Federal Grants

Federal Grants

Securing large new federal grants is a necessary and critical step to achieve the California High-Speed Rail Authority’s (Authority) goal of delivering high-speed passenger rail by 2030. Bipartisan Infrastructure Law (BIL) grant opportunities of more than $75 billion have been identified, making significant funding available for projects like high-speed rail to compete for.

The Authority is uniquely positioned to immediately deploy new federal funding investments that will supplement current state funds toward the delivery of the initial high-speed rail line between Merced and Bakersfield and to advance design on crucial segments in both Northern and Southern California.

The Authority will continue to submit multiple federal grant applications annually over the 5-year BIL program with a total award target of $8 billion. If funding is provided at this level, the federal share would increase to between 35 and 37%.

Recent Federal Investment

Over the last few years, the Authority has received $69 million in funding from three Rebuilding American Infrastructure with Sustainability and Equity (RAISE) grants, almost $202 million from the Consolidated Rail Infrastructure and Safety Improvements (CRISI) grant program and nearly $3.1 billion from the Federal-State Partnership for Intercity Passenger Rail Program, totaling over $3.3 billion. Further detail on these grants is included in the table below.

Early Federal Investment

The Authority received approximately $3.5 billion in federal funding commitments to complete environmental review for the Phase 1 system and to construct the 119-mile Central Valley Segment between Madera and Poplar Avenue.

Of this:

  • $2.5 billion was from the federal American Recovery and Reinvestment Act of 2009 (ARRA) and;
  • $929 million was appropriated by Congress from Fiscal Year 2010 (FY10) Transportation, Housing and Urban Development funds.

These funds were awarded by the Federal Railroad Administration (FRA) through federal grants. This partnership was instrumental in enabling the Authority to advance the program into construction. The $2.5 billion in ARRA funding was fully expended before the statutory deadline and in compliance with the FRA grant requirement. In January 2022, the FRA fully approved the Authority’s state match, about 12 months ahead of the deadline.

Per the terms of the federal grant agreement, the $929 million of FY10 funds, along with $360 million of state matching funds, are scheduled to be the last funding required to complete the federal grant scope of work.

More on these grants can be found on our Capital Costs and Funding page.

The chart below highlights federal grant funding awarded and pending to date.

Grant ProgramDateAmountScope
AWARDED
ARRAAwarded
2009
$2.5BThe ARRA grant provided HSR with $2.5 billion in federal funding, which was fully expended by the statutory deadline of October 2017. In January 2022, the Authority achieved its state match requirement ($2.5 billion), approximately one year ahead of schedule.
FY10Awarded
2010
$929MThe FY10 grant provides the Authority with $929 million and has state match requirement of $360 million. The period of performance under the grant is through 2026 with planned expenditures to start in the summer of 2024.
BrownfieldsAwarded
August 2017
$600KThe Brownfields EPA grant targeted Project Development work in the Los Angeles-Anaheim region. This grant was closed out with all tasks and deliverables met in March 2023.
RAISEAwarded
November 2021
$24M (Grant Awarded)

$84M (Total Project Cost)
The grant was awarded to fund crucial safety, efficiency, and construction projects in and around the City of Wasco.
RAISEAwarded
August 2022
$25M (Grant Awarded)

$41M (Total Project Cost)
This grant was awarded to fund design for the Merced Extension of the California High-Speed Rail project. The project will design civil infrastructure, track and systems and station platforms from Madera to Merced.
RAISEAwarded
June 2023
$20M (Grant Awarded)

$33M (Total Project Cost)
This grant was awarded to fund the Fresno Historic Depot Renovation and Plaza Activation Project, and to integrate zero emissions vehicle infrastructure into historically disadvantaged communities.
CRISIAwarded
September 2023
$202M (Grant Awarded)

$292M (Total Project Cost)
This grant was awarded to fund complete design, purchase right-or-way and construct six grade separations in the city of Shafter.
Corridor IdentificationAwarded
December 2023
No monetary request, but acceptance into the program came with $500,000Acceptance into this program included California High-Speed Rail in the National Rail Network.
Federal-State PartnershipAwarded
December 2023
$3.073B (Grant Awarded)

$3.842 B (Total Project Cost)
Inaugural High-Speed Service:

  • Procure 6 electric trainsets for testing and use

  • Fund design and construction of trainset facilities

  • Fund design and construction of the Fresno station

  • Fund final design and right-of-way acquisition for the Merced and the Bakersfield extensions

  • Construction, including track and systems, for the Merced-Bakersfield Initial Operating Segment

APPLIED FOR
GRIPSubmitted
April 17, 2024
$60.2M (Applied)

$120.4M (Total Project Cost)
The Grid-Optimal Infrastructure Project will deploy behind-themeter solar photovoltaic (PV) energy generation to:

  • Serve four Traction Power Substations (TPSS)

  • A battery energy storage system (BESS)

  • Controls to form a resilient, clean energy Microgrid around each TPSS and station-adjacent district
MegaSubmitted
May 2024
$236.1M (Applied)

$393.5M (Total Project Cost)
This grant for the Merced Integrated Multimodal Station would fund final design for all the following:

  • Canopies and platforms, including a center platform to allow seamless transfers

  • Elevators, escalators and concourses;
    Functional and operational spaces, including crew space

  • Electric vehicle charging and transit facilities (including bus stops)

  • Parking (ADA, bike, automobile), solar facilities and pick-up and drop-off areas

  • Station access, landscaping and sustainable stormwater management
CRISISubmitted
May 2024
$450M (Applied)

$562M (Total Project Cost)
The grant will advance the Merced Extension element of the Inaugural High-Speed Service from Merced to Bakersfield, a crucial part of the California High-Speed Rail Phase 1 Corridor.

  • $446 million is requested to construct the first eight (8) miles of the extension from Madera to Merced (the Project). The Project includes utility relocation, civil construction, track and systems that will connect with the 119-mile Central Valley
    Segment already under construction

  • $4 million is requested to continue funding for existing pre-apprenticeship training programs and expand to new programs to further support construction of the Project and all elements of high-speed rail in the region

The California High-Speed Rail Authority makes every effort to ensure the website and its contents meet mandated ADA requirements as per the California State mandated Web Content Accessibility Guidelines 2.0 Level AA standard. If you are looking for a particular document not located on the California High-Speed Rail Authority website, you may make a request for the document under the Public Records Act through the Public Records Act page. If you have any questions about the website or its contents, please contact the Authority at info@hsr.ca.gov.