucking costs. Terry Ogle - Director of Design & Construction Michael Costa - Project Director Patrick Jolly - DB Oversight Manager
CP 2-3 HSR 13-57 58 7/18/2018 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Manning Expressway Cross slope Rev $- This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to allow future road widening at Manning Avenue. The costs for this change order, $184,681.26, were paid in Change Order number 48. Terry Ogle - Director of Design & Construction Michael Costa - Project Director Patrick Jolly - DB Oversight Manager
CP 2-3 HSR 13-57 52.1 5/9/2018 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Houston Ave - Fire Station Drvwys $- This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to modify the design at Houston Avenue to reduce impacts to Kings County Fire Station 4. The costs for this change order, $150,368.02, were paid in Change Order number 48. Terry Ogle - Director of Design & Construction Michael Costa - Project Director Patrick Jolly - DB Oversight Manager
CP 2-3 HSR 13-57 54 5/9/2018 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Hormel Feed Mill Horz Wly Main Shift $- This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to modify the final route in the vicinity of Hormel Feed Mill to avoid impacts to the mill. The costs for this change order, $285,499.23, were paid in Change Order number 48. Terry Ogle - Director of Design & Construction Michael Costa - Project Director Patrick Jolly - DB Oversight Manager
CP 2-3 HSR 13-57 55 5/9/2018 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Silveria Box Structure - Design $446,267.02 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to design a new crossing under the future high-speed rail system at Avenue 156. Terry Ogle - Director of Design & Construction Michael Costa - Dragados / Flatiron Joint Venture Patrick Jolly - DB Oversight Manager
CP 2-3 HSR 13-57 56 5/9/2018 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Lansing Ave Undercrossing - Design $637,520.35 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to design a new crossing under the future high-speed rail system at Lansing Avenue. Terry Ogle - Director of Design & Construction Michael Costa - Dragados / Flatiron Joint Venture Patrick Jolly - DB Oversight Manager
CP 2-3 HSR 13-57 57 5/9/2018 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Access Restriction Fencing $81,385.04 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to modify the design for fencing to keep people out of the future high-speed rail system. Terry Ogle - Director of Design & Construction Michael Costa - Project Director Patrick Jolly - DB Oversight Manager
CP 2-3 HSR 13-57 35.2 5/3/2018 Dragados/Flatiron Joint Venture Third-party Related Caltrans IQA - Phase 2 ROW ($640,000.00) This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to implement the agreement between the Authority and Caltrans for Caltrans to bill their services on the project directly to the Authority. This change order provides the Authority a credit for removing these activities from the contract. Terry Ogle - Director of Design & Construction Michael Costa - Dragados / Flatiron Joint Venture Patrick Jolly - DB Oversight Manager
CP 2-3 HSR 13-57 52 4/24/2018 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Houston Ave Grade Sep Span Reduction $- This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to design the Houston Avenue bridge as a shorter structure. The cost for this work, $147,244.45, is included in change order number 48. Terry Ogle - Director of Design & Construction Michael Costa - Dragados / Flatiron Joint Venture Patrick Jolly - DB Oversight Manager
CP 2-3 HSR 13-57 35.1 4/19/2018 Dragados/Flatiron Joint Venture Third-party Related Caltrans IQA - Construction Phase ($4,130,000.00) This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to implement the agreement between the Authority and Caltrans for Caltrans to bill their services on the project directly to the Authority rather than through the general contractor. This change order provides the Authority a credit for removing these activities from the contract. Terry Ogle - Director of Design & Construction Michael Costa - Dragados / Flatiron Joint Venture Patrick Jolly - DB Oversight Manager
CP 2-3 HSR 13-57 53 4/10/2018 Dragados/Flatiron Joint Venture Right-of-Way (ROW) Related Design for Te Velde Dairy (Ave 136) $- This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to complete the design for avoidance of the TeVelde Dairy. The cost of this work, $535,010.36 is included in change order number 48. Terry Ogle - Director of Design & Construction Michael Costa - Dragados / Flatiron Joint Venture
CP 2-3 HSR 13-57 36.2 4/3/2018 Dragados/Flatiron Joint Venture Utility Relocation Deductive Change Order - Unilateral ($922,883.00) This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to rescind change order numbers 36 and 36.1. Terry Ogle - Director of Design & Construction Michael Costa - Dragados / Flatiron Joint Venture
CP 2-3 HSR 13-57 24.9 3/21/2018 Dragados/Flatiron Joint Venture Environmental Haz Mat Abatement COP 88.13 -5 Sites $116,755.47 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to remove hazardous materials at five properties bought by the Authority. Terry Ogle - Director of Design & Construction Michael Costa - Dragados / Flatiron Joint Venture Carole Sanders - DB Oversight Manager
CP 2-3 HSR 13-57 24.8 2/20/2018 Dragados/Flatiron Joint Venture Environmental Haz Mat Abatement COP 88.12, 1 Site $10,528.77 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to remove hazardous materials at one property in Hanford bought by the Authority. Terry Ogle - Director of Design & Construction Michael Costa - Dragados / Flatiron Joint Venture Carole Sanders - DB Oversight Manager
CP 2-3 HSR 13-57 24.7 2/13/2018 Dragados/Flatiron Joint Venture Environmental Haz Mat Abatement COP 88.11, 2 Sites $26,156.60 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to remove hazardous materials at two properties on E. Floral Avenue in Fresno bought by the Authority. Terry Ogle - Director of Design & Construction Michael Costa - Dragados / Flatiron Joint Venture Carole Sanders - DB Oversight Manager
CP 2-3 HSR 13-57 50 12/29/2017 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Prepare AAAT Bike/Ped Design Concept $21,379.43 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to prepare the AAAT Bike/Pedestrian Design Concept. Scott Jarvis - Chief of Engineering Michael Costa - Dragados / Flatiron Joint Venture Carole Sanders - DB Oversight Manager
CP 2-3 HSR 13-57 51 12/29/2017 Dragados/Flatiron Joint Venture Changes to Plans and Specifications OCS Strcl Conn to Type 1 Aerial Strc $- This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to design future high-speed rail overhead electrical system connections to bridges. Some of the work ($113,555.24) was paid via change order number 48. Terry Ogle - Director of Design & Construction Michael Costa - Dragados / Flatiron Joint Venture Carole Sanders - DB Oversight Manager
CP 2-3 HSR 13-57 45 12/20/2017 Dragados/Flatiron Joint Venture Right-of-Way (ROW) Related Time Extension No. 1 $50,750,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to settle and resolve all time delays and impacts prior to August 31, 2017. Thomas Fellenz - Interim Chief Executive Officer Rishard Grabinski - Senior Vice President, Western Region Roy Hill - Chief Program Officer
CP 2-3 HSR 13-57 24.5 12/19/2017 Dragados/Flatiron Joint Venture Environmental Haz Mat Abatement COP 88.8 - 1 Site $11,984.72 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to remove a hazardous underground storage tank on a perperty bought by the Authority. Terry Ogle - Director of Design & Construction Michael Costa - Dragados / Flatiron Joint Venture Carole Sanders - DB Oversight Manager
CP 2-3 HSR 13-57 24.6 12/19/2017 Dragados/Flatiron Joint Venture Environmental Haz Mat Abatement COP 88.10 - 1 Site $51,896.64 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to remove hazardous materials at two properties bought by the Authority on E. Floral Avenue in Fresno. Glady Guzman - Design & Construction Manager Michael Costa - Dragados / Flatiron Joint Venture Carole Sanders - DB Oversight Manager
CP 2-3 HSR 13-57 10.7 12/15/2017 Dragados/Flatiron Joint Venture Environmental Small Mammal Trapping $347,339.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to conduct small mammal trapping as part of the Authority's environmental commitments. Terry Ogle - Director of Design & Construction Michael Costa - Dragados / Flatiron Joint Venture Carole Sanders - DB Oversight Manager
CP 2-3 HSR 13-57 49 12/6/2017 Dragados/Flatiron Joint Venture Environmental Costs Associated with BVLOS $18,785.82 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to protect the Buena Vista Lake ornate shrew as part of the Authority's environmental commitments. Jorge Granados - Design & Construction Manager Michael Costa - Dragados / Flatiron Joint Venture Carole Sanders - DB Oversight Manager
CP 2-3 HSR 13-57 17.1 10/23/2017 Dragados/Flatiron Joint Venture Third-party Related Jurisdictional Waters Add'l Work $11,199.37 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to finish the report authorized in change order number 17 based on additional Authority comments. The report details which permiting agency has jurisdiction over water resources in the Kings River Complex. Glady Guzman - Design & Construction Manager Michael Costa - Dragados / Flatiron Joint Venture Carole Sanders - DB Oversight Manager
CP 2-3 HSR 13-57 36.1 10/12/2017 Dragados/Flatiron Joint Venture Utility Relocation Rescinded - PGE-DFJV Staffing $669,168.00 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to design and construct the relocation of PG&E facilities to move them out of the way of the future high-speed rail system. Glady Guzman - Design & Construction Manager Michael Costs - Dragados / Flatiron Joint Venture Carlo Sanders - DB Oversight Manager
CP 2-3 HSR 13-57 44 10/10/2017 Dragados/Flatiron Joint Venture Changes to Plans and Specifications DL061, Nebraska Ave GS Design Concep $33,425.55 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to provide design for a bridge at Nebraska Avenue. Glady Guzman - Design & Construction Manager Michael Costa - Dragados / Flatiron Joint Venture Carole Sanders - DB Oversight Manager
CP 2-3 HSR 13-57 15.1 10/9/2017 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Early Work Bridge Design Supplement $343,946.68 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to perform early design work on a bridge. It includes a $1,094,775.39 credit to the Authority for work authorized in change order number 15. Glady Guzman - Design & Construction Manager Michael Costa - Dragados / Flatiron Joint Venture Carole Sanders - DB Oversight Manager
CP 2-3 HSR 13-57 30.1 10/9/2017 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Open Abutment Supplemental - DL 44.1 $504,587.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to do geotechnical investigations at 28 bridge sites due to a design change. Gladys Guzman - Design & Construction Manager Michael Costa - Project Director Carole Sanders - DB Oversight Manager
CP 2-3 HSR 13-57 41 10/9/2017 Dragados/Flatiron Joint Venture Changes to Plans and Specifications DL 20.1, Spare Conduits, Design Cost $199,535.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to perform design and construction of utility conduits under the future high-speed rail system. Gladys Guzman - Design and Construction Manager Michael Costa - Dragados / Flatiron Joint Venture Carole N Sanders - DB Oversight Manager
CP 2-3 HSR 13-57 42 10/9/2017 Dragados/Flatiron Joint Venture Changes to Plans and Specifications DL 065, 8' Shoulders South Avenue GS $60,231.21 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to design roadway shoulders to a new standard at South Avenue Grade Separation. Gladys Guzman - Design & Construction Manager Michael Costa - Project Director Carole Sanders - DB Oversight Manager
CP 2-3 HSR 13-57 43 10/9/2017 Dragados/Flatiron Joint Venture Right-of-Way (ROW) Related DL 56, Richards, Singh, Bettencourt $49,417.42 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is for design services at a property impacted by the future high-speed rail system. Glady Guzman - Design & Construction Manager Michael Costa - Dragados / Flatiron Joint Venture Carole Sanders - DB Oversight Manager
CP 2-3 HSR 13-57 48 10/9/2017 Dragados/Flatiron Joint Venture Administrative Administrative Change Order $2,000,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to implement a partnering agreement between the Design-Builder and the Authority. Glady Guzman - Design & Construction Manager Michael Costa - Dragados / Flatiron Joint Venture Carole Sanders - DB Oversight Manager
CP 2-3 HSR 13-57 24.3 9/14/2017 Dragados/Flatiron Joint Venture Environmental Haz Mat Abatement, COP 88.6 - 2 Site $120,993.61 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to remove hazardous materials at 3 sites. Gladys Guzman - Design & Construction Manager Michael Costa - Project Director Carole Sanders - DB Oversight Manager
CP 2-3 HSR 13-57 24.4 9/14/2017 Dragados/Flatiron Joint Venture Environmental Haz Mat Abatement, COP 88.7, 7 Sites $273,069.13 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to remove hazardous materials at 7 sites. Gladys Guzman - Design & Construction Manager Michael Costa - Project Director Carole Sanders - DB Oversight Manager
CP 2-3 HSR 13-57 10.6 8/8/2017 Dragados/Flatiron Joint Venture Environmental Tulare Co. Review Cost for Sub-Utili $85,727.76 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to fulfill Tulare County Sub-Utility Agreement 1.01. Gladys Guzman - Design & Construction Manager Michael Costa - Project Director Carole Sanders - DB Oversight Manager
CP 2-3 HSR 13-57 40 8/8/2017 Dragados/Flatiron Joint Venture Environmental Increase in required BNLL Surveys $352,490.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to provide environmental surveys and reports for Blunt Nose Leopard Lizard on additional areas. Gladys Guzman - Acting Design & Construction Manager Michael Costa - Project Director Carole Sanders - DB Oversight Manager
CP 2-3 HSR 13-57 24.2 7/13/2017 Dragados/Flatiron Joint Venture Environmental Haz Mat Abatement, COP 88.5 - 3 Prop $98,208.59 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to remove hazardous materials at 3 sites. Gladys Guzman - Design & Construction Manager Michael Costa - Project Director Michael COsts - Project Director
CP 2-3 HSR 13-57 15 7/11/2017 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Early Start Design - 8 Bridges $1,094,775.39 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to provide proposals to accelerate work. Gladys Guzman - Design & Construction Manager Michael Costa - Project Director Carole Sanders - DB Oversight Manager
CP 2-3 HSR 13-57 38 7/11/2017 Dragados/Flatiron Joint Venture Environmental Early Work Environmental Re-Exam $218,788.21 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to complete environmental re-examination and permit amendments associated with advanced designs. Gladys Guzman - Design & Construction Manager Michael Costa - Project Director Carole Sanders - DB Oversight Manager
CP 2-3 HSR 13-57 33 7/7/2017 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Design Study for DL59, Dover & Silve $9,334.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to provide design drawings for 8th and Dover and Silveira property. Gladys Guzman - Design & Construction Manager Michael Costa - Project Director Carole Sanders - DB Oversight Manager
CP 2-3 HSR 13-57 39 7/7/2017 Dragados/Flatiron Joint Venture Environmental Bio Precon Surveys (ITP) for Geotech $200,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to provide biological pre-construction clearance surveys in accordance with the Authority's environmental commitments. Gladys Guzman - Design & Construction Manager Michael Costa - Project Director Charlie Guess, DB Oversight Manager
CP 2-3 HSR 13-57 32 7/3/2017 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Design Study for DL57, Elkhorn Ditch $35,739.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to provide design drawings for Elkhorn Ditch for an alternative route for the future high-speed rail system. Gladys Guzman for Jorge Granados - Design & Construction Manager Michael Costa - Project Director Charlie Guess, DB Oversight Manager
CP 2-3 HSR 13-57 37 7/3/2017 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Design Study, DL 60, Flood Property $4,927.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to provide design drawings for Flood Property. Gladys Guzman - Design & Construction Manager Michael Costa - Project Director Carole Sanders - DB Oversight Manager
CP 2-3 HSR 13-57 29.1 6/12/2017 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Dudek's Early Start Staffing $57,138.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to provide environmental services to accelerate the start of construction. Jorge Granados, P.E. - Design & Construction Manager Michael Costa - Project Director Charlie Guess, DB Oversight Manager
CP 2-3 HSR 13-57 24.1 5/24/2017 Dragados/Flatiron Joint Venture Environmental Haz Mat Abatement COP 88.3 and 88.4 $142,712.55 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to remove hazardous materials from a property acquired by the Authority. Jorge Granados - Design & Construction Manager Michael Costa - Project Director Charlie Guess - DB Oversight Manager
CP 2-3 HSR 13-57 36 5/10/2017 Dragados/Flatiron Joint Venture Utility Relocation Rescinded - PG&E Provisional Sum $253,715.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to provide management and support of activities to move PG&E facilities out of the way of the future high-speed rail system. Jorge Granados - Design & Construction Manager Michael Costa - Project Director Charlie Guess - DB Oversight Manager
CP 2-3 HSR 13-57 10.3 5/5/2017 Dragados/Flatiron Joint Venture Environmental Tulare Co Item 1.08 Road 24 Overlay $660,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to perform construction work on Road 24 to fulfil commitments made to Tulare County Jorge Granados, P.E. - Design & Construction Manager Michael Costa - Project Director Charlie Guess, DB Oversight Manager
CP 2-3 HSR 13-57 10.4 5/5/2017 Dragados/Flatiron Joint Venture Environmental Ave 24 - 4 Seasons Crossing Design $698,625.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to design Avenue 24 as a four-season undercrossing beneath the future high-speed rail system due to the high groud water in Tulare County. Jorge Granados, P.E. - Design & Construction Manager Michael Costa - Project Director Charlie Guess, DB Oversight Manager
CP 2-3 HSR 13-57 19 5/5/2017 Dragados/Flatiron Joint Venture Differing Site Conditions Adjust Design Grade for Subsidence $2,527,630.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to update the design to reflect new survey data. Terry Ogle - Director of Design & Construction Michael Costa - Project Director Charlie Guess, DB Oversight Manager
CP 2-3 HSR 13-57 27 5/5/2017 Dragados/Flatiron Joint Venture Right-of-Way (ROW) Related Utility Disconnects $2,700,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to disconnect utilities from structures planned for demolition. Terry Ogle - Director of Design & Construction Michael Costa - Project Director Charlie Guess, DB Oversight Manager
CP 2-3 HSR 13-57 28 5/5/2017 Dragados/Flatiron Joint Venture Changes to Plans and Specifications RAM Reporting and Analysis $1,200,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to provide plans, reports, manuals and tests related to the Reliability, Availability and Maintainability requirements. Jorge Granados, P.E. - Design & Construction Manager Michael Costa - Project Director Charlie Guess, DB Oversight Manager
CP 2-3 HSR 13-57 30 5/5/2017 Dragados/Flatiron Joint Venture Changes to Plans and Specifications DL 44.1 - Open Abutments Type 2 Stru $2,782,471.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to implement new design requirements for bridges over the future high-speed rail system. Terry Ogle - Director of Design & Construction Michael Costa - Project Director Charlie Guess, DB Oversight Manager
CP 2-3 HSR 13-57 31 4/26/2017 Dragados/Flatiron Joint Venture Environmental Inefficiency with using EMMA 1.0 $290,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to implement the Authority's environmental requirements tracking software. Jorge Granados, P.E. - Design & Construction Manager Michael Costa - Project Director Charlie Guess, DB Oversight Manager
CP 2-3 HSR 13-57 34 4/26/2017 Dragados/Flatiron Joint Venture Differing Site Conditions Unforseen Field Conditions T&M $150,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to address unexpected conditions. Jorge Granados, P.E. - Design & Construction Manager Michael Costa - Project Director Charlie Guess, DB Oversight Manager
CP 2-3 HSR 13-57 35 4/25/2017 Dragados/Flatiron Joint Venture Third-party Related Deductions for Caltrans IQA Design ($4,800,000.00) This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to amend the contract to remove the Caltrans quality assurance scope from the contractor and to give it to the Authority. Caltrans provide quality assurance on high-speed rail design affecting the state highway system. Terry Ogle - Director of Design & Construction Michael Costa - Project Director Charlie Guess, DB Oversight Manager
CP 2-3 HSR 13-57 26 3/8/2017 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Aesthetic Treatments on Type 1 Struc $560,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to provide consistent aesthetic treatment on future high-speed rail bridges to make them look the same as those bridges. Jorge Granados - Design & Construction Manager Michael Costa - Project Director Charlie Guess, DB Oversight Manager
CP 2-3 HSR 13-57 29 1/25/2017 Dragados/Flatiron Joint Venture Administrative DFJV Early Start Staffing $4,100,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to advance design to accelerate the start of construction activities. Terry Ogle - Director of Design & Construction Michael Costa - Project Director Charlie Guess, DB Oversight Manager
CP 2-3 HSR 13-57 20 1/24/2017 Dragados/Flatiron Joint Venture Changes to Plans and Specifications South Ave to Adams Clear and Grub $12,290.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to construct irrigation pipe protection in various locations where irrigation crosses the future high-speed rail system. Jorge Granados, P.E. - Design & Construction Manager Michael Costa - Project Director Charlie Guess, DB Oversight Manager
CP 2-3 HSR 13-57 23 12/22/2016 Dragados/Flatiron Joint Venture Environmental Reexam Fowler Elkhorn Clovis Davis $67,018.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to prepare additional environmental analysis at the Fowler, Elkhorn, Clovis and Davis bridges. Jorge Granados, P.E. - Design & Construction Manager Lloyd Neal, Project Manager Charlie Guess, DB Oversight Manager
CP 2-3 HSR 13-57 22 10/14/2016 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Storage of Foundation Piles $7,500.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to store construction elements prior to installation. Jorge Granados, P.E. - Design & Construction Manager Lloyd Neal, Project Manager Charlie Guess, DB Oversight Manager
CP 2-3 HSR 13-57 24 10/14/2016 Dragados/Flatiron Joint Venture Environmental Material Abatement COP 88,88.1,88.2 $528,610.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to remove hazardous materials at 26 sites. Jorge Granados, P.E. - Design & Construction Manager Lloyd Neal, Project Manager Charlie Guess, DB Oversight Manager
CP 2-3 HSR 13-57 10.2 9/26/2016 Dragados/Flatiron Joint Venture Environmental Tulare Co Landowner ROW (Design) $331,167.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to develop alternative design solutions to accommodate landowner facilities near Avenues 88 and 24. Jorge Granados, P.E. - Design & Construction Manager Lloyd Neal, Project Manager Charlie Guess, DB Oversight Manager
CP 2-3 HSR 13-57 17 9/26/2016 Dragados/Flatiron Joint Venture Third-party Related Jurisdictional Delineation $138,266.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to provide environmental work within the Kings River Complex of rivers. Jorge Granados, P.E. - Design & Construction Manager Lloyd Neal, Project Manager Charlie Guess, DB Oversight Manager
CP 2-3 HSR 13-57 18 9/26/2016 Dragados/Flatiron Joint Venture Third-party Related Washington IC, People's, Lakeside $117,662.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to provide plans for interpretive, educational materials and photography for Washington Irrigated Colony and Peoples Ditch as well as plants to screen the Lakeside Cemetery. Jorge Granados, P.E. - Design & Construction Manager Lloyd Neal, Project Manager Charlie Guess, DB Oversight Manager
CP 2-3 HSR 13-57 21 9/16/2016 Dragados/Flatiron Joint Venture Administrative Additional Allowable Stored Material $- This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to revise the Special Provisions section 8.2, Unincorporated Materials, to include a list of specific materials. Jorge Granados, P.E. - Design & Construction Manager Lloyd Neal, Project Manager Charlie Guess, DB Oversight Manager
CP 2-3 HSR 13-57 16 8/22/2016 Dragados/Flatiron Joint Venture Environmental Cultural Mitigation of Two Buildings $92,778.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to provide cultural mitigation evaluations of buildings in Fresno as part of the Authority's environmental commitments. Jorge Granados, P.E. - Design & Construction Manager Drew Erickson - Third Party Manager Charlie Guess, DB Oversight Manager
CP 2-3 HSR 13-57 13 8/15/2016 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Design CP 2-3 to meet CP1 profile $77,446.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to coordinate the design between Construction Package 1 and Construction Package 2-3 at the point where they meet. Jorge Granados, P.E. - Design & Construction Manager Lloyd Neal, Project Manager Charlie Guess, DB Oversight Manager
CP 2-3 HSR 13-57 10.1 7/18/2016 Dragados/Flatiron Joint Venture Environmental Tulare Co Overlay No. 1.09 $1,596,855.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to perform road construction work on Road 40 to fulfil commitments made to Tulare County. Jorge Granados, P.E. - Design & Construction Manager Lloyd Neal, Project Manager Charlie Guess, DB Oversight Manager
CP 2-3 HSR 13-57 14 6/30/2016 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Orthographic Photography $8,160.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to provide high resolution pictures and maps of the project area. Jorge Granados, P.E. - Design & Construction Manager Lloyd Neal, Project Manager Charlie Guess, DB Oversight Manager
CP 2-3 HSR 13-57 12 5/13/2016 Dragados/Flatiron Joint Venture Environmental Abatement of Hazardous Materials $456,905.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to remove hazardous materials at 13 properties owned by the Authority. Jorge Granados, P.E. - Design & Construction Manager Lloyd Neal, Project Manager Charlie Guess, DB Oversight Manager
CP 2-3 HSR 13-57 10 5/11/2016 Dragados/Flatiron Joint Venture Environmental Tulare County Agreement - Design $1,899,482.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to design and develop final construction cost estimates for Tulare County's requirements at 18 roads and associated land acquisition activities. Jorge Granados, P.E. - Design & Construction Manager Lloyd Neal, Project Manager Charlie Guess, DB Oversight Manager
CP 2-3 HSR 13-57 11 5/5/2016 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Start Bridge Construction $327,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to assess the potential risks and benefits associated with early bridge construction. This included assembling a team to review the Contract Baseline Schedule, design processes, permitting processes, Right-of-Way availability, attend briefings, prepare a cost estimate and schedule analysis, and present the findings and recommendations to Authority staff. Jorge Granados - Design & Construction Manager Lloyd Neal - Project Manager Charlie Guess - DB Oversight Manager
CP 2-3 HSR 13-57 9 5/4/2016 Dragados/Flatiron Joint Venture Differing Site Conditions Analysis of Subsidence Survey Data $20,954.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to prepare a digital terrain model. Jorge Granados - Design & Construction Manager Lloyd Neal - Project Manager Charlie Guess, DB Oversight Manager
CP 2-3 HSR 13-57 8 4/7/2016 Dragados/Flatiron Joint Venture Utility Relocation Evaluation of PG&E Provisional Sum $105,891.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to estimate the scale of work to move all PG&E facilities out of the way of the future high-speed rail system. Jorge Granados, P.E. - Design & Construction Manager Lloyd Neal, Project Manager Charlie Guess, DB Oversight Manager
CP 2-3 HSR 13-57 7 4/4/2016 Dragados/Flatiron Joint Venture Environmental Tribal Monitoring $130,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to conduct daily Tribal Monitoring during the Authority’s pre-construction phase. Jorge Granados, P.E. - Design & Construction Manager Lloyd Neal, Project Manager Charlie Guess, DB Oversight Manager
CP 2-3 HSR 13-57 4.1 3/23/2016 Dragados/Flatiron Joint Venture Right-of-Way (ROW) Related Supplemental ROW Delineators $2,932.50 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to buy, install and maintain more poles to show the limit of property bought by the Authority. Jorge Granados, P.E. - Design & Construction Manager Lloyd Neal, Project Manager Charlie Guess, DB Oversight Manager
CP 2-3 HSR 13-57 4 3/1/2016 Dragados/Flatiron Joint Venture Right-of-Way (ROW) Related Right-of-Way Delineators $107,467.50 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to buy, install and maintain poles to show the limit of property bought by the Authority. Jorge Granados, P.E. - Design & Construction Manager Lloyd Neal, Project Manager Charlie Guess, DB Oversight Manager
CP 2-3 HSR 13-57 5 1/29/2016 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Subsidence Survey $335,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to survey the gradual caving in or sinking of an area of land (subsidence). This scope of work includes data collection, planning and reporting with remote sensing technology (LIDAR). Jorge Granados, P.E. - Design & Construction Manager Lloyd Neal, Project Manager Charlie Guess, DB Oversight Manager
CP 2-3 HSR 13-57 2 1/4/2016 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Hormel Feed Mill Alignment Study $29,963.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to re-design the route of the future high-speed rail system to avoid the Hormel Feed Mill. Jorge Granados, P.E. - Design & Construction Manager Lloyd Neal, Project Manager Charlie Guess, DB Oversight Manager
CP 2-3 HSR 13-57 3 11/12/2015 Dragados/Flatiron Joint Venture Changes to Plans and Specifications Early Start Analysis Staff $120,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is the addition of two contractor management staff to assist the Authority in evaluating the effort needed to start early construction. Jorge Granados, P.E. - Design & Construction Manager Lloyd Neal, Project Manager Charlie Guess, DB Oversight Manager
CP 2-3 HSR 13-57 1 7/31/2015 Dragados/Flatiron Joint Venture Administrative Partnering & DRB $270,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to account for the partnering and Dispute Resolution Board (DRB)expenses the Authority shares with the contractor. The Authority is responsible for 50% of the Partnering and DRB costs over the planned four year duration. Jorge Granados, P.E. - Design & Construction Manager Lloyd Neal, Project Manager Charlie Guess, DB Oversight Manager
CP 4 HSR 14-32 56 5/29/2020 California Rail Builders Third-Party Related So Cal Gas (Sempra) Additional Costs $9,798,912.00 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to finalize negotiations of a dispute regarding So Cal Gas (Sempra) work. Joe Hedges Antonio Canate Berenguer R. Kennah
CP 4 HSR 14-32 18 R4 5/19/2020 California Rail Builders Environmental Add'l Survey & Investigation $2,147,556.20 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to increase the Not-to-Exceed (NTE) amount of Change Order 18, executed on June 19,2017 for $400,000, previously increased under Change Order 18R2 executed on May 2, 2018 by $700,000, by Change Order 18R3 executed on Dec. 3, 2019 for $1,875,000 and by this CO for $2,147,556.20 to $5,122,556.20. The reason for change order number 18 is a delay in the release of land to the general contractor to begin construction. Joe Hedges Antonio Canate Berenguer R. Kennah
CP 4 HSR 14-32 55 4/21/2020 California Rail Builders Roadway Modifications Peterson Road Bridge Extension Mitigation Measure $4,998,981.43 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to redesign and construct an extension to the previously planned bridge at Peterson Road in Wasco, California. Elias Mahfoud Antonio Canate Berenguer R. Kennah
CP 4 HSR 14-32 39 R2 3/5/2020 California Rail Builders Track Structure: At-grade track IPB Remaining Berm Viaduct Mod Const $15,872,287.58 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to initiate construction of a portion of the Intrusion Protection Barrier berm on the project. Joe Hedges Antonio Canate Berenguer R. Kennah
CP 4 HSR 14-32 53 2/28/2020 California Rail Builders Environmental Removal of Two Underground Storage Tank's and Two Concrete Vaults at G Street $71,211.60 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to compensate for the removal of underground facilities tanks in Wasco, California. Elias Mahfoud Antonio Canate Berenguer R. Kennah
CP 4 HSR 14-32 51 2/27/2020 California Rail Builders Environmental Claim Settlement for DL-00058 Dedicated Wildlife Crossing $11,938,500.00 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to pay California Rail Builders for the installation of Dedicated Wildlife Crossings on the project. Joe Hedges Antonio Canate Berenguer R. Kennah
CP 4 HSR 14-32 52 2/18/2020 California Rail Builders Roadway Modifications Merced CIDH Piling Resequencing $121,364.75 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to pay California Rail Builders for mitigation costs due to PG&E delays. Elias Mahfoud Antonio Canate Berenguer R. Kennah
CP 4 HSR 14-32 11 R1 2/18/2020 California Rail Builders Contract Upgraded Site Office Internet Bandwidth $41,275.08 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to increase internet speed for the Authority's utilization.This Change Order shall fully compensate California Rail Builders (CRB) to provide an upgrade the Authority’s Wasco Office internet from 10 Mbps to 20 Mbps internet connection with fiber optic. Elias Mahfoud Antonio Canate Berenguer R. Kennah
CP 4 HSR 14-32 50 1/14/2020 California Rail Builders Environmental Mitigation Costs Reimbusement for Zones 12-15 $1,914,162.87 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to pay California Rail Builders for mitigation costs due to right-of-way acquisition delay in Wasco. Elias Mahfoud Antonio Canate Berenguer R. Kennah
CP 4 HSR 14-32 49 12/10/2019 California Rail Builders Site Utiltiies Relocation Water Service at Parcel FB-15-00-28 $83,978.62 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to install a 24-inch casing and 12-inch PVC water line to enable existing water service restoration to a parcel in Wasco. Elias Mahfoud Antonio Canate Berenguer R. Kennah
CP 4 HSR 14-32 39 R1 12/10/2019 California Rail Builders Track Structure: At-grade track IBP Last Mile $13,977,559.30 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to initiate construction of a portion of the Intrusion Protection Barrier berm on the project. Joe Hedges Antonio Canate Berenguer R. Kennah
CP 4 HSR 14-32 48 12/4/2019 California Rail Builders Changes to Plans and Specifications Kimberlina CIDH Piling Work Resequencing $265,860.94 This is a change to a contract for design and construction services in the Central Valley. The reasons for the change is to move the pile drilling operation twice to install and remove additional CMP liners at Kimberlina Abutment 2. Elias Mahfoud - State Senior Construction Manager Antonio Canete - Project Director and CEO of CRB Robert Kennah - DB Oversight Manager
CP 4 HSR 14-32 18 R3 12/3/2019 California Rail Builders Environmental Additional Environmental Surveys and Investigations $1,875,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to increase the Not-to-Exceed (NTE) amount of Change Order 18, executed on June 19,2017 for $400,000 and previously increased under Change Order 18R2 executed on May 2, 2018 by $700,000. The NTE ceiling is now increased by $1,875,000 to $2,875,000. The reason for change order number 18 is a delay in the release of land to the general contractor to begin construction. Elias Mahfoud - State Senior Construction Manager Antonio Canete - Project Director and CEO of CRB Robert Kennah - DB Oversight Manager
CP 4 HSR 14-32 47 11/22/2019 California Rail Builders Utility Relocation Sempra Relocation at State Route 46 Conflict 10003 Design $459,722.86 This is a change to a contract for design services in the Central Valley. The reason for the change is to fully compensate California Rail Builders for the design of the relocation of utility conflict #10003, a gas line at State Route 46 owned by Sempra Energy, (“Sempra”, also known as SoCalGas). Elias Mahfoud - State Senior Construction Manager Antonio Canete - Project Director and CEO of CRB Robert Kennah - DB Oversight Manager
CP 4 HSR 14-32 46 11/5/2019 California Rail Builders Right-of-Way (ROW) Related Mitigation Cost Reimburse Zones 1-5 $2,800,000.00 This is a change to a contract for construction services in the Central Valley. The reason for the change is mitigation costs incurred due to the delay in right-of-way (ROW) acquisition in the north area of CP-4 (Zones 1-5). Elias Mahfoud - State Senior Construction Manager Antonio Canete - Project Director and CEO of CRB Robert Kennah - DB Oversight Manager
CP 4 HSR 14-32 45 10/28/2019 California Rail Builders Changes to Plans and Specifications Intrusion Protection Barrier Design Modifications $1,300,000.00 This is a change to a contract for design services in the Central Valley. The reason for the change is required design revisions due to updates to the Intrusion Protection Barrier standards ordered under Directive Letters (DL) 0007, 0024, 0024R1, 0024R3, and 0024R4. Elias Mahfoud - State Senior Construction Manager Antonio Canete - Project Director and CEO of CRB Robert Kennah - DB Oversight Manager
CP 4 HSR 14-32 44 10/8/2019 California Rail Builders Changes to Plans and Specifications Work Separation of HSR Alignment from State Route 46 at BNSF Crossing $68,821.33 This is a change to a contract for design and construction services in the Central Valley. This reason for the change is to fully compensate the Contractor for work performed under Directive Letter (DL)-00054 of April 8, 2019, Separation of Work of HSR Alignment form SR 46 at BNSF Crossing. This work includes evaluations of conceptual options to resolve the conflict between the current BSNF shoofly design at SR 46 and the requirement of DL-00054 to finish the construction of the HSR Alignment by the Substantial Completion Date and then complete the other work of SR 46 at BNSF Crossing at a date to be determined. Elias Mahfoud - State Senior Construction Manager Antonio Canete - Project Director and CEO of CRB Robert Kennah - DB Oversight Manager
CP 4 HSR 14-32 43 10/8/2019 California Rail Builders Right-of-Way (ROW) Related Landowner Reimbursement $125,688.67 This is a change to a contract for construction services in the Central Valley. The reason for the change is to compensate California Rail Builders to make an immediate payment to Mr. Steve Brock of Land Value Farms, Fresno, California. This payment is for modifications to the farm’s irrigation system made and paid for by Mr. Brock to accommodate the CP-4 and are reimbursable to Mr. Brock and Land Value Farms by the Authority. Elias Mahfoud - State Senior Construction Manager Antonio Canete - Project Director and CEO of CRB Robert Kennah - DB Oversight Manager
CP 4 HSR 14-32 42 10/3/2019 California Rail Builders Changes to Plans and Specifications Resume Original Merced Avenue Alignment Design $601,641.77 This is a change to a contract for design services in the Central Valley. The reason for the change is to fully compensate California Rail Builders to cease all design work for the Merced Avenue Overhead and Roadway Realignment as defined in Directive Letter (DL) DL-00025, DL-00025R1, and Change Order (CO) CO-00021, and to resume and complete the design work for the original Contract alignment. Elias Mahfoud - State Senior Construction Manager Antonio Canete - Project Director and CEO of CRB Robert Kennah - DB Oversight Manager
CP 4 HSR 14-32 41 9/24/2019 California Rail Builders Changes to Plans and Specifications Revise Realignment of Canal 9-22 Design $180,657.04 This is a change to a contract for design services in the Central Valley. The reason for the change is to fully compensate California Rail Builders to revise the design of the realignment of Canal 922. Elias Mahfoud - State Senior Construction Manager Antonio Canete - Project Director and CEO of CRB Robert Kennah - DB Oversight Manager
CP 4 HSR 14-32 39 8/29/2019 California Rail Builders Changes to Plans and Specifications IPB Last Mile $5,500,000.00 This is a change to a contract for design and construction services in the Central Valley. The change order is to construct a protective barrier to separate the high-speed rail alignment from the adjacent freight railroad as modified by the Authority’s Directive Letter 24R3. Joe Hedges - Chief Operating Officer Antonio Canete - Project Director and CEO Stephen Lowry - Design-Build Oversignt Manager
CP 4 HSR 14-32 27 R1 8/28/2019 California Rail Builders Utility Relocation Design SR-46 Pumping Station to RFC $242,102.40 This is a change to a contract for design and construction services in the Central Valley. The change order is to design a replacement for the Caltrans pumping station at State Route 46 to move it out of the way of the high-speed rail alignment. Elias Mahfoud - Senior State Contract Manager Antonio Canete - Project Director and CEO Stephen Lowry - Design-Build Oversignt Manager
CP 4 HSR 14-32 40 8/26/2019 California Rail Builders Utility Relocation Un-ID'd Frontier Utility Conflicts $25,879.00 This is a change to a contract for design and construction services in the Central Valley. The change order moves Frontier Communications facilities out of the way of the high-speed rail alignment. Elias Mahfoud - Senior State Contract Manager Antonio Canete - Project Director and CEO Stephen Lowry - Design-Build Oversignt Manager
CP 4 HSR 14-32 38 8/15/2019 California Rail Builders Changes to Plans and Specifications CO 38 BNSF Access Roads $3,717,579.65 This is a change to a contract for design and construction services in the Central Valley. The change order is to design and construct BNSF access roads where access is impacted by the high-speed rail project. Elias Mahfoud - Senior State Contract Manager Antonio Canete - Project Director and CEO Stephen Lowry - Design-Build Oversignt Manager
CP 4 HSR 14-32 35 8/6/2019 California Rail Builders Environmental CO 35 Reimburse Specific CDFW Fees $73,053.62 This is a change to a contract for design and construction services in the Central Valley. The change order allows for the acquisition of the required environmental permits for construction at 5 locations on the high-speed rail right of way. Elias Mahfoud - Senior State Contract Manager Antonio Canete - Project Director and CEO Mike Barbour - Design-Build Oversignt Manager
CP 4 HSR 14-32 37 7/25/2019 California Rail Builders Utility Relocation SoCal Edison Relocation at Peterson Road $324,862.51 This is a change to a contract for design and construction services in the Central Valley. The change order moves Edison Overhead Distribution line out of the way of the future high-speed rail system at Peterson Road in Kern County. Elias Mahfoud - Senior State Contract Manager Antonio Canete - Project Director and CEO Mike Barbour - Design-Build Oversignt Manager
CP 4 HSR 14-32 36 7/25/2019 California Rail Builders Third-party Related City of Wasco Additional Utility Casings-Increase Amount $4,998,220.99 This is a change to a contract for design and construction services in the Central Valley. The change order pays for installation of 9 utility casings and design of 1 utility casing for the City of Wasco. Elias Mahfoud - Senior State Contract Manager Antonio Canete - Project Director and CEO Mike Barbour - Design-Build Oversignt Manager
CP 4 HSR 14-32 34 5/20/2019 California Rail Builders Differing Site Conditions City of Wasco Well #13 Test Well $297,900.28 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to pay the City of Wasco, the local governing body, to move its services out of the way of the future high-speed rail system. This work is coordinated by the general contractor in Wasco responsible for designing and constructing the future high-speed rail system. Elias Mahfoud Antonio Canete, Project Director and CEO of CRP Mike Barbour, Design-Build Oversight Manager
CP 4 HSR 14-32 33 3/21/2019 California Rail Builders Administrative CO 33 Un-ID Frontier Con 2000-2002 $190,962.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to pay Frontier Communications, a telecomunications company, to move its services out of the way of the future high-speed rail system. This work is coordinated by the general contractor in Wasco responsible for designing and constructing the future system. William Grimsley, Acting Director of Design & Construction Antonio Canete, Project Director and CEO of CRP Mike Barbour, Design-Build Oversight Manager
CP 4 HSR 14-32 32 3/4/2019 California Rail Builders Dispute Resolution CO 32 Settlement/ Release/Wavier $40,459,152.00 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is to account for delays caused by the Authority from the start of work until January 31, 2019. This change order allows the general contractor more time and additional budget to complete the delayed work (as documented in Time Impact Analyses 1 through 5). In addition to the additional budget, a contract extension of 525 working days was given to the contractor. Joe Hedges - Chief Operating Officer Antonio Canete - Project Directo and CEO of CRB Mike Barbour - Design-Build Oversight Manager
CP 4 HSR 14-32 28 2/8/2019 California Rail Builders Dispute Resolution CO 28 Dispute Review-Executive $- This is a change to a contract for construction services in the Central Valley. This change eliminates the Dipute Resolution Board from the dispute resolution procedures. The reason for the change is to improve dispute resolution process. Joe Hedges, Chief Operating Officer Antonio Canete, Project Director and CEO of CRP Mike Barbour, Design-Build Oversight Manager
CP 4 HSR 14-32 30 11/28/2018 California Rail Builders Environmental CO 30 BNSF ROE Permits Renewal-2018 $17,988.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to secure permits to enter BNSF proprety to conduct work. William Grimsley - Director of Design & Construction Antonio Canete - Project Directo and CEO of CRB Mike Barbour - Design-Build Oversight Manager
CP 4 HSR 14-32 29 10/31/2018 California Rail Builders Dispute Resolution CO 29 Privately-Own Irrigation Line $1,819,676.47 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to relocate private irrigation lines to move them out of the way of the future high-speed rail system. William Grimsley - Director of Design & Construction Antonio Canete - Project Directo and CEO of CRB Mike Barbour - Design-Build Oversight Manager
CP 4 HSR 14-32 27 9/5/2018 California Rail Builders Third-party Related CO 27 SR46 @ BNSF Crossing Design $1,158,550.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to design the BNSF bridge at State Route 46 and the State Route 46 roadway. Terry Ogle - Director of Design & Construction Antonio Canete - Project Directo and CEO of CRB Mike Barbour - Design-Build Oversight Manager
CP 4 HSR 14-32 18 R2 6/26/2018 California Rail Builders Environmental CO 18R2 Enviro Surveys & Invest R2 $700,000.00 This is a change to a contract for design and construction services in the Central Valley. This is a supplemental to change order number 18 to increase the cost for the work by an additional $700,000 taking the total to $1,100,000. The reason for change order number 18 is a delay in the release of land to the general contractor to begin construction. Terry Ogle - Director of Design & Construction Antonio Canete - Project Directo and CEO of CRB Mike Barbour - Design-Build Oversight Manager
CP 4 HSR 14-32 26 6/21/2018 California Rail Builders Third-party Related CO 26 Pile Rig Standby Costs $171,200.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to conduct pile load tests and to pay for unused equipment due to lack of land on which to conduct the tests. Terry Ogle - Director of Design & Construction Antonio Canete - Project Directo and CEO of CRB Mike Barbour - Design-Build Oversight Manager
CP 4 HSR 14-32 25 6/21/2018 California Rail Builders Third-party Related CO 25 Kimberlina Crossing @BNSF&SR43 $- This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to incorporate the revised design to the Kimberlina Avenue crossing. Terry Ogle - Director of Design & Construction Antonio Canete - Project Directo and CEO of CRB Mike Barbour - Design-Build Oversight Manager
CP 4 HSR 14-32 24 5/9/2018 California Rail Builders Administrative CO 24 MultiMonth Schedule 12/17-3/18 $- This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to revise the requirements for updates to the schedule from December 2017 through March 2018. Terry Ogle - Director of Design & Construction Antonio Canete - Project Directo and CEO of CRB Mike Barbour - Design-Build Oversight Manager
CP 4 HSR 14-32 23 4/17/2018 California Rail Builders Third-party Related CO 23 Caltrans Reimbursement ($3,530,000.00) This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to implement the agreement between the Authority and Caltrans for Caltrans to bill their services on the project directly to the Authority. This change order provides the Authority a credit for removing these activities from the contract. Terry Ogle - Director of Design & Construction Antonio Canete - Project Directo and CEO of CRB Mike Barbour - Design-Build Oversight Manager
CP 4 HSR 14-32 22 1/31/2018 California Rail Builders Third-party Related CO 22 BNSF ROE Insurance Renewal $26,165.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to extend insurance policies required by BNSF for entry onto their property. Terry Ogle - Director of Design & Construction Antonio Canete - Project Directo and CEO of CRB Mike Barbour - Design-Build Oversight Manager
CP 4 HSR 14-32 21 1/31/2018 California Rail Builders Third-party Related CO 21 Merced Ave Realignment Design $300,199.06 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to design a bridge alternative at the Merced Avenue overpass. Terry Ogle - Director of Design & Construction Antonio Canete - Project Directo and CEO of CRB Mike Barbour - Design-Build Oversight Manager
CP 4 HSR 14-32 20 8/15/2017 California Rail Builders Changes to Plans and Specifications CO 20 Ductbank Ext. to System Site $296,356.31 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to construct underground duct banks for the future high-speed rail system. Benjamin Camarena - Design & Construction Manager Antonio Canete - Project Directo and CEO of CRB Mike Barbour - Design-Build Oversight Manager
CP 4 HSR 14-32 19 7/31/2017 California Rail Builders Administrative CO 19 McCombs Avenue Options Study $40,732.72 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to study three options for the design at McCombs Avenue. Benjamin Camarena - Design & Construction Manager Antonio Canete - Project Directo and CEO of CRB Mike Barbour - Design-Build Oversight Manager
CP 4 HSR 14-32 12 6/20/2017 California Rail Builders Differing Site Conditions CO 12 Prelim Enviro&Geotech Inv Work $100,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to complete the remaining environmental and geotechnical investigations. Benjamin Camarena - Design & Construction Manager Antonio Canete - Project Directo and CEO of CRB Claudio Dallavalle - Design-Build Oversight Manager
CP 4 HSR 14-32 18 6/1/2017 California Rail Builders Differing Site Conditions CO 18 Add'l Survey & Investigation $400,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for this change is a delay in the release of land to the general contractor to begin construction. Benjamin Camarena - Design & Construction Manager Antonio Canete - Project Directo and CEO of CRB Claudio Dallavalle - Design-Build Oversight Manager
CP 4 HSR 14-32 15 5/15/2017 California Rail Builders Right-of-Way (ROW) Related CO 15 ROW Delay Notices & TIA Sub. $- This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to clarify the Right-of-Way delay notification and time impact analysis processes in the contract. Terry Ogle - Director of Design & Construction Antonio Canete - Project Directo and CEO of CRB Claudio Dallavalle - Design-Build Oversight Manager
CP 4 HSR 14-32 13 4/13/2017 California Rail Builders Administrative CO 13 Multimonth Progress Updates $- This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to revise the requirements for updates to the schedule to bring the schedule baseline up to date. Benjamin Camarena - Design & Construction Manager Antonio Canete - Project Directo and CEO of CRB Claudio Dallavalle - Design-Build Oversight Manager
CP 4 HSR 14-32 11 3/17/2017 California Rail Builders Administrative CO 11 Authority Wasco Internet Upgra $32,492.88 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to install an internet connection to the Authority office in Wasco. Benjamin Camarena - Design & Construction Manager Antonio Canete - Project Directo and CEO of CRB Claudio Dallavalle - Design-Build Oversight Manager
CP 4 HSR 14-32 10 2/17/2017 California Rail Builders Administrative CO 10 Admin Correction to CO No. 02 $- This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to correct an error on change order number 2. Terry Ogle - Director of Design & Construction Antonio Canete - Project Directo and CEO of CRB Claudio Dallavalle - Design-Build Oversight Manager
CP 4 HSR 14-32 9 2/7/2017 California Rail Builders Third-party Related CO 9 Additional BNSF Insurance $3,450.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to obtain right of entry permits from BNSF. Terry Ogle - Director of Design & Construction Antonio Canete - Project Director and CEO of CRB Claudio Dallavalle - PCM Oversight Manager
CP 4 HSR 14-32 8 1/17/2017 California Rail Builders Third-party Related CO 8 Partnering Services-Ongoing $237,150.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to establish a fund for partnering costs, which are shared between the Authority and the contractor. Terry Ogle - Director of Design & Construction Antonio Canete - Project Director and CEO of CRB Claudio Dallavalle - PCM Oversight Manager
CP 4 HSR 14-32 7 11/14/2016 California Rail Builders Dispute Resolution CO 7 Disputes Resolution Board $250,000.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to establish a fund for the Dispute Resolution Board and dispute resolution training. Costs are shared between the Authority and the contractor. Terry Ogle - Director of Design & Construction Antonio Canete - Project Director and CEO of CRB Claudio Dallavalle - PCM Oversight Manager
CP 4 HSR 14-32 6 10/17/2016 California Rail Builders Third-party Related CO 6 Partnering Services $9,900.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to conduct partnering workshops between the Authority and the contractor. Terry Ogle - Director of Design & Construction Antonio Canete - Project Director and CEO of CRB Claudio Dallavalle - PCM Oversight Manager
CP 4 HSR 14-32 2 8/22/2016 California Rail Builders Dispute Resolution CO 2 Tribal Monitoring $74,557.60 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to conduct tribal monitoring as part of the Authrities environmental requirements. Terry Ogle - Director of Design & Construction Antonio Canete - Project Director and CEO of CRB Claudio Dallavalle - PCM Oversight Manager
CP 4 HSR 14-32 5 8/12/2016 California Rail Builders Administrative CO 5 Addition of Griffith to Bonds $- This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to modify the contract with Griffith Company becoming a 20% member of the general contractor. Terry Ogle - Director of Design & Construction Antonio Canete - Project Director and CEO of CRB Claudio Dallavalle - PCM Oversight Manager
CP 4 HSR 14-32 4 7/19/2016 California Rail Builders Dispute Resolution CO4 BNSF Timeframe Clarification $- This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to record a new commitment regarding work to be completed by BNSF from 24 to 12 months. Terry Ogle - Director of Design & Construction Antonio Canete - Project Director and CEO of CRB Claudio Dallavalle - PCM Oversight Manager
CP 4 HSR 14-32 3 7/19/2016 California Rail Builders Administrative CO3 Form I Update $- This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to modify the contract based on updated data regarding bonding, insurance and mobilization costs. Terry Ogle - Director of Design & Construction Antonio Canete - Project Director and CEO of CRB Claudio Dallavalle - PCM Oversight Manager
CP 4 HSR 14-32 1 3/24/2016 California Rail Builders Third-party Related CO 1 Bonding and Insurance Increase $1,359,570.00 This is a change to a contract for design and construction services in the Central Valley. The reason for the change is to cover increases in bonding and insurance costs associated with an increase in work related to moving public utilities out of the way of the future high-speed rail system. Terry Ogle - Director of Design & Construction Jose Baraja - Authorized Representative Claudio Dallavalle - PCM Oversight Manager